‫دورة تدر یب ا�هندس ‪2‬‬

‫‪PRIMAVERA P6‬‬
TABLEAU DE CONTENU

TABLEAU DE CONTENU
LE TITRE _________________________________________________________________PAGE

1.LES DONNÉES DU PROJET _____________________________________________1

2.LES PARAMÈTRES DU PROJET ___________________________________________4

3.LES PARAMÈTRES DU PRIMAVERA ________________________________________6

A.LE DEVIS _________________________________________________________________ 6

B.LES CATÉGORIES DE L'ADMINISTRATEUR___________________________________________ 6

4.L'INTERFACE DU PRIMAVERA ___________________________________________6

5.LA LANGUE D'AFFICHAGE ______________________________________________8

6.LES PARAMÈTRES DU DEVIS ____________________________________________8

7.LES PRÉFÉRENCES DE L'UTILISATEUR _____________________________________8

8.LES PARAMÈTRES DE L'ADMINISTRATEUR __________________________________ 10

A.LES CALENDRIERS _________________________________________________________ 10

B.LES PRÉFÉRENCES DE L'ADMINISTRATEUR_________________________________________ 11

C.LES CATÉGORIES DE L'ADMINISTRATEUR _________________________________________ 12

9.LA HIÉRARCHISATION PAR OBS. ________________________________________ 12

10.LA STRUCTURATION DE L'ENTREPRISE ___________________________________ 13

11.LES CODES ______________________________________________________ 13

A.LES CODES DES PROJETS ____________________________________________________ 13

B.LES CODES DES TACHES _____________________________________________________ 14

C.LES CODES DES RESSOURCES _________________________________________________ 15

12.LE DICTIONNAIRE DES RESSOURCES_____________________________________ 17

13.LES CENTRES DE FRAIS ______________________________________________ 21

14.LA CRÉATION DU PROJET ____________________________________________ 21

2 ‫دورة تدریب ا�هندس‬


TABLEAU DE CONTENU
15.EXPLICATION _____________________________________________________ 24

A.ACTIVITY TYPE ___________________________________________________________ 24

B.ACTIVITY DURATION TYPE ___________________________________________________ 24

C.ACTIVITY % COMPLETE TYPE__________________________________________________ 26

16.ENREGISTRER ET EXPORTER PROJECT LAY-OUT ___________________________ 26

17.LA DOCUMENTATION DU PROJET ______________________________________ 27

18.LE DÉCOUPAGE DU PROJET PAR WBS ___________________________________ 29

19.L'INSERTION DES ACTIVITÉS __________________________________________ 31

20.PLANIFIER LE PROJET ______________________________________________ 38

21.NIVELER LES RESSOURCES ___________________________________________ 39

22.LES STATISTIQUES DU PROJET PAR TACHES_______________________________ 42

23.PARAMÈTRES DIVERS _______________________________________________ 44

24.LE PLANNING DE REFERENCE _________________________________________ 45

25.L'ACTUALISATION MANUELLE DU PLANNING_______________________________ 49

26.L'ACTUALISATION AUTOMATIQUE DU PLANNING ___________________________ 50

A.APPLIQUER LES VALEURS RÉELLES ______________________________________________ 50

B.METTRE A JOUR DE LA PROGRESSION ___________________________________________ 52

27.LA VALEUR ACQUISE _______________________________________________ 55

28.LA PRÉSENTATION DES RÉSULTATS _____________________________________ 57

29.EXERCICE _______________________________________________________ 59

30.REPORTING ET COMMUNICATION DES DONNÉES ____________________________ 63

A.LES RAPPORTS____________________________________________________________ 63
I.LE PROJET EN CHIFFRE______________________________________________________ 63
II.LE BUDGET DES TACHES ____________________________________________________ 65
III.LA LISTE DES RESSOURCES __________________________________________________ 68
IV.LA LISTE DES DÉPENSES ____________________________________________________ 70
V.LE CALENDRIER DES PAYEMENTS ______________________________________________ 71

B.IMPRESSION DES LAY-OUTS ___________________________________________________ 73

2 ‫دورة تدریب ا�هندس‬


TABLEAU DE CONTENU
C.CHECK IN / CHECK OUT _____________________________________________________ 78
I.CHECK OUT _____________________________________________________________ 78
II.CHECK IN ______________________________________________________________ 78

D.EXPORTATION / IMPORTATION ________________________________________________ 80


I.EXPORTER XER___________________________________________________________ 80
II.EXPORTER XLS __________________________________________________________ 80
III.EXPORTER MS PROJECT ____________________________________________________ 81
IV.EXPORTER LAY-OUTS / RAPPORTS / GLOBAL CHANGE ________________________________ 83

E.PUBLIER LE PROJET EN SITE WEB ______________________________________________ 84

31.ANNEXE A : LES RACCOURCIS DU CLAVIER ________________________________ 85

2 ‫دورة تدریب ا�هندس‬


PAGE 1 LES DONNÉES DU PROJET

LES DONNÉES DU PROJET


LA FILIALE « CONSTRUCTION » DE L’ENTREPRISE « PROJECT ALGERIA » A UN PROJET DE 100
MDA POUR "AADL" A JANVIER 2017 :
ID DE PROJET : 10LOGS
CODE DU PROJET : 17/21/LG.HS/AADL/M/001
NOM DU PROJET : RÉALISATION D’UN BÂTIMENT DE 10 LOGS HAUT STANDING EN TCE
WILAYA DU PROJET : BLIDA

TABLEAU 1 : LISTE DES TACHES ET RELATIONS.


ID TACHE DURÉE (J) PRÉDÉCESSEUR RESSOURCES QTT

LG01 ODS DE DÉMARRAGE - - -

LG02 IMPLANTATION 1 LG01 FS TOPO 01

LG03 DÉCAPAGE 1 LG02 FS PLMC 01

LG04 EXCAVATION 3 LG03 SS PLMC 02


MOPOLY 05
LG05 BP (BÉTON DE PROPRETÉ) 2 LG04 FS + 1
BA150 50 M3
LG06 TRAÇAGE DES FONDATIONS 1 LG05FS + 1 TOPO 01
MOPOLY 05
LG07 BÉTONNAGE DES FONDATIONS 20 LG06 FS
BA350 200 M3
LG08 REMBLAIEMENT 5 LG07 FS PLMC 01

LG09 ASSAINISSEMENT ET PLATE FORME 10 LG08 FS + 5 SOUS TRAITANT

LG010 STRUCTURE EN ÉLÉVATION 60 LG09 FS SOUS TRAITANT


LG010 SS + 20 ; SOUS TRAITANT ;
LG011 SECONDE ŒUVRE 50
LG010 FF + 20 ENG.CES 01
LG012 RÉCEPTION DES TRAVAUX - LG011 FS -
LG05 SS
LG013 PÉRIODE DU BÉTONNAGE ? ENG.BA 01
LG010 FF
CHFP 01
LG014 DUREE DU PROJET ? - ENG.SIT 01
PLFC 01

TABLEAU 2 : LES BUDGETS ET LES CALENDRIERS DES TACHES.


ID TACHE BUDGET CALENDRIER

LG01 ODS DE DÉMARRAGE - 10 LOGS CALENDRIER

LG02 IMPLANTATION - 10 LOGS CALENDRIER

LG03 DÉCAPAGE 100 000.00 DA 10 LOGS CALENDRIER

LG04 EXCAVATION 100 000.00 DA 10 LOGS CALENDRIER

LG05 BP (BÉTON DE PROPRETÉ) 600 000.00 DA 10 LOGS CALENDRIER

2 ‫دورة تدریب ا�هندس‬


LES DONNÉES DU PROJET PAGE 2

ID TACHE BUDGET CALENDRIER

LG06 TRAÇAGE DES FONDATIONS - 10 LOGS CALENDRIER

LG07 BÉTONNAGE DES FONDATIONS 8 000 000.00 DA 10 LOGS CALENDRIER

LG08 REMBLAIEMENT 50 000.00 DA 10 LOGS CALENDRIER

LG09 ASSAINISSEMENT ET PLATE FORME 150 000.00 DA 10 LOGS CALENDRIER

LG010 STRUCTURE EN ÉLÉVATION 36 000 000.00 DA 10 LOGS CALENDRIER

LG011 SECONDE ŒUVRE 55 000 000.00 DA 10 LOGS CALENDRIER

LG012 RÉCEPTION DES TRAVAUX - 10 LOGS CALENDRIER

LG013 PÉRIODE DU BÉTONNAGE - 10 LOGS CALENDRIER

LG014 DURÉE DU PROJET - 10 LOGS CALENDRIER

TOTAL 100 000 000.00 DA

TABLEAU 3 : LES TYPES DES TACHES.


% COMPLETE
ID TACHE ACTIVITY TYPE DURATION TYPE
TYPE
START
LG01 ODS DE DÉMARRAGE - PHYSICAL
MILESTONE
LG02 IMPLANTATION TASK DEPENDENT FIXED UNITS/TIME PHYSICAL

LG03 DÉCAPAGE TASK DEPENDENT FIXED UNITS/TIME PHYSICAL

LG04 EXCAVATION TASK DEPENDENT FIXED UNITS/TIME DURATION


FIXED DURATION
LG05 BP (BÉTON DE PROPRETÉ) TASK DEPENDENT PHYSICAL
& UNITS
LG06 TRAÇAGE DES FONDATIONS TASK DEPENDENT FIXED UNITS/TIME PHYSICAL

LG07 BÉTONNAGE DES FONDATIONS TASK DEPENDENT FIXED UNITS PHYSICAL


FIXED DURATION
LG08 REMBLAIEMENT TASK DEPENDENT PHYSICAL
& UNITS/TIME
FIXED DURATION
LG09 ASSAINISSEMENT ET PLATE FORME TASK DEPENDENT PHYSICAL
& UNITS/TIME
FIXED DURATION
LG010 STRUCTURE EN ÉLÉVATION TASK DEPENDENT PHYSICAL
& UNITS/TIME
RESOURCES FIXED DURATION
LG011 SECONDE ŒUVRE PHYSICAL
DEPENDENT & UNITS/TIME
FINISH
LG012 RÉCEPTION DES TRAVAUX - PHYSICAL
MILESTONE
LG013 PÉRIODE DU BÉTONNAGE LOE FIXED UNITS/TIME DURATION

LG014 DURÉE DU PROJET WBS SUMMARY FIXED UNITS/TIME DURATION

2 ‫دورة تدریب ا�هندس‬


PAGE 3 LES DONNÉES DU PROJET

TABLEAU 4 : LISTE DES RESSOURCES.


NOM & TITRE DE MAX COST
ID TYPE COST/UNITE CALENDRIER
RESSOURCE UNITS/TIME ACCOUNT
ILYAS – 10 LOGS
CHFP LABOR 3000 DA/d 1 d/d 063
CHEF DE PROJET CALENDRIER
HICHAM – 10 LOGS
ENG.SIT LABOR 2000 DA/d 1 d/d 063
INGÉNIEUR DE SITE CALENDRIER
10 LOGS
PLFC PLANIFICATEUR LABOR 2000 DA/d 1 d/d 063
CALENDRIER
10 LOGS
TOPO HOUARI - TOPOGRAPHE LABOR 2000 DA/d 1 d/d 063
CALENDRIER
BELKACEM - INGÉNIEUR 10 LOGS
ENG.BA LABOR 2000 DA/d 1 d/d 063
BÉTON ARMÉE CALENDRIER
ENG.CES
ENG.CES AYMEN – INGÉNIEUR CES LABOR 2000 DA/d 1 d/d 063
CALENDRIER
OUVRIERS 10 LOGS
MOPOLY LABOR 1500 DA/d 5 d/d 063
POLYVALENTS CALENDRIER
NON 10 LOGS
PLMC PELLE MÉCANIQUE 3000 DA/d 2 d/d 611
LABOR CALENDRIER
10 LOGS
BA150 BÉTON 150 KG/M3 MATERIAL 9000 DA/M3 20 M3/d 604
CALENDRIER
10 LOGS
BA350 BÉTON 350 KG/M3 MATERIAL 13000 DA/M3 30 M3/d 604
CALENDRIER

TABLEAU 5 : LISTE DES DÉPENSES


MONTANT DE CATÉGORIE DE CENTRE DE
ID TACHE
DÉPENSE DÉPENSE FRAIS
LG01 ODS DE DÉMARRAGE 100 000.00 DA BUREAUTIQUE 062

LG05 BP (BÉTON DE PROPRETÉ) 20 000.00 DA REPAS 063

LG07 BÉTONNAGE DES FONDATIONS 100 000.00 DA REPAS 063

LG09 ASSAINISSEMENT ET PLATE FORME 120 000.00 DA SOUS-TRAITANCE 611

LG010 STRUCTURE EN ÉLÉVATION 30 000 000.00 DA SOUS-TRAITANCE 611

LG011 SECONDE ŒUVRE 50 000 000.00 DA SOUS-TRAITANCE 611

LG012 RÉCEPTION DES TRAVAUX 100 000.00 DA BUREAUTIQUE 062

TABLEAU 6 : LES ÉTAPES DE LA TACHE LG07


ID TACHE NOM DE L'ÉTAPE POIDS DE L'ÉTAPE
LG07 BÉTONNAGE DES FONDATIONS COFFRAGE SEMELLE 3
DATE DE CONTRAINT FERRAILLAGE SEMELLE 2
CETTE TACHE NE PEUT PAS COULAGE SEMELLE 1
DÉMARRER AVANT LE : FERRAILLAGE AM POTEAUX 5
16 / JAN / 2017 COFFRAGE AM POTEAUX 5
COULAGE AM POTEAUX 1
DÉCOFFRAGE ET CURAGE 2
NETTOYAGE 1

2 ‫دورة تدریب ا�هندس‬


LES PARAMÈTRES DU PROJET PAGE 4

LES PARAMÈTRES DU PROJET

FIGURE 1 : LA STRUCTURATION DE L'ENTREPRISE.

TABLEAU 7 : LES CODES DES PROJETS.


MAITRE DE
ANNÉE RÉGION. WILAYA TYPE CAPACITÉ
L'OUVRAGE
15 2015 1 EST LOG LOGEMENTS AADL AADL P < 50 MDA
HAUT
16 2016 1.1 ANNABA LOG.HS CEVITAL CEVITAL M 50-200 MDA
STANDING
17 2017 1.2 BATNA LOG.SOC SOCIAL DLEP DLEP G > 200 MDA
18 2018 2 CENTRE VILLA VILLAS
19 2019 2.1 BLIDA
20 2020 2.2 MEDEA
3 OUEST
3.1 ORAN
3.2 TELEMCEN

TABLEAU 8 : LES CODES DES TACHES


TYPE EXÉCUTEUR NIVEAU
PREP PRÉPARATION PRPMO PROPRE MAIN D'ŒUVRE PRJT PROJET
PROD PRODUCTION STRT SOUS-TRAITANCE INFR INFRASTRUCTURE
MNGM MANAGEMENT NA NULLE SUPR SUPERSTRUCTURE

2 ‫دورة تدریب ا�هندس‬


PAGE 5 LES PARAMÈTRES DU PROJET
TABLEAU 9 : LES CODES DES RESSOURCES
CATÉGORIE CLASSEMENT
PROD PRODUCTIVE PRRS PROPRE RESSOURCE
EQPM ÉQUIPEMENT STRT SOUS-TRAITANT
CNSM CONSOMMABLE
MNGL MANAGÉRIALE

TABLEAU 10 : LES CENTRES DE FRAIS


ID DÉSIGNATION
062 SERVICES
063 CHARGES DE PERSONNEL
604 ACHATS D'ÉTUDES ET DE PRESTATION DE SERVICES
611 SOUS-TRAITANCE GÉNÉRALE

TABLEAU 11 : LA DOCUMENTATION DU PROJET


LE DOCUMENT REFERENCE N° CATÉGORIE ÉTAT
LE MARCHÉ LG.HS-PRJT-001 CONTRATS APPROVED
ODS DÉMARRAGE LG.HS-PRJT-002 ORDRES DE SERVICE APPROVED
PLAN DE TERRASSEMENT LG.HS-INFR-1/3 PLAN TECHNIQUES APPROVED
PLAN DE FONDATION LG.HS-INFR-2/3 PLAN TECHNIQUES APPROVED
PLAN ASSAINISSEMENT LG.HS-INFR-3/3 PLAN TECHNIQUES APPROVED
PLAN DE LA STRUCTURE LG.HS-SUPR-1/2 PLAN TECHNIQUES APPROVED
PLAN CES LG.HS-SUPR-2/2 PLAN TECHNIQUES UNDER REVIEW
PV DE RÉCEPTION DU PROJET LG.HS-PRJT-003 PROCÈS VERBAUX ON HOLD

TABLEAU 12 : LES CALENDRIERS.


GLOBAL PERSONAL RESSOURCE PROJECT
ALGÉRIE CALENDRIER ENG CES CALENDRIER 10 LOGS CALENDRIER
-BASE SUR (TRADES-5 DAYS -CALENDRIER DE DE 8 H /JOUR -BASE SUR ALGÉRIE CALENDRIER
WORKWEEK) ET 6 J/SEMAINE -LE MOIS D’AOÛT EST UN CONGÉ
-CALENDRIER DE DE 8 H /JOUR -LE WEEK-END EST VENDREDI ANNUEL
ET 5 J/SEMAINE -1 JANVIER, 1 MAI, 5 JUILLET ET
-LE WEEK-END EST VENDREDI, 1ER NOVEMBRE SONT DES
SAMEDI PÉRIODES CHÔMÉES.
-1 JANVIER, 1 MAI, 5 JUILLET ET
1ER NOVEMBRE SONT DES
PÉRIODES CHÔMÉES.

2 ‫دورة تدریب ا�هندس‬


LES PARAMÈTRES DU PRIMAVERA PAGE 6

LES PARAMÈTRES DU PRIMAVERA


A. LE DEVIS

ID : DZD NOM : DINAR ALGÉRIEN SYMBOL : DA TAUX D'ÉCHANGE : 1$ = 130 DA


GROUPEMENT : (,) DÉCIMAL : (.00) POSITIVE = 1.1 $ NÉGATIVE = -1.1 $

B. LES CATÉGORIES DE L'ADMINISTRATEUR

TABLEAU 13 : LES CATÉGORIES DE L'ADMINISTRATEUR


CATÉGORIES DE DÉPENSES CATÉGORIES DE DOC LES UNITES
BUREAUTIQUE CONTRATS U UNITÉ
REPAS PLANS TECHNIQUES ML LONGUEUR
SOUS-TRAITANCE ORDRES DE SERVICE M2 SURFACE
PROCÈS VERBAUX M3 VOLUME

L'INTERFACE DU PRIMAVERA

1 : LA BARRE DES COMMANDES 2 : LA BARRE DES ICONES 3 & 4 : LA PARTIE HAUTE


3 : LE TABLEAU 4 : LE DIAGRAMME DE GANTT 5 : LA PARTIE BASSE
6 : LA BARRE D'ÉTAT

2 ‫دورة تدریب ا�هندس‬


PAGE 7 L'INTERFACE DU PRIMAVERA

ALLEZ VERS : VIEW > TOOLBARS > CUSTOMIZE


À PARTIR DU VOLET (TOOLBARS) SÉLECTIONNEZ LES BARRES
DES ICONES A AFFICHER.
SUR LE VOLET (OPTIONS) DÉCOCHEZ L'OPTION (MENUS SHOW
RECENTLY…) ET CLIQUEZ CLOSE

AU COTE DROIT DE LA BARRE DES ICONES (SHOW ON TOP) CLICK


SUR LE PETIT TRIANGLE POUR AFFICHER LE MENU DES ICONES
CACHÉS ; ET SÉLECTIONNEZ EN PLUS
 ACTIVITY USAGE SPREAD SHEET (ACTIVITY WINDOW)
 HIDE LEFT COLUMN (TRACKING WINDOW)
 HIDE TOP WINDOW (TRACKING WINDOW)
 RESOURCE USAGE SPREADSHEET (ACTIVITY WINDOW)

LE MÊME TRAVAIL POUR AFFICHER


 NO BOTTOM LAYOUT
QUI VEUT DIRE CACHER LA PARTIE BASSE

NOTES :

2 ‫دورة تدریب ا�هندس‬


LA LANGUE D'AFFICHAGE PAGE 8

LA LANGUE D'AFFICHAGE

POUR CHANGER LA LANGUE DE L'INTERFACE, ALLEZ VERS : TOOLS > SET LANGUAGE

LES PARAMÈTRES DU DEVIS

CLIQUEZ SUR : ADMIN > CURRENCIES

ET AJOUTEZ UN NOUVEAU DEVIS EN CLIQUANT SUR ADD ET APPLIQUEZ LES MODIFICATIONS


NÉCESSAIRES

VOUS POUVEZ CHERCHER UN DEVIS OU IMPRIMER LA LISTE DES DEVIS

 VOUS DEVEZ ASSURER LA COMPATIBILITÉ DES PARAMÈTRES DU CHIFFRE MONÉTAIRE ENTRE


LE SYSTÈME ET LE PRIMAVERA P6

LES PRÉFÉRENCES DE L'UTILISATEUR


POUR AVOIR L'ACCÈS AUX PARAMÈTRES D'UTILISATEUR, ALLEZ
VERS : LE MENU : EDIT > USER PREFERENCES.

2 ‫دورة تدریب ا�هندس‬


PAGE 9 LES PRÉFÉRENCES DE L'UTILISATEUR

 SI VOUS COCHEZ (SUB-UNITS), L'EXPORTATION


VERS LA FEUILLE DE CALCUL NE SERA PAS
ASSEZ AIDANTE

CLIQUEZ SUR CLOSE

NOTES :

2 ‫دورة تدریب ا�هندس‬


LES PARAMÈTRES DE L'ADMINISTRATEUR PAGE 10

LES PARAMÈTRES DE L'ADMINISTRATEUR


A. LES CALENDRIERS

POUR AJOUTER (GLOBAL) CALENDRIER, CHOISISSEZ (CALENDARS)


A PARTIR DU MENU (ENTERPRISE)

CLIQUEZ SUR ADD ET CHOISISSEZ LE UTILISEZ LES BOUTONS WORK ET NONWORK POUR
CALENDRIER DE BASE, CLIQUEZ MODIFY SIGNALER LES JOURS OUVRABLE ET CHÔMÉS

CLIQUEZ SUR LE BOUTON WORKWEEK… ET


CLIQUEZ SUR TIME PERIODS AFIN DE DÉTERMINER
MENTIONNEZ LE NOMBRE DES HEURES POUR
L'ÉQUIVALENCE DE CHAQUE PÉRIODE EN HEURES
CHAQUE JOUR DE LA SEMAINE
 QUAND TU SÉLECTIONNES UNE JOURNÉE DU CALENDRIER ET MODIFIES SON NOMBRE DES HEURES,
CETTE JOURNÉE VA ÊTRE (EXCEPTION) AVEC UNE COULEUR BLANCHE. LE BOUTON STANDARD
PEUT L'INITIALISER
 MET TON CALENDRIER COCHER (DEFAULT)
FERMER LA FENÊTRE DES CALENDRIERS

NOTES :

2 ‫دورة تدریب ا�هندس‬


PAGE 11 LES PARAMÈTRES DE L'ADMINISTRATEUR
B. LES PRÉFÉRENCES DE L'ADMINISTRATEUR

ALLER VERS : ADMIN > ADMIN PREFERENCES

POUR L'INDUSTRIE, CHOISISSEZ

CLIQUEZ CLOSE POUR SORTIR

NOTES :

2 ‫دورة تدریب ا�هندس‬


LA HIÉRARCHISATION PAR OBS. PAGE 12
C. LES CATÉGORIES DE L'ADMINISTRATEUR

CHOISISSEZ : ADMIN >ADMIN CATEGORIES

POUR AJOUTER UNE NOUVELLE CASE, CLIQUEZ SUR ADD


LE BOUTON DISPLAY VOUS PERMET D'IMPRIMER LES LISTES DES CATÉGORIES
 LES TROIS PETITES TIRETS SUR LA TÊTE DE LA COLONNE VEUT DIRE QUE TU PEUX
ORGANISER LA LISTE PAR SHIFT UP ET SHIFT DOWN

CLIQUEZ SUR CLOSE POUR SORTIR

LA HIÉRARCHISATION PAR OBS.


OBS. EST L'ABRÉVIATION DE (ORGANIZATIONAL BREAKDOWN STRUCTURE) QUI VEUT DIRE LA
STRUCTURATION DES RESPONSABLES DE
L'ENTREPRISE
ALLEZ VERS : ENTERPRISE > OBS...

AJOUTEZ LES ÉLÉMENTS PAR ADD

LES 4 FLÈCHES SERVENT À


L'ORGANISATION DES ÉLÉMENTS

DISPLAY OU CLIQUE DROITE VOUS


PERMET D'AFFICHER LES ÉLÉMENTS EN
ORGANIGRAMME, FILTRER LA LISTE,
CHANGER LE POLICE...ETC.

VOUS POUVEZ AJOUTER DES


COMMENTAIRES (TEXTES ; PHOTOS ;
LIENS OU TABLEAUX) AUX ÉLÉMENTS A
PARTIR DU MODIFY

2 ‫دورة تدریب ا�هندس‬


PAGE 13 LA STRUCTURATION DE L'ENTREPRISE

LA STRUCTURATION DE L'ENTREPRISE
EPS. EST L'ABRÉVIATION DE (ENTERPRISE PROJECT STRUCTURE) QUI VEUT DIRE LA
STRUCTURATION DES PROJETS DE L'ENTREPRISE
ALLEZ VERS : ENTERPRISE > ENTERPRISE PROJECT STRUCTURE…

AJOUTEZ LES EPS PAR ADD

DISPLAY OU CLIQUE DROITE


VOUS PERMET D'AFFICHER LES EPS
EN ORGANIGRAMME, FILTRER LA
LISTE, CHANGER LE POLICE...ETC.

CHOISISSEZ COLUMNS >


RESPONSIBLE MANAGERS. POUR
AJOUTER CETTE COLONNE

AFFECTEZ CHAQUE OBS. SUR SON


EPS À TRAVERS LE BOUTON _…_

 L'ICÔNE DE TROIS PETITES TIRETS ENCERCLÉES VEUT DIRE QUE TU PEUX ORGANISER LA
LISTE PAR LES 4 FLÈCHES

CLIQUEZ SUR CLOSE POUR SORTIR

LES CODES
A. LES CODES DES PROJETS

LES CODES DES PROJETS SERVENT À ORGANISER, CLASSIFIER OU


FILTRER LES PROJETS SELON UN AU PLUSIEURS CRITÈRES AUSSI
QU'ANALYSER LEURS RÉSULTATS

POUR ACCÉDER AU DICTIONNAIRE DES


CODES DES PROJET, ALLEZ VERS :
ENTERPRISE > PROJECT CODES…

CLIQUEZ SUR MODIFY

2 ‫دورة تدریب ا�هندس‬


LES CODES PAGE 14
POUR AJOUTER LES CODES CLIQUEZ
SUR ADD

VOUS POUVEZ LES ORGANISER PAR


SHIFT UP ET SHIFT DOWN SI LE
TRI EST INACTIF

À TRAVERS DISPLAY OU CLIQUE


DROITE VOUS POUVEZ IMPRIMER LA
LISTE DES CODES, MODIFIER LES
COLONNES OU LE POLICE…ETC.

POUR SORTIR CLIQUEZ CLOSE

MAINTENANT, VOUS POUVEZ


AFFECTER LES VALEURS DE CHAQUE
CODE EN CHOISISSANT LE CODE ET
CLIQUANT ADD

ORGANISEZ CES VALEURS PAR LES 4


FLÈCHES SI LE TRI EST INACTIF

À TRAVERS DISPLAY OU CLIQUE


DROITE VOUS POUVEZ IMPRIMER LA
LISTES DES VALEURS OU LES
AFFICHER EN DIAGRAMME,
MODIFIER LES COLONNES OU LE
POLICE, FILTRER LES
VALEURS…ETC.

POUR FERMER LA FENÊTRE CLIQUEZ


CLOSE

B. LES CODES DES TACHES

LES CODES DES TACHES SERVENT À ORGANISER, CLASSIFIER OU FILTRER LES TACHES SELON UN AU
PLUSIEURS CRITÈRES AUSSI QU'ANALYSER LEURS RÉSULTATS

POUR ACCÉDER AU DICTIONNAIRE DES CODES DES TACHES,


ALLEZ VERS : ENTERPRISE > ACTIVITY CODES…

CHOISISSEZ (GLOBAL) ET CLIQUEZ SUR MODIFY

2 ‫دورة تدریب ا�هندس‬


PAGE 15 LES CODES

POUR AJOUTER LES CODES CLIQUEZ SUR ADD

VOUS POUVEZ LES ORGANISER PAR SHIFT UP


ET SHIFT DOWN SI LE TRI EST INACTIF

À TRAVERS DISPLAY VOUS POUVEZ IMPRIMER


LA LISTE DES CODES

POUR SORTIR CLIQUEZ CLOSE

MAINTENANT, VOUS POUVEZ AFFECTER LES


VALEURS DE CHAQUE CODE EN CHOISISSANT LE
CODE ET CLIQUANT ADD

ORGANISEZ CES VALEURS PAR LES 4 FLÈCHES SI


LE TRI EST INACTIF

À TRAVERS DISPLAY OU CLIQUE DROITE VOUS


POUVEZ IMPRIMER LA LISTES DES VALEURS OU
LES AFFICHER EN DIAGRAMME, MODIFIER LES
COLONNES OU LE POLICE, FILTRER LES
VALEURS…ETC.

 C'EST PRÉFÉRABLE DE LAISSER CHAQUE


CODE DISTINCT EXP : TYPE tsk
/ prjt

CLIQUEZ CLOSE

 GLOBAL : LES CODES SONT UTILISÉS


POUR TOUTE L'ENTREPRISE
 EPS : LES CODES SONT UTILISÉS POUR
UN NIVEAU D'EPS SPÉCIFIQUE
/SÉLECTIONNÉ
 PROJECT : LES CODES SONT UTILISÉS
POUR UN PROJET SPÉCIFIQUE / OUVERT

C. LES CODES DES RESSOURCES

LES CODES DES RESSOURCES SERVENT À ORGANISER, CLASSIFIER OU FILTRER LES RESSOURCES
SELON UN AU PLUSIEURS CRITÈRES AUSSI QU'ANALYSER LEURS DÉPENSES ET AFFECTATIONS

POUR ACCÉDER AU DICTIONNAIRE DES CODES DES RESSOURCES,


ALLEZ VERS : ENTERPRISE > RESOURCE CODES…

2 ‫دورة تدریب ا�هندس‬


LES CODES PAGE 16

CLIQUEZ SUR MODIFY

POUR AJOUTER LES CODES CLIQUEZ SUR ADD

VOUS POUVEZ LES ORGANISER PAR SHIFT UP


ET SHIFT DOWN SI LE TRI EST INACTIF

À TRAVERS DISPLAY OU CLIQUE DROITE VOUS


POUVEZ IMPRIMER LA LISTE DES CODES

POUR SORTIR CLIQUEZ CLOSE

MAINTENANT, VOUS POUVEZ AFFECTER LES


VALEURS DE CHAQUE CODE EN CHOISISSANT LE
CODE ET CLIQUANT ADD

ORGANISEZ LES VALEURS PAR LES 4 FLÈCHES SI


LE TRI EST INACTIF
PRRS

À TRAVERS DISPLAY OU CLIQUE DROITE VOUS


POUVEZ IMPRIMER LA LISTE DES VALEURS OU
LES AFFICHER EN DIAGRAMME, MODIFIER LES
COLONNES OU LE POLICE, FILTRER LES
VALEURS…ETC.

CLIQUEZ CLOSE

2 ‫دورة تدریب ا�هندس‬


PAGE 17 LE DICTIONNAIRE DES RESSOURCES

LE DICTIONNAIRE DES RESSOURCES


POUR CRÉER LE DICTIONNAIRE DES RESSOURCES, CHOISISSEZ
(RESOURCES…) A PARTIR DU MENU (ENTERPRISE)

SITE

CLIQUE DROITE ET CHOISISSEZ (COLUMNS > CUSTOMIZE)

UTILISEZ LES FLÈCHES NOIRES POUR PORTEZ LES COLONNES


DEPUIS (AVAILABLE OPTIONS) VERS (SELECTED OPTIONS) ET
POUR LES ORGANISER

DISPLAY OU CLIQUE DROITE VOUS PERMET LES AFFICHER EN


DIAGRAMME, MODIFIER LES COLONNES, CHANGER LE POLICE,
FILTRER, GROUPER ET TRIER LES RESSOURCES

UTILISEZ LES 4 FLÈCHES BLEUES POUR HIÉRARCHISER LES


RESSOURCES -ULTÉRIEUREMENT- SI NÉCESSAIRE
POUR AJOUTER UNE RESSOURCE, CLIQUEZ SUR , UN
WIZARD VA DÉCLENCHER POUR VOUS AIDER AU COURS DE LA
CRÉATION DE RESSOURCE

2 ‫دورة تدریب ا�هندس‬


LE DICTIONNAIRE DES RESSOURCES PAGE 18

CLIQUEZ NEXT CLIQUEZ NEXT

CLIQUEZ NEXT CLIQUEZ NEXT

VOUS POUVEZ CONSULTER LE CALENDRIER PAR


CLIQUEZ NEXT VIEW/EDIT
CLIQUEZ NEXT

2 ‫دورة تدریب ا�هندس‬


PAGE 19 LE DICTIONNAIRE DES RESSOURCES

CLIQUEZ NEXT COCHEZ (DO NOT SHOW THIS WIZARD AGAIN)


VOUS POUVEZ LE RÉACTIVER DEPUIS :
EDIT > USER PREFERENCES > ASSISTANCE
CLIQUEZ OK PUIS FINISH

DEPUIS LA PARTIE BASSE DE LA FENÊTRE RESSOURCES, VOUS POUVEZ


AFFECTER LES CODES POUR CHAQUE RESSOURCE EN CLIQUANT ASSIGN

À PARTIR DU VOLET (DETAILS), VOUS


POUVEZ AJOUTER LE CALENDRIER
SPÉCIFIQUE POUR L'INGÉNIEUR CES

CLIQUEZ OK POUR SORTIR

 ASSURER TOUJOURS QUE CES PARAMÈTRES


SONT COCHÉS

2 ‫دورة تدریب ا�هندس‬


LE DICTIONNAIRE DES RESSOURCES PAGE 20
(UNITS & PRICES) : VOUS POUVEZ AFFECTER PLUS
QU'UN TAUX DE PRIX SELON LES DIFFÉRENTES
PÉRIODES

POUR GROUPER LES RESSOURCES SELON LES


DIFFÉRENTS TYPES CLIQUEZ SUR DISPLAY OU
CLIQUE DROITE DANS LA FENÊTRE (RESOURCES) ET
CHOISISSEZ :
GROUP AND SORT BY > CUSTOMIZE

MAINTENAIT, VOUS VOYEZ QUE LES RESSOURCES


SONT GROUPÉES PAR TYPE

CLIQUEZ SUR (RESOURCE ID) POUR TRIER LES


RESSOURCES EN ALPHANUMÉRIQUE DANS CHAQUE
GROUPE

NOTES :

2 ‫دورة تدریب ا�هندس‬


PAGE 21 LES CENTRES DE FRAIS

LES CENTRES DE FRAIS


CES COMPTES SERVENT À ORGANISER, CLASSIFIER OU FILTRER LES DÉPENSES OU LES CHARGES
DES RESSOURCES POUR FACILITER L'ANALYSE FINANCIÈRE
POUR ACCÉDER AU DICTIONNAIRE DES COMPTES FINANCIER,
ALLEZ VERS : ENTERPRISE > COST ACCOUNTS…

AJOUTEZ LES COMPTES PAR ADD

ORGANISEZ-LES PAR LES 4 FLÈCHES

VOUS POUVEZ LES TRIER EN CLIQUANT 611


SUR LA TÊTE DE COLONNE

LE BOUTON MODIFY VOUS PERMET


D'ACCÉDER AU BLOC-NOTES DE CHAQUE
COMPTES

VOUS POUVEZ NOTIFIER PAR UN TEXTE,


IMAGES, LIENS OU TABLEAUX

DISPLAY OU CLIQUE DROITE VOUS


PERMET D'AFFICHER LES COMPTES EN
DIAGRAMME, FILTRER, MODIFIER LE
POLICE…ETC.

LA CRÉATION DU PROJET
POUR CRÉER LE PROJET, ALLEZ VERS : FILE > NEW…

ET CHOISISSEZ L'EPS DE VOTRE PROJET

CLIQUEZ NEXT

CLIQUEZ NEXT CLIQUEZ NEXT

2 ‫دورة تدریب ا�هندس‬


LA CRÉATION DU PROJET PAGE 22

CLIQUEZ NEXT CLIQUEZ FINISH

MAINTENANT, ALLEZ VERS :


ENTERPRISE > PROJECTS

DISPLAY OU CLIQUE DROITE VOUS PERMET


DE TRAVAILLER AVEC LAYOUTS, MODIFIER
LES COLONNES, CHANGER LE POLICE,
FILTRER, GROUPER ET TRIER LES PROJETS

CLIQUE DROITE ET CHOISISSEZ (CUSTOMIZE


PROJECT DETAILS…)

UTILISEZ LES FLÈCHES NOIRS POUR PORTEZ


LES VOLETS DEPUIS (AVAILABLE TABS) VERS
(DISPLAY TABS) OU POUR LES ORGANISER

NOTES :

2 ‫دورة تدریب ا�هندس‬


PAGE 23 LA CRÉATION DU PROJET

STATUS : L'ÉTAT DU PROJET


ACTIVE : LE PROJET EST EN COURS
INACTIVE : LE PROJET ET SUSPENDU
PLANNED : LE PROJET EST À L'ÉTAPE
PLANIFICATION
WHAT IF : CE PROJET EST UNE SIMULATION

CHECKED IN/OUT : DEDANS / DEHORS

POUR LAISSER LES DIFFÉRENTS VOUS POUVEZ MODIFIER LES DIFFÉRENTES


COMMENTAIRES SUR LE PROJET CLIQUEZ MODIFY DATES DU PROJET

CODIFIEZ LE PROJET À TRAVERS S'IL Y A PAS DES TACHES DANS LE PROJET, VOUS
LE BOUTON ASSIGN POUVEZ AFFECTER DES DATES ANTICIPÉES

CE VOLET SERT À DÉTERMINER LES PARAMÈTRES


PAR DÉFAUT DU PROJET POUR LES NOUVELLES
TACHES

2 ‫دورة تدریب ا�هندس‬


EXPLICATION PAGE 24

POUR CRÉER LE CALENDRIER DU PROJET ALLER VERS : ENTERPRISE > CALENDARS… ET SELECT (PROJECT)
ET CLIQUEZ ADD
MAINTENANT, CHOISISSEZ LE CALENDRIER DE BASE ET METTEZ LE MOIS D'AOUT (NONWORK)
CLIQUEZ OK POUR SORTIR

 S'IL Y A UN CHANGEMENT AU NIVEAU DU CALENDRIER DE BASE, IL VA ÊTRE SIGNALÉ DANS LE


CALENDRIER DU PROJET COMME ÇA

EXPLICATION
A. ACTIVITY TYPE

START/FINISH MILE STONE : JALON DE DÉBUT ET DE FIN


TASK / RESOURCE DEPENDENT : LA TACHE SUIT SON CALENDRIER OU CELUI DE LA RESSOURCE
LOE : DÉBUT ET FIN SELON LES RELATIONS
WBS SUMMARY : SELON LE DÉBUT ET LA FIN DE WBS QUI CONTIENT CETTE TACHE

 S'IL Y A PLUSIEURS RESSOURCES AFFECTÉES À LA TACHE, LA DURÉE DE CELLE-CI SUIT LA


PLUS GRAND VALEUR DE (ORIGINAL DURATION) DE SES RESSOURCES

B. ACTIVITY DURATION TYPE

UNITS(Qtt De Travail)
DURATION(Durée) =
UNITS/TIME(Productivité)

2 ‫دورة تدریب ا�هندس‬


PAGE 25 EXPLICATION
PAR EXEMPLE :

500 M3 DE BÉTON AVEC UNE CADENCE DE 100 M3/JOUR  DURATION = 5 JOURS

2000 M3 DU DÉBLAI AVEC UNE PELLE QUI EXTRAIT 1000 M3/JOUR  DURATION = 2 JOURS

500 POINTS À LEVER, LE TOPOGRAPHE PEUT LEVER 200 POINTS/JOUR  DURATION = 2.5 JOURS

UN COURS DES MATHÉMATIQUES NÉCESSITE 2 JOURS D’ASSISTANCE, MAIS LE PROFESSEUR NE


POUVAIT ASSISTER QUE 0.5 JOURNÉE/JOUR  DURATION = 4 JOURS

FIXED DURATION & UNITS/TIME FIXED DURATION & UNITS

NOTE : NOTE :

FIXED UNITS FIXED UNITS/TIME

NOTE : NOTE :

2 ‫دورة تدریب ا�هندس‬


ENREGISTRER ET EXPORTER PROJECT LAY-OUT PAGE 26
C. ACTIVITY % COMPLETE TYPE

PHYSICAL % = ESTIMATION PERSONNELLE

DURATION % = {(ORIGINAL DURATION – REMAINING DURATION) /ORIGINAL DURATION} X 100

UNIT % = (ACTUAL UNITS / AT COMPLETION UNITS) X 100 (ONLY LABOR AND NON LABOR)

ENREGISTRER ET EXPORTER PROJECT LAY-OUT

CLIQUEZ SUR :
LAY-OUT > COLUMNS > CUSTOMIZE…

UTILISEZ LES FLÈCHES POUR AFFECTER ET


ORGANISER LES COLONNES A (SELECTED
OPTIONS)

POUR ENREGISTRER LE LAY-OUT


CLIQUEZ :
LAY-OUT > SAVE AS…

TAPEZ LE NOM
ET CLIQUEZ SAVE

POUR EXPORTER UN LAY-OUT


CHOISISSEZ : LAY-OUT > OPEN…

SÉLECTIONNEZ LE LAY-OUT

ET CLIQUEZ EXPORT

2 ‫دورة تدریب ا�هندس‬


PAGE 27 LA DOCUMENTATION DU PROJET

LA DOCUMENTATION DU PROJET
DANS LE PRIMAVERA, VOUS POUVEZ ORGANISER VOTRE DOCUMENTATION AFIN DE FACILITER SA
CONSULTATION

POUR ACCÉDER À LA BIBLIOTHÈQUE DU PROJET, CLIQUEZ :


PROJECT > WPS & DOCS

CLIQUE DROITE ET CHOISISSEZ (COLUMNS > CUSTOMIZE)

UTILISEZ LES FLÈCHES NOIRES POUR PORTEZ LES


COLONNES DEPUIS (AVAILABLE OPTIONS) VERS
(SELECTED OPTIONS) ET/OU POUR LES ORGANISER
POUR AJOUTER UN DOCUMENT, CLIQUEZ SUR

DISPLAY OU CLIQUE DROITE VOUS PERMET D'AFFICHER,


MODIFIER LES COLONNES, CHANGER LE POLICE,
FILTRER, GROUPER ET TRIER LES DOCUMENTS DELIVERABLE : SI LE DOCUMENTS ET UN
OUTPUT DU PROJET TELLS QUE LES PLANS
UTILISEZ LES 4 FLÈCHES BLEUES POUR HIÉRARCHISER TECHNIQUES POUR UN PROJET D'ÉTUDE
LES DOCUMENTS SI NÉCESSAIRE

PRIVATE LOCATION : QUE LES


UTILISATEURS DU P6 PROFESSIONAL
PEUVENT CONSULTER CE DOCUMENT

PUBLIC LOCATION : TOUS LES


UTILISATEURS PEUVENT CONSULTER
CE DOCUMENT

2 ‫دورة تدریب ا�هندس‬


LA DOCUMENTATION DU PROJET PAGE 28

VOUS POUVEZ AFFECTER LE


DOCUMENT SUR UNE TACHE OU SUR
UN WBS ET MÊME SUR LE PROJET

WORK PRODUCT : SI LE DOCUMENT


EST UN OUTPUT, MAIS CE N'EST PAS
CELUI DU PROJET, TELS QUE LES
SITUATIONS DES TRAVAUX

AFIN DE GROUPER LES DOCUMENTS


PAR CATÉGORIE, CLIQUEZ DROITE ET
SÉLECTIONNEZ :
GROUPE & SORT BY > CATEGORY

NOTES :

2 ‫دورة تدریب ا�هندس‬


PAGE 29 LE DÉCOUPAGE DU PROJET PAR WBS

LE DÉCOUPAGE DU PROJET PAR WBS


WBS. EST L'ABRÉVIATION DU (WORK BREAKDOWN STRUCTURE) QUI VEUT DIRE LE DÉCOUPAGE
STRUCTURÉ DE TRAVAIL, LES WBS SONT LES PARTIES QUI VONT ÊTRE
RÉCEPTIONNÉS PAR LE MAITRE DE L'OUVRAGE AFIN DE PAYER
L'ENTREPRISE

POUR ACCÉDER À LA FENÊTRE WBS, ALLER VERS : PROJECT > WBS

CLIQUEZ SUR LE BOUTON (LAY-OUT) OU CLIQUE DROITE SUR LA PARTIE


TABLEAU, SÉLECTIONNEZ (COLUMNS)
ET CHOISISSEZ (RESPONSIBLE MANAGER)

1 : LE TABLEAU
2 : LE DIAGRAMME DE GANTT
1 & 2 : LA PARTIE HAUTE
3 : LA PARTIE BASSE

CLIQUE DROITE SUR LA PARTIE BASSE, CHOISISSEZ


(CUSTOMIZE WBS DETAILS…) ET ORGANISEZ LES VOLETS

POUR AJOUTER LES WBS CLIQUEZ SUR , VOUS POUVEZ UTILISER LES FLÈCHES BLUES POUR
HIÉRARCHISER LES WBS

2 ‫دورة تدریب ا�هندس‬


LE DÉCOUPAGE DU PROJET PAR WBS PAGE 30

VOUS POUVEZ AJOUTER DES


COMMENTAIRES SUR CHAQUE WBS

POUR AFFECTER LES


DOCUMENTS AU WBS A
PARTIR DE CETTE FENÊTRE
CLIQUEZ SUE ASSIGN

CLIQUEZ SUR DETAILS


POUR AFFICHER LES
INFORMATIONS DU
DOCUMENT EN
"LECTURE SEULE"

UNE CLIQUE SUR


LUNCHE VA VOUS
OUVRIR DIRECTEMENT LE
DOCUMENT

CLIQUEZ CLOSE POUR


SORTIR

CLIQUEZ : FILE > CLOSE ALL POUR FERMER TOUS LES PROJETS

FERMEZ TOUTES LES FENÊTRES

NOTES :

2 ‫دورة تدریب ا�هندس‬


PAGE 31 L'INSERTION DES ACTIVITÉS

L'INSERTION DES ACTIVITÉS


OUVREZ LA FENÊTRE (PROJECT) A PARTIR DE : ENTERPRISE > PROJECTS SI ELLE N'EST PAS
OUVERTE

SÉLECTIONNEZ LE PROJET ET CLIQUE DROITE,


CHOISISSEZ (OPEN PROJECT)
UN PROJET FERMÉ
UN PROJET OUVERT
ET VOUS AUREZ LA FENÊTRE (ACTIVITY)
OUVERTE A COTE DE CELLE DE (PROJECT)

1 : LE TABLEAU 2 : LE DIAGRAMME DE GANTT 1 & 2 : LA PARTIE HAUTE


3 : LA PARTIE BASSE

CLIQUE DROITE SUR LE


TABLEAU VOUS PERMET
D'AFFICHER LA PARTIE
BASSE, EXPORTER LE
TABLEAU DIRECTEMENT
VERS EXCEL, MODIFIER
LES COLONNES, LE
POLICE, FILTRER
GROUPER ET TRIER LES
TACHES

CLIQUE DROITE SUR LA PARTIE BASSE, CHOISISSEZ (CUTOMIZE ACTIVITY


DETAILS) ET ORGANISER LES VOLETS COMME CI-DESSUS

POUR AJOUTER LES TACHES, CHOISISSEZ LE WBS QUI CONVIENT ET CLIQUEZ


SUR , UN WIZARD VA DÉCLENCHER POUR VOUS AIDER AU COURS DE LA
CRÉATION DE LA TACHE

2 ‫دورة تدریب ا�هندس‬


L'INSERTION DES ACTIVITÉS PAGE 32

CONFIRMEZ LE WBS ET CLIQUEZ NEXT

CHOISISSEZ LE TYPE DE LA TACHE


ET CLIQUEZ NEXT
TAPEZ ID ET NOM DE LA TACHE
CLIQUEZ NEXT

CHOISISSEZ (NO, CONTINUE) POUR LAISSER LE


RELIAGE ULTÉRIEUREMENT ET CLIQUEZ NEXT

CHOISISSEZ (YES, CONTINUE CONFIGURING ACTIVITY CLIQUEZ SUR ADD ET TAPEZ LE NOM ET LE
INFORMATION) ET CLIQUEZ NEXT MONTANT DE LA DÉPENSE
CLIQUEZ NEXT

CLIQUEZ ASSIGN POUR CHOISIR LES CODES DE LA CLIQUEZ ASSIGN ET CHOISISSEZ LES DOCUMENTS DE
TACHE ET CLIQUEZ NEXT LA TACHE ET CLIQUEZ NEXT

2 ‫دورة تدریب ا�هندس‬


PAGE 33 L'INSERTION DES ACTIVITÉS
COCHEZ (DO NOT SHOW THIS WIZARD AGAIN)

VOUS POUVEZ LE RÉACTIVER A PARTIR DE :


EDIT > USER PREFERENCES > ASSISTANCE
CLIQUEZ OK PUIS FINISH

LE VOLET (GENERAL) VOUS PERMET DE SAISIR OU CHOISIR LES INPUTS DE LA TACHE

ON UTILISE LE VOLET DE (STATUS) POUR PLANIFIER LA TACHE OU POUR LA SUIVRE

LA PARTIE DES RESSOURCES UNITÉS/COUT SERT À PLANIFIER LE PROJET SANS AFFECTER DE RESSOURCES

 (SATRT/FINISH ON) FIXE LA DATE AVEC UN RESPECT DU RÉSEAU DES TACHES


 (MONDATORY) FIXE LA DATE SANS CONSIDÉRATION AU RÉSEAU DES TACHES

AJOUTEZ LES RESSOURCES DE CHAQUE TACHE

2 ‫دورة تدریب ا�هندس‬


L'INSERTION DES ACTIVITÉS PAGE 34

CLIQUE DROITE SUR LE VOLET (RESOURCES) ET AFFECTEZ LES CODES DE CHAQUE TACHE
ORGANISEZ LES COLONNES DEDANS COMME CI-DESSUS

ORGANISEZ LES COLONNES COMME CI-DESSUS

(AUTO COMPUTE ACTUALS) DOIT ÊTRE COCHÉE

(ACURAL TYPE) A TROIS PARAMÈTRES :

UNIFORME : REPARTIE SUR LA DURÉE DE L'ACTIVITÉ


START : AFFECTER LA DÉPENSE AU DÉBUT
FINISH : AFFECTER LA DÉPENSE A LA FIN

À PARTIR DE CE VOLET, VOUS POUVEZ RELIER LES TACHES EN CLIQUANT ASSIGN ET AFFECTER LA TACHE
PRÉCÉDENTE OU/ET LA TACHE SUIVANTE

VOUS POUVEZ SÉLECTIONNER LES TACHES A VOUS POUVEZ LES RELIER, AU DIAGRAMME DE GANTT,
RELIER, CLIQUE DROITE ET CHOISIR (LINK PAR LA FLECHE NOIRE EN RAPPROCHANT LE CURSEUR
ACTIVITIES) A LA BARRE DE LA TACHE

2 ‫دورة تدریب ا�هندس‬


PAGE 35 L'INSERTION DES ACTIVITÉS

VOUS POUVEZ FRACTIONNER LA TACHE EN ÉTAPES ET AJOUTER DES COMMENTAIRES SUR CHAQUE ÉTAPE

CES TROIS FENÊTRES DONNENT LE RÉSUMÉ DE LA TACHE

 POUR COMMETTRE LES MODIFICATIONS : TOOLS > SCHEDULE ET CHOISISSEZ SCHEDULE


 CLIQUEZ F5 POUR ACTUALISER LES DONNÉES

2 ‫دورة تدریب ا�هندس‬


L'INSERTION DES ACTIVITÉS PAGE 36

À PARTIR DU VOLET (WPS & DOCS) AFFECTEZ LES DOCUMENTS DE CHAQUE TACHE

 VOUS POUVEZ NAVIGUER ENTRE LES TACHES PAR LES DEUX FLÈCHES
 COMPLÉTEZ LE RESTE DES TACHES

CHOISISSEZ (COLUMNS) A PARTIR DU


BOUTON LAY-OUT OU PAR CLIQUE DROITE
SUR LE TABLEAU

ORGANISER LES COLONNES COMME CI-DESSUS

CLIQUEZ SUR: VIEW > SHOW ON TOP > TABLE CLIQUEZ SUR
POUR AFFICHER UNIQUEMENT LE TABLEAU DANS VIEW > SHOW ON BOTTOM > NO BOTTOM LAYOUT
LA PARTIE HAUTE POUR CACHER LA PARTIE BASSE

AFIN D'ENREGISTRER CES MODIFICATION DE LAY-


OUT, CLIQUEZ SUR (SAVE AS) ET TAPEZ LE NOM
DU NOUVEAU LAY-OUT ET CLIQUEZ SAVE

2 ‫دورة تدریب ا�هندس‬


PAGE 37 L'INSERTION DES ACTIVITÉS

2 ‫دورة تدریب ا�هندس‬


PLANIFIER LE PROJET PAGE 38

PLANIFIER LE PROJET
RETOURNEZ A (ACTIVITY LAYOUT)
CLIQUE DROITE SUR LE
GANTT ET CHOISISSEZ
(BARS...)

COCHEZ (START
CONSTRAINT) ET
MODIFIEZ (LEVEL OF
EFFORT) TIMESCALE AU
(CURRENT BAR)

ACTIVEZ L'AFFICHAGE DES RELATIONS ENTRE LES TACHES


POUR VALIDER ET AFFICHER LES CHANGEMENTS CLIQUEZ :
TOOLS > SCHEDULE...

CHOISISSEZ (OPTIONS) ET COCHER (SCHEDULE AUTOMATICALLY) ET (RECALCULATE ASSIGNMENT)

MODIFIE LES COLONNES DU TABLEAU COMME CI-DESSUS ET ENREGISTRER LE LAY-OUT SOUS LE NOM
(ACTIVITY PLANIFICATION)
2 ‫دورة تدریب ا�هندس‬
PAGE 39 NIVELER LES RESSOURCES

NIVELER LES RESSOURCES

AFFICHEZ (RESOURCE USAGE PROFILE) EN BAS

VOUS CONSTATEZ QUE LA RESSOURCE (PELLE MÉCANIQUE) A


UNE SUR AFFECTATION QUI DOIT ÊTRE ÉLIMINÉ PAR UN
NIVELAGE, ALORS, CLIQUEZ : TOOLS > LEVEL RESOURCES…

COCHEZ (AUTOMATICALLY LEVEL) ET CLIQUEZ LEVEL

VOUS ALLEZ TROUVER QUE LA SUR AFFECTATION EST DISPARUE ET LA TACHE


EXCAVATION A ÉTÉ DÉPLACÉE JUSQU'À LA FIN DE LA TACHE DÉCAPAGE PARCE
QUE LE CONFLIT ÉTÉ ENTRE CES DEUX TACHES

2 ‫دورة تدریب ا�هندس‬


NIVELER LES RESSOURCES PAGE 40

VOYEZ AUSSI LA RESSOURCE (BÉTON 150 KG/M3), LE CONFLIT EST DANS LA TACHE ELLE-MÊME, DONC :
- ALLEZ AUX PARAMÈTRES DE CETTE RESSOURCE ET MODIFIEZ (MAX UNITS/TIME) A 25 M3/JOUR
- OU MODIFIEZ (UNITS/TIME) DE L'AFFECTATION A 20 M3/J
- OU MODIFIEZ LA DURÉE DE LA TACHE
VOUS CONSTATEZ QUE LA SUR AFFECTATION EST DISPARUE

UNE DOUBLE CLIQUE SUR UNE PÉRIODE, VOUS


AFFICHE L'UNITÉ/COUT DE CELLE-CI ET LE
CUMUL JUSQU'À CETTE PÉRIODE 1

DÉCOCHER (SHOW ALL PROJECTS) VOUS PERMET


DE FILTRER LES ACTIVITÉS CIBLÉES PAR
RESSOURCE OU PAR PÉRIODE DE TEMPS

CLIQUE DROITE ET CHOISISSEZ


(RESSOURCE USAGE PROFILE OPTIONS…)

UTILISEZ POUR ÉTALER OU


SERRER LE DIAGRAMME DE GANTT
ET/OU LE PROFILE

1
PÉRIODE : HEURE, JOUR, SEMAINE, MOIS, TRIMESTRE…ETC
2 ‫دورة تدریب ا�هندس‬
PAGE 41 NIVELER LES RESSOURCES

CLIQUE DROITE SUR LE TABLEAU ET


CHOISISSEZ : (GROUP & SORT…)

GROUPÉ PAR : (PROJECT) ET PUIS PAR LE


CODE DES TACHES (TYPE)

COCHER (SHRINK VERTICAL GROUPING BANDS)


CLIQUEZ OK POUR SORTIE

ORGANISEZ LA PARTIE HAUTE COMME CI-DESSUS

ENREGISTRER LAY-OUT D'ACTIVITÉ SOUS LE NOM (ANALYSE DES RESSOURCES)

2 ‫دورة تدریب ا�هندس‬


LES STATISTIQUES DU PROJET PAR TACHES PAGE 42

LES STATISTIQUES DU PROJET PAR TACHES

AFIN D'AFFICHER LES STATISTIQUES DE CHAQUE


TACHE, ALLEZ VERS :
VIEW > SHOW EN BOTTOM > ACTIVITY USAGE PROFILE

DOUBLE-CLIQUE SUR UNE PÉRIODE, UNE PETITE FENÊTRE APPARAIT PORTANT LE CHIFFRE DE LA
PÉRIODE ELLE MÊME (TOTAL) ET LE CHIFFRE CUMULÉ (CUMULATIVE)

CLIQUE DROITE SUR LE GRAPHE ET CHOISISSEZ (ACTIVITY USAGE PROFILE OPTIONS…)

(TIMESCALE…) SERT À ORGANISER L'AXE DE TEMPS

2 ‫دورة تدریب ا�هندس‬


PAGE 43 LES STATISTIQUES DU PROJET PAR TACHES

POUR AFFICHER CES INFORMATIONS EN FORME DE


TABLEAU, CHOISISSEZ
(ACTIVITY USAGE SPREADSHEET) À PARTIR DE :
VIEW > SHOW EN BOTTOM

CLIQUE DROITE SUR LE RECTANGLE ENTRE L'AXE DE TEMPS ET L'AXE DES ARTICLES DE TABLEAU A LA
PARTIE BASSE ET CHOISISSEZ (SPREADSHEET FIELDS…), SÉLECTIONNEZ (BUDGETED TOTAL COST) ET
(CUM BUDGETED TOTAL COST) POUR AFFICHER LES COUTS PRÉVISIONNELS ET LE CUMUL A CHAQUE
PÉRIODE

NOTES :

2 ‫دورة تدریب ا�هندس‬


PARAMÈTRES DIVERS PAGE 44

PARAMÈTRES DIVERS

POUR ANNULER LA DERNIÈRE OPÉRATION, MAIS CE


PARAMÈTRE EST LIMITÉ
COUPER, COPIER, COLLER

AJOUTER

SUPPRIMER

DISSOLVE UNE
TACHE 2

RENUMÉROTER
LES ACTIVITÉS ID

COPIER LA
VALEUR
SECTIONNÉE EN
HAUT SUR LES
AUTRES CASES EN
BAS

TROUVER
ET
REMPLACER

LA VÉRIFICATION ORTHOGRAPHIQUE

POUR AUTOMATISER L'ORGANISATION DE LA FENÊTRE


ACTIVE SELON LES CONDITIONS DE (GROUP & SORT)
QUAND IL Y A UNE MODIFICATION (AJOUTER,
SUPPRIMER, MODIFIER) DES DONNÉES
IL EST PRÉFÉRABLE DE DÉSACTIVER CETTE OPTION
SAUF S'IL Y A PLUSIEURS MODIFICATION A FAIRE

2
PRENDRE LE DÉBUT DE RELATION (1  2) AVEC LA FIN DE RELATION (2  3)
2 ‫دورة تدریب ا�هندس‬
PAGE 45 LE PLANNING DE REFERENCE

LE PLANNING DE REFERENCE
APRÈS LA VÉRIFICATION DÉFINITIVE DE VOTRE PROJET, VOUS POUVEZ MAINTENANT ÉTABLIR UN
PLANNING DE REFERENCE AFIN D'AVOIR UNE PLATEFORME DE COMPARAISON

ALLER VERS : PROJECT > MAINTAIN BASELINE…

CLIQUEZ ADD POUR AJOUTER UNE REFERENCE

CHOISISSEZ (SAVE A COPY OF THE PROJECT AS A


BASELINE…) ET CLIQUEZ OK

RENOMMEZ CETTE REFERENCE COMME (RESSOURCE)


ET CLIQUEZ CLOSE

ALLEZ VERS LA FENÊTRE (PROJECT), CLIQUEZ OK


SÉLECTIONNEZ LE PROJET, CLIQUE DROITE ET
CHOISISSEZ (CREATE REFLECTION…)

RENOMMEZ LA SIMULATION COMME (BUDGET), CLIQUE DROITE ET CHOISISSEZ (OPEN PROJECT)

GLOBAL CHANGE EST UN OUTILLE DE


PRIMAVERA POUR MODIFIER PLUSIEURS
VALEURS PAR UNE SEULE OPÉRATION
CONDITIONNÉE

VOUS POUVEZ CRÉER PLUSIEURS


NOUVELLES OPÉRATIONS, LES MODIFIER OU
LES EXPORTER VERS LE PC

MAINTENANT, AJOUTEZ L'OPÉRATION


(FIXER LA DATE DE DÉBUT)

2 ‫دورة تدریب ا�هندس‬


LE PLANNING DE REFERENCE PAGE 46

SÉLECTIONNEZ LA
PREMIÈRE FENÊTRE ET
CLIQUEZ ADD POUR
AJOUTER LA PARTIE (SI)

LA DEUXIÈME FENÊTRE
POUR LA PARTIE (ALORS)

LA TROISIÈME FENÊTRE
POUR LA PARTIE(SINON)

CLIQUEZ CHANGE

UN RAPPORT DE
MODIFICATION VA ÊTRE
AFFICHÉ

VOUS POUVEZ
MAINTENANT
ENREGISTRER CE
RAPPORT, ANNULER LES
MODIFICATIONS OU
ACCEPTER LES
MODIFICATIONS

OUVREZ LA FENÊTRE (PROJECT EXPENSES), SUPPRIMEZ TOUTES LES DÉPENSES COURANTES ET AJOUTEZ
LE BUDGETS DES TACHES COMME DÉPENSES
2 ‫دورة تدریب ا�هندس‬
PAGE 47 LE PLANNING DE REFERENCE

POUR CONFIRMER, ALLER VERS LA FENÊTRE (ACTIVITY)


ET OUVREZ LE LAY-OUT (COUT DES TACHES PAR CODES)

FERMER LA SIMULATION (BUDGET) ET OUVREZ LE PROJET INITIAL

ALLER VERS : PROJECT > MAINTAIN BASELINE…


ET CLIQUEZ ADD , MAIS CETTE FOIS-CI, CHOISISSEZ
(CONVERT ANOTHER PROJECT TO A NEW BASELINE)

CHOISISSEZ LA SIMULATION (BUDGET)

CLIQUEZ CLOSE

2 ‫دورة تدریب ا�هندس‬


LE PLANNING DE REFERENCE PAGE 48

POUR AFFECTER LE PLANNING DE


REFERENCE AU PROJET, ALLER VERS :
PROJECT > ASSIGN BASELINE

AFFECTEZ (BUDGET) COMME PROJECT


BASELEINE ET (RESSOURCE) COMME
PRIMARY BASELINE

OUVREZ (BARS) A PARTIR DU BOUTON (LAY-OUT) :


- AJOUTEZ (PROJECT BASELINE) ROW 2
- MODIFIEZ (PRIMARY BASELINE) ROW 3
- COCHER LES DEUX BASELINE AVEC (BASELINE
MILESTONE)

CLIQUEZ OK

OUVREZ ET DÉCOCHEZ
(KEEP CURRENT ROW HIGHTS), SÉLECTIONNEZ
(SELECT HIGH FOR ALL ROWS) ET TAPEZ 24 ET
COCHEZ (SHOW ICONS)

CLIQUEZ OK

2 ‫دورة تدریب ا�هندس‬


PAGE 49 L'ACTUALISATION MANUELLE DU PLANNING

 POUR ATTEINDRE UNE BARRE, DOUBLE CLIQUE AU NIVEAU DE CETTE TACHE DANS LE GANTT

L'ACTUALISATION MANUELLE DU PLANNING

 DÉSACTIVEZ LA PLANIFICATION AUTOMATIQUE A PARTIR DE


POUR ACTUALISER MANUELLEMENT LES TACHES, VOUS DEVEZ -D'ABORD- MODIFIER LES
PARAMÈTRES (DATE ACTUELLE DE DÉBUT/FIN, DURÉE ACTUELLE, UTILISATION ACTUELLE DES

RESSOURCES , MONTANT ACTUEL DES DÉPENSES ET LE POURCENTAGE


D'AVANCEMENT) DES TACHES CIBLÉES

OUVREZ ET CHOISISSEZ LA DATE DE MISE AJOUR (09/JAN/17) ET PLANIFIEZ LE PROJET


À TRAVERS

2 ‫دورة تدریب ا�هندس‬


L'ACTUALISATION AUTOMATIQUE DU PLANNING PAGE 50

L'ACTUALISATION AUTOMATIQUE DU PLANNING


AFIN DE NE PAS MODIFIER LES DONNÉES DE CHAQUE TACHE A PART, VOUS POUVEZ ACTUALISER LE
PLANNING AUTOMATIQUEMENT
 L'ACTUALISATION AUTOMATIQUE CONSIDÈRE QUE LES TACHES PROGRESSAIENT SELON LE
PLANNING
 LA PROCÉDURE (APPLIQUER LES VALEURS RÉELLES) TRAITE LES TACHES ACHEVÉE OU EN
COURS PAR LEURS DATES PLANIFIÉES ET ÉCRASE LES DATES ACTUELLES MÊME POUR LES
TACHES ACHEVÉES AVANT LA DATE DE DERNIER MISE A JOUR
 L'INTERVALLE D'APPLICATION DU (METTRE A JOUR DE LA PROGRESSION) COMMENCE PAR
LA DERNIÈRE DATE DE MISE AJOUR JUSQU'À LA DATE ACTUELLE DE MISE A JOUR EN
ÉCRASANT LES DATES ACTUELLES PAR LES DATES PLANIFIÉES UNIQUEMENT POUR LES
TACHES EN COURS

A. APPLIQUER LES VALEURS RÉELLES

CETTE PROCÉDURE DONNE UN AVANCEMENT POUR LES TACHES DONT L'OPTION (AUTO COMPUTE
ACTUALS) EST COCHÉE, SOIT VERS L'AVANT OU VERS L'ARRIÈRE

ALLEZ VERS : TOOLS > APPLY ACTUALS…

CHOISISSEZ LE PROJET
ET (15/ JAN/17) DATE DE MISE
A JOUR

VOUS POUVEZ METTRE UNE


SEULE DATE DE MISE A JOUR
POUR TOUS LES PROJETS OU
CHAQUE PROJET A PART

LA DURÉE RESTANTE PEUT


ÊTRE CALCULÉE SELON SON
(ACTIVITY DURATION TYPE)
OU TRAITÉE COMME (FIXED
UNIT/TIME OU FIXED UNITS)

CLIQUEZ APPLY

SI LA DATE EST AU FUTURE, CETTE FENÊTRE CLIQUEZ OK


S'AFFICHE
CLIQUEZ YES

VOUS POUVEZ MAINTENANT MODIFIER MANUELLEMENT LES DONNÉES DE CHAQUE TACHE A PARTIR DU
VOLET (STATUS, RESOURCES, EXPENSES, STEPS)
VOUS POUVEZ CONSULTER L'ÉTATS DE LA TACHE A PARTIR DU VOLET (SUMMARY)

2 ‫دورة تدریب ا�هندس‬


PAGE 51 L'ACTUALISATION AUTOMATIQUE DU PLANNING

2 ‫دورة تدریب ا�هندس‬


L'ACTUALISATION AUTOMATIQUE DU PLANNING PAGE 52

AFFICHEZ CE LAY-
OUT ET
L'ENREGISTREZ
SOUS LE NOM
(ÉTAT ACTUEL 1)

B. METTRE A JOUR DE LA PROGRESSION

SI LE PROJET EST MARCHÉ COMME PRÉVU, UTILISEZ LA PROCÉDURE


(UPDATE PROGRESS) POUR ACTUALISER LES AVANCEMENTS DES TACHES
CHOISISSEZ : TOOLS > UPDATE PROGRESS…

CHOISISSEZ LA DATE DE (01/FÉV/17) COMME DATE DE MISE A JOUR

UNE BANDE D'ÉCLAIRAGE OCCUPE LA PÉRIODE DE LA DERNIER DATE DE MISE A JOUR JUSQU'À LA
NOUVELLE DATE DE MISE A JOUR

VOUS POUVEZ APPLIQUER LE CALCUL D'AVANCEMENT SUR LES TACHES SÉLECTIONNÉES OU SUR TOUTES
LES TACHES

LA DURÉE RESTANTE DES TACHES PEUT ÊTRE CALCULÉE SELON LE (ACTIVITY DURATION TYPE) OU
TRAITER LES TACHES COMME (FIXED UNIT/TIME OU FIXED UNITS)

2 ‫دورة تدریب ا�هندس‬


PAGE 53 L'ACTUALISATION AUTOMATIQUE DU PLANNING

POUR CALCULER LE POURCENTAGE D'AVANCEMENT


D'UNE TACHE OÙ IL Y A DES (ÉTAPES) :
- LE TYPE DE POURCENTAGE DE LA TACHE DOIT
ÊTRE (PHYSICAL)
- L'OPTION (ACTIVITY PERCENT COMPLETE BASED
ON ACTIVITY STEPS) DOIT ÊTRE COCHÉE

POUR COCHER CETTE OPTION ALLER À LA FENÊTRE


(PROJECT) SÉLECTIONNEZ LE PROJET ET AFFICHER
LE VOLET (CALCULATIONS) DANS LA PARTIE BASSE

COCHEZ LES 4 PREMIÈRES ÉTAPES DE LA TACHE


(LG07) COMME TERMINÉES ET LA 5ÈME COMME 50%

MODIFIER (ACTUAL UNITS) DU (BA350) DE 120 M3 A 150 M3

CONSULTER LE VOLET (STATUS) POUR LIRE OU MODIFIER L'ÉTAT DE LA TACHE (DURÉE, AVANCEMENT,
LE NOMBRE DES RESSOURCES…)

2 ‫دورة تدریب ا�هندس‬


L'ACTUALISATION AUTOMATIQUE DU PLANNING PAGE 54

VOUS POUVEZ
MAINTENANT
MODIFIER
MANUELLEMENT
LES DONNÉES DE
CHAQUE TACHE A
PARTIR DES VOLETS
(STATUS,
RESOURCES,
EXPENSES, STEPS)

OU VOUS POUVEZ
CONSULTER L'ÉTAT
DE LA TACHE A
PARTIR DU VOLET
(SUMMARY)

ORGANISEZ CE
LAY-OUT
COMME L'IMAGE A
GAUCHE ET
ENREGISTREZ-LE
SOUS LE NOM
(ÉTAT ACTUEL 2)

2 ‫دورة تدریب ا�هندس‬


PAGE 55 LA VALEUR ACQUISE

LA VALEUR ACQUISE
ON VA PRENDRE COMME EXEMPLE LA TACHE (LG07-BÉTONNAGE DES FONDATIONS) :

16/JAN 01/FEV 12/FEV

LE PLANNINGS DE REFERENCE 60 % 100 %

DÉPENSES
AC = 1 710 000.00 DA ATC = 2 850 000.00 DA

PAYEMENT PC = EV = 4 800 000.00 DA BAC = 8 000 000.00 DA

CPI = IPC : INDICE DE PERFORMANCE DES COUTS = EV / AC = 4 800 000.00 / 1 710 000.00 = 2.8

CV = EV - AC = 4 800 000.00 - 1 710 000.00 = 3 090 000.00 DA

SPI = IPP : INDICE DE PERFORMANCE DU PLANNING = EV / PC = 4 800 000.00 / 4 800 000.00 =1

SV = EV – PC = 4 800 000.00 - 4 800 000.00 = 0.00 DA

2 ‫دورة تدریب ا�هندس‬


LA VALEUR ACQUISE PAGE 56

16/JAN 01/FEV 12/FEV

L'ÉTAT ACTUEL
67.5 % 100 %

AC = 2 100 000.00 DA ATC = 2 850 000.00 DA

EV = 5 400 000.00 DA BAC = 8 000 000.00 DA

CPI = IPC : INDICE DE PERFORMANCE DES COUTS = EV / AC = 5 400 000.00 / 2 100 000.00 = 2.57

CV = EV - AC = 5 400 000.00 - 2 100 000.00 = 3 300 000.00 DA

SPI = IPP : INDICE DE PERFORMANCE DU PLANNING = EV / PC = 5 400 000.00 / 4 800 000.00 ≈ 1.13

SV = EV - PC = 5 400 000.00 - 4 800 000.00 = 600 000.00 DA

 CES CALCULS SONT VALABLES POUR LES TACHES, LES WBS ET LES PROJETS

2 ‫دورة تدریب ا�هندس‬


PAGE 57 LA PRÉSENTATION DES RÉSULTATS

LA PRÉSENTATION DES RÉSULTATS

220,000.00 DA 220,000.00 DA

100,000.00 DA 100,000.00 DA

DANS LA FENÊTRE (ACTIVITY)


OUVREZ LE LAY-OUT (ANALYSE
DES TACHES PROFILE) ET
ACCÉDEZ AUX PARAMÈTRES
(ACTIVITY USAGE PROFILE
OPTIONS) PAR CLIQUE DROITE
SUR LE GRAPHE

MODIFIEZ LES PARAMÈTRES


COMME L'IMAGE A GAUCHE
CLIQUEZ OK

VOUS POUVEZ AFFICHER LES


DONNÉES D'UNE SEULE TACHE OU
CELLES-CI DE TOUTES LES
TACHES

DOUBLE CLIQUE SUR LES BARRES


DE MOIS DE (JANVIER) VOUS
DONNE UNE PETITE FENÊTRE
SERT À AFFICHER LES
INFORMATION DU CETTE PÉRIODE

2 ‫دورة تدریب ا�هندس‬


LA PRÉSENTATION DES RÉSULTATS PAGE 58
VOUS POUVEZ AUSSI VOIR LA
PRÉSENTATION DU PROJET ENTIER SUR LA
FENÊTRE (TRACKING), MAIS AVANT
L'OUVERTURE DE CETTE FENÊTRE VOUS
DEVEZ RÉSUMER LE PROJET PAR
(SUMMARIZE) A PARTIR DE (TOOLS)

AFIN D'OUVRIR LA FENÊTRE DE SUIVI DES PROJETS (TRACKING),


ALLEZ VERS : ENTERPRISE > TRACKING

OUVREZ / CRÉER LE LAY-OUT (EARNED VALUE CURVES)

2,936,000.00 DA 2,936,000.00 DA

40,000.00 DA 40,000.00 DA

CLIQUE DROITE SUR LE GRAPHE ET


MODIFIEZ LES PARAMÈTRES COMME
L'IMAGE A GAUCHE

DOUBLE CLIQUE SUR LA BARRE DU


MOIS DE (JANVIER) VOUS AFFICHE LA
PETITE FENÊTRE DES DONNÉES

2 ‫دورة تدریب ا�هندس‬


PAGE 59 EXERCICE
CLIQUEZ SUR (DISPLAY – PROJECT
GANTT/PROFILE)

À PARTIR DE (LAY-OUT) CRÉEZ, OUVREZ OU


ENREGISTREZ UN LAY-OUT

(TOP LAY-OUT OPTIONS) VOUS PERMET DE


MODIFIER LES BARRES DE GANTT, LES
COLONNES, LE POLICE ET LES COULEURS,
LE FILTRAGE, LE GROUPAGE ET LE TRIAGE

(HIDE /LEFT COLUMNS-TOP WINDOW-


BOTTOM WINDOW) VOUS PERMET DE
CACHER OU AFFICHER LA PARTIE COLONNE,
LA PARTIE HAUTE ET LA PARTIE BASSE

EXERCICE
APRÈS L'ACTUALISATION D'ÉTAT DU PROJET AU CHANTIER, VOUS AVAIT REÇU LE RAPPORT
SUIVANT :

DATE DE MISE A JOUR : 2 / AVR / 17 08:00

DATE DE DURÉE
ID TACHE DATE DE FIN %
DÉBUT ACTUELLE
LG07 BÉTONNAGE DES FONDATIONS 16/JAN/17 12/FEV/17 20 J 100%

LG08 REMBLAIEMENT 19/FEV/17 23/FEV/17 5J 100%

LG09 ASSAINISSEMENT ET PLATE FORME - - - 0%


25 J
LG010 STRUCTURE EN ÉLÉVATION 26/FEV/17 - 30%
RESTE 35 J

LG011 SECONDE ŒUVRE - - - 0%

LG012 RÉCEPTION DES TRAVAUX // - // 0%

 INTRODUISEZ CES MODIFICATIONS SUR PRIMAVERA

2 ‫دورة تدریب ا�هندس‬


‫‪EXERCICE‬‬ ‫‪PAGE 60‬‬

‫دورة تدریب ا�هندس ‪2‬‬


‫‪PAGE 61‬‬ ‫‪EXERCICE‬‬

‫دورة تدریب ا�هندس ‪2‬‬


‫‪EXERCICE‬‬ ‫‪PAGE 62‬‬

‫دورة تدریب ا�هندس ‪2‬‬


PAGE 63 REPORTING ET COMMUNICATION DES DONNÉES

REPORTING ET COMMUNICATION DES DONNÉES


POUR COMMUNIQUER LES OUTPUTS DU PROJET AVEC LES DIFFÉRENTS INTERVENANTS, PRIMAVERA
VOUS PERMET DE GÉNÉRER LES RAPPORTS, IMPRIMER LES TABLEAUX ET LES GRAPHES, EXPORTER
LES LAY-OUTS ET LES DONNÉES.

A. LES RAPPORTS

POUR OUVRIR LA FENÊTRE DES RAPPORTS, ALLEZ VERS :


TOOLS > REPORTS > REPORTS
APRÈS L'OUVERTURE DE CETTE FENÊTRE, RETOURNEZ AU :
TOOLS > REPORTS > REPORTS GROUPS…
AJOUTEZ LES CATÉGORIES EN CLIQUANT ADD , UTILISEZ LES 4 FLÈCHES POUR
LES STRUCTURER
À PARTIR DU DISPLAY : REPORT GROUPS... VOUS POUVEZ CHERCHER,
IMPRIMER OU MODIFIER LE POLICE DE LA LISTE
CLIQUEZ CLOSE POUR SORTIR

SUR LA FENÊTRE (REPORTS), CLIQUEZ SUR F5 POUR


L'ACTUALISER SI LES CATÉGORIES AJOUTÉES SONT PAS
ENCORE AFFICHÉES

I. LE PROJET EN CHIFFRE

CHOISISSEZ LE CATÉGORIE (RAPPORTS DU PROJET) ET CLIQUEZ SUR


SÉLECTIONNEZ (NEW REPORT) ET CLIQUEZ NEXT
SÉLECTIONNEZ (WBS) ET CLIQUEZ NEXT
LAISSEZ QUE (WBS) DANS LE VOLET (SELECTED SUBJECT AREAS) ET CLIQUEZ NEXT

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 64

SÉLECTIONNEZ (WBS) ET CLIQUEZ COLUMNS POUR DÉTERMINER LES COLONNES A AFFICHER


VOUS POUVEZ MODIFIER LES PARAMÈTRES DE CHAQUE COLONNE À TRAVERS EDIT COLUMNS…
CLIQUEZ APPLY OU OK

CLIQUEZ NEXT

TAPEZ LE NOM DU RAPPORTS ET CLIQUEZ NEXT

COCHEZ (FORMAT NUMBERS) ET CLIQUEZ RUN REPORT…

À PARTIR DE CETTE FENÊTRE VOUS


POUVEZ APERCEVOIR LE RAPPORT,
L'IMPRIMER DIRECTEMENT SUR
L'IMPRIMANT, L'ENVOYER PAR EMAIL,
L'EXPORTER EN FORMAT HTML OU EN
FORMAT DE TEXTE

VOUS POUVEZ AJOUTER DES NOTES


SUR LE RAPPORT

SÉLECTIONNEZ (PRINT PREVIEW) ET


CLIQUEZ OK

2 ‫دورة تدریب ا�هندس‬


PAGE 65 REPORTING ET COMMUNICATION DES DONNÉES

*
FERMEZ LE RAPPORT ET CLIQUEZ NEXT

CLIQUEZ SAVE REPORT


POUR ENREGISTRER LE
RAPPORT

CLIQUEZ FINISH

II. LE BUDGET DES TACHES

POUR CRÉER LE DEUXIÈME RAPPORT, ALLEZ VERS


LA FENÊTRE (ACTIVITY)

CLIQUE DROITE SUR LA BERRE DES ICONES


COCHEZ ,

CLIQUEZ SUR LA PARTIE TABLEAU

CLIQUEZ SUR

*
SÉLECTIONNEZ (USE CURRENT SCREEN) ET CLIQUEZ NEXT
SÉLECTIONNEZ (ACTIVITIES) ET CLIQUEZ NEXT
NE LAISSEZ QUE (ACTIVITIES) DANS LE VOLET (SELECTED SUBJECT AREAS) ET CLIQUEZ NEXT

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 66

CLIQUEZ SUR COLUMNS…

VOUS CONSTATEZ QUE LES COLONNES SONT


ORGANISÉES DANS LE VOLET (SELECTED OPTIONS)

VOUS POUVEZ MODIFIER LES PARAMÈTRES DE


CHAQUE COLONNE

CLIQUEZ OK

CLIQUEZ MAINTENANT SUR GROUP & SORT…

CLIQUEZ OK

ET CLIQUEZ NEXT

DONNEZ CE RAPPORT LE NOM SUIVANT : ET CLIQUEZ NEXT

CLIQUEZ RUN REPORT ET SÉLECTIONNEZ (PRINT PREVIEW)

2 ‫دورة تدریب ا�هندس‬


PAGE 67 REPORTING ET COMMUNICATION DES DONNÉES

DANS L'AFFICHAGE DU RAPPORT, CLIQUEZ SUR ( PAGE SETUP)


VOUS POUVEZ, À TRAVERS
CETTE FENÊTRE, AJUSTER
LA MISE EN PAGE DU
RAPPORT (DIMENSION, LES
MARGES, ENTÊTES ET PIEDS
DE PAGE…)

CLIQUEZ APPLY POUR


APPLIQUER LES
MODIFICATIONS ET
CLIQUEZ OK

FERMEZ LE RAPPORT ET
CLIQUEZ NEXT

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 68

CLIQUEZ SAVE REPORT ET CLIQUEZ FINISH

POUR RENOMMER OU POSITIONNER LE RAPPORT SOUS LA CATÉGORIE (RAPPORTS DES TACHES),


SÉLECTIONNEZ LE RAPPORT ET MODIFIER SES PARAMÈTRES DANS LA PARTIE BASSE DE LA FENÊTRE

III. LA LISTE DES RESSOURCES


RETOURNEZ A LA FENÊTRE DES RAPPORTS, SÉLECTIONNEZ (RAPPORTS DES RESSOURCES)
CLIQUEZ

SÉLECTIONNEZ (RESSOURCES) ET CLIQUEZ NEXT

SÉLECTIONNEZ LES COLONNES A AFFICHER DANS LE


RAPPORT

VOUS POUVEZ MODIFIER LES PARAMÈTRES DE CHAQUE


COLONNE A PARTIR DU BOUTON EDIT COLUMN…

CLIQUEZ OK

2 ‫دورة تدریب ا�هندس‬


PAGE 69 REPORTING ET COMMUNICATION DES DONNÉES

CLIQUEZ SUR GROUPE & SORT...


ET GROUPEZ LES RESSOURCES PAR
LES TYPES DE RESSOURCE

CLIQUEZ OK

CLIQUEZ NEXT

ENREGISTREZ LE RAPPORT SOU LE NOM :

LANCEZ LE RAPPORT

FERMEZ CETTE FENÊTRE ET ENREGISTREZ LE RAPPORT

VOUS ALLEZ TROUVEZ CE RAPPORT SOUS LA CATÉGORIE (RAPPORTS DES RESSOURCES)

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 70
IV. LA LISTE DES DÉPENSES
SUR LA FENÊTRE DES RAPPORTS
SÉLECTIONNEZ LA CATÉGORIE (RAPPORTS DES DÉPENSES) ET
CLIQUEZ

SÉLECTIONNEZ (EXPENSES CATEGORIES > PROJECT EXPENSES)

*
ORGANISEZ LES COLONNES À AFFICHER COMME L'IMAGE CI-DESSUS

DONNEZ CE RAPPORT LE NOM SUIVANT:


ENREGISTREZ CE RAPPORT

2 ‫دورة تدریب ا�هندس‬


PAGE 71 REPORTING ET COMMUNICATION DES DONNÉES
V. LE CALENDRIER DES PAYEMENTS
POUR CRÉER UN RAPPORT QUI VA ÊTRE ENVOYÉ AU MAITRE DE L'OUVRAGE
SÉLECTIONNEZ LA CATÉGORIE (RAPPORTS DE MAITRE DE L'OUVRAGE) ET CLIQUEZ SUR

SÉLECTIONNEZ (ACTIVITIES) ET COCHER (TIME DISTRIBUTED DATA)

AFFICHEZ DEUX COLONNES


(ACTIVITIY ID) ET (ACTIVITY NAME)

AFFECTER CES PARAMÈTRES AUX


TIMESCALE… ET TIME INTERVAL FIELDS…

CLIQUEZ OK POUR FERMER CES FENÊTRES

CLIQUEZ NEXT

ENREGISTRER LE RAPPORT SOUS LES NOM :

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 72

 L'UTILISATION D'UN RAPPORT PEUT ÊTRE :


(GLOBAL : TOUS LES PROJETS PEUVENT UTILISER CE RAPPORT)
(CURRENT PROJECT : CE RAPPORT EST DESTINÉ SEULEMENT POUR CE PROJET)

VOUS POUVEZ PACKAGER PLUSIEURS RAPPORTS SOUS UN SEUL LOT DES RAPPORTS
ALLEZ VERS : TOOLS > REPORTS > BATCH REPORTS…

CLIQUE DROITE SUR LA FENÊTRE DES RAPPORTS


VOUS PERMET DE CHOISIR ENTRE LE LANCEMENT
DU RAPPORT SÉLECTIONNÉ OU LE LANCEMENT
D'UN LOT DES RAPPORTS

2 ‫دورة تدریب ا�هندس‬


PAGE 73 REPORTING ET COMMUNICATION DES DONNÉES
B. IMPRESSION DES LAY-OUTS

AVEC PRIMAVERA VOUS POUVEZ IMPRIMER TOUS CE QUI EST AFFICHÉES, EN ENSEMBLE OU
CHAQUE FENÊTRE SÉPARÉE
OUVREZ (ANALYSE DES TACHES PROFILE SUIVI) LAY-OUT DE LA FENÊTRE (ACTIVITY)

ALLEZ VERS : ET CLIQUEZ SUR ( PAGE SETUP) EN HAUT DROITE DE LA FENÊTRE


AFFICHÉE

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 74

2 ‫دورة تدریب ا�هندس‬


PAGE 75 REPORTING ET COMMUNICATION DES DONNÉES

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 76

2 ‫دورة تدریب ا�هندس‬


PAGE 77 REPORTING ET COMMUNICATION DES DONNÉES
POUR AFFICHER ET IMPRIMER LE LAYOUT (RÉSEAU – TACHE)
ALLER VERS :
VIEW > SHOW EN TOP > ACTIVITY NETWORK

CLIQUE DROITE SUR LA FENÊTRE


VOUS PERMET D'ACCÉDER A
(ACTIVITY NETWORK OPTIONS), OU
VOUS POUVEZ MODIFIER LA FORME
ET LES INFORMATIONS AFFICHÉES
SUR LES BOX

ENREGISTREZ CE LAY-OUT SOUS LE


NOM (LE RÉSEAU-TACHE)

À PARTIR DE : VIEW > ACTIVITY NETWORK


VOUS POUVEZ ENREGISTRER/EXPORTER LA
DISPOSITION DES TACHES SUR L'ÉCRAN EN
CLIQUANT SUR (SAVE NETWORK POSITION…)

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 78
C. CHECK IN / CHECK OUT

I. CHECK OUT
AVANT DE CHECK OUT, CRÉEZ UNE COPIE DE VOTRE PROJET SUR LE MÊME EPS

POUR RETIRER LE PROJET, ALLER VERS : FILE > CHECK OUT

COCHEZ LE PROJET A RETIRER ET CLIQUEZ NEXT

CHOISISSEZ L'EMPLACEMENT OU VOUS ALLEZ ENREGISTRER LE FICHIER

CLIQUEZ FINISH , SI LE CHECK OUT EST SUCCÈS CLIQUEZ CLOSE

 QUAND LE PROJET EST CHECK OUT, VOUS NE POUVEZ PAS LE MODIFIER

II. CHECK IN

POUR CHECK IN LE PROJET, CLIQUEZ :


FILE > CHECK IN…

CHOISISSEZ LE FICHIER A IMPORTER, ET APRÈS, LE


MODE DE L'IMPORTATION ET LE PROJECT CIBLÉ *
 CHOISISSEZ (REPLACE EXISTING PROJECT) SUPPRIME LES PLANNINGS DE RÉFÉRENCES

2 ‫دورة تدریب ا�هندس‬


PAGE 79 REPORTING ET COMMUNICATION DES DONNÉES

MODIFIEZ LES OPTIONS DE L'IMPORTATION


S'IL EST NÉCESSAIRE

CLIQUEZ FINISH POUR COMMENCER


L'IMPORTATION

 POUR ÊTRE FAMILIARISÉ AVEC CETTE


OPÉRATION, ESSAYEZ PLUSIEURS
FOIS AVANT TRAVAILLER SUR UN
PROJET RÉEL

VOILA, LE PROJET ET CHECK IN,


MAINTENANT, VOUS POUVEZ LE MODIFIER

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 80
D. EXPORTATION / IMPORTATION

VOUS POUVEZ IMPORTER TOUS LES ÉLÉMENTS EXPORTÉS

I. EXPORTER XER

FILE > EXPORT

SÉLECTIONNEZ (PRIMAVERA PM-XER)

SÉLECTIONNEZ LES PROJETS À EXPORTER

SÉLECTIONNEZ L'EMPLACEMENT DE
L'EXPORTATION

CLIQUEZ CLOSE

II. EXPORTER XLS

SÉLECTIONNEZ FILE > EXPORTER


CHOISISSEZ (SPREADSHEET-XLS)

CHOISISSEZ LES DONNÉES À EXPORTER

CHOISISSEZ LES PROJET A EXPORTER

SÉLECTIONNEZ / MODIFIEZ LES


PARAMÈTRES DE L'EXPORTATION
EN CLIQUANT MODIFY

2 ‫دورة تدریب ا�هندس‬


PAGE 81 REPORTING ET COMMUNICATION DES DONNÉES

SÉLECTIONNEZ L'EMPLACEMENT
DE L'EXPORTATION

CLIQUEZ FINISH CLIQUEZ CLOSE

III. EXPORTER MS PROJECT

SÉLECTIONNEZ LE TYPE DE
FICHIER A EXPORTER
SÉLECTIONNEZ LE TYPE DES DONNÉES A EXPORTER

SÉLECTIONNEZ LES PROJETS À EXPORTER

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 82

SÉLECTIONNEZ/MODIFIEZ LES PARAMÈTRES DE L'EXPORTATION AFIN DE COMPTABILISER LE FICHIER


AVEC MS PROJECT

2 ‫دورة تدریب ا�هندس‬


PAGE 83 REPORTING ET COMMUNICATION DES DONNÉES

IV. EXPORTER LAY-OUTS / RAPPORTS / GLOBAL CHANGE

EXPORTEZ LES LAY-OUTS DE (PROJECT) EXPORTEZ LES LAY-OUTS DE (ACTIVITY)

EXPORTEZ LES LAY-OUTS DE (TRACKING)

SÉLECTIONNEZ LES RAPPORTS A EXPORTER, CLIQUE EXPORTEZ LES PARAMÈTRES DE


DROITE, ET CHOISISSEZ (EXPORT) (GLOBAL CHANGE)

2 ‫دورة تدریب ا�هندس‬


REPORTING ET COMMUNICATION DES DONNÉES PAGE 84
E. PUBLIER LE PROJET EN SITE WEB

2 ‫دورة تدریب ا�هندس‬


PAGE 85 ANNEXE A : LES RACCOURCIS DU CLAVIER

LE DOSSIER DES FICHIERS EXPORTÉS

ANNEXE A : LES RACCOURCIS DU CLAVIER

TOOLS MENU (ALT+T) FILE MENU (ALT+F)


<F9> PLANIFIER CTRL+N NOUVEAU
<SHIFT> + <F9> LISSER LES RESSOURCES CTRL+O OUVRIR
DÉSACTIVER ORGANISATION CTRL+W FERMER
<SHIFT> + <F12>
AUTOMATIQUE CTRL+P IMPRIMER
<F10> APPLIQUER LES CHANGEMENT
EDIT MENU (ALT+E) <F5> ACTUALISER
CTRL+Z ANNULER
CTRL+X COUPER
CTRL+C COPIER VIEW MENU (ALT+V)
CTRL+V COLLER ALT+<F1> CONSEIL AIDE
<INS> AJOUTER
<DEL> SUPPRIMER HELP MENU (ALT+H)
CTRL+F CHERCHER CTRL+<F1> AIDE LOCAL
<F3> TROUVER SUIVANT CTRL+ALT+<F1> AIDE EN LIGNE
CTRL+R REMPLACER
<F7> ORTHOGRAPHIE
CTRL +  DÉPLACER/ORGANISER
CTRL + « - » RÉDUIRE TOUT
CTRL + « + » DÉVELOPPER TOUT
CTRL+A SÉLECTIONNER TOUT
CTRL+E REMPLIR VERS LE BAS
SÉLECTIONNER 1+
SÉLECTIONNER 1 VERS 20
APPUYER SHIFT + 20
SÉLECTIONNER 1+
SÉLECTIONNER 1 ET 20
APPUYER CTRL+ 20

2 ‫دورة تدریب ا�هندس‬