Vous êtes sur la page 1sur 166

RAPPORT DE PRODUCTION DU TUNNEL PRINCIPAL

OCTOBRE 2022

RAPPORT DE PRODUCTION DU TUNNEL PRINCIPAL


INDEX
1. LOCALISATION GRAPHIQUE DU TBM
2. GRAPHIQUES DE PRODUCTION
3. SUIVI DE PLANNING
4. RAPPORT GRAPHIQUE DE SUIVI
5. FICHES DE CONTRÔLE

1. LOCALISATION GRAPHIQUE DU TBM

Arrivé´é du tunnéliér TBM, au PV 10


2. GRAPHIQUES DE PRODUCTION

EXTENSION EL HARRACH CE

CON

EQUIPES
DATE Nº D'ANNEAU PK (m)

20-Dec-2019 -6 3,872.320
21-Dec-2019 -5 3,873.860
22-Dec-2019 -5 3,873.860
23-Dec-2019 -5 3,873.860
24-Dec-2019 -5 3,873.860
25-Dec-2019 -5 3,873.860
26-Dec-2019 -5 3,873.860
27-Dec-2019 -5 3,873.860
28-Dec-2019 -5 3,873.860
29-Dec-2019 -5 3,873.860
30-Dec-2019 -5 3,873.860
31-Dec-2019 -5 3,873.860
01-Jan-2020 -5 3,873.860
02-Jan-2020 -5 3,873.860
03-Jan-2020 -5 3,873.860
04-Jan-2020 -5 3,873.860
05-Jan-2020 -4 3,874.936
06-Jan-2020 -4 3,875.386
07-Jan-2020 -3 3,875.792
08-Jan-2020 -2 3,878.038
09-Jan-2020 -2 3,878.438
10-Jan-2020 -1 3,878.838
11-Jan-2020 -1 3,879.555
12-Jan-2020 1 3,881.983
13-Jan-2020 2 3,882.872
14-Jan-2020 3 3,886.441
15-Jan-2020 4 3,887.411
16-Jan-2020 4 3,887.411
17-Jan-2020 4 3,887.411
18-Jan-2020 4 3,887.411
19-Jan-2020 4 3,887.411
20-Jan-2020 4 3,888.491
21-Jan-2020 5 3,890.727
22-Jan-2020 6 3,891.105
23-Jan-2020 7 3,892.725
24-Jan-2020 7 3,893.125
25-Jan-2020 7 3,893.525
26-Jan-2020 8 3,894.472
27-Jan-2020 9 3,896.117
28-Jan-2020 10 3,898.439
29-Jan-2020 11 3,900.669
30-Jan-2020 12 3,900.669
31-Jan-2020 12 3,900.669
01-Feb-2020 12 3,900.669
02-Feb-2020 12 3,900.669
03-Feb-2020 12 3,902.432
04-Feb-2020 13 3,903.963
05-Feb-2020 13 3,903.963
06-Feb-2020 13 3,905.058
07-Feb-2020 13 3,905.058
08-Feb-2020 13 3,905.058
09-Feb-2020 13 3,905.058
10-Feb-2020 13 3,905.058
11-Feb-2020 13 3,905.058
12-Feb-2020 13 3,905.058
13-Feb-2020 13 3,905.058
14-Feb-2020 13 3,905.058
15-Feb-2020 14 3,905.676
16-Feb-2020 14 3,905.676
17-Feb-2020 15 3,907.631
18-Feb-2020 16 3,909.036
19-Feb-2020 17 3,910.738
20-Feb-2020 17 3,910.738
21-Feb-2020 17 3,910.738
22-Feb-2020 17 3,910.738
23-Feb-2020 17 3,910.817
24-Feb-2020 17 3,912.447
25-Feb-2020 18 3,912.542
26-Feb-2020 18 3,912.542
27-Feb-2020 18 3,912.542
28-Feb-2020 18 3,912.542
29-Feb-2020 18 3,912.542
01-Mar-2020 18 3,912.668
02-Mar-2020 18 3,912.714
03-Mar-2020 18 3,912.746
04-Mar-2020 18 3,912.819
05-Mar-2020 18 3,912.819
06-Mar-2020 18 3,912.819
07-Mar-2020 18 3,912.819
08-Mar-2020 18 3,912.824
09-Mar-2020 18 3,912.824
10-Mar-2020 18 3,912.824
11-Mar-2020 18 3,912.824
12-Mar-2020 18 3,912.824
13-Mar-2020 18 3,912.824
14-Mar-2020 18 3,912.824
15-Mar-2020 18 3,912.824
16-Mar-2020 18 3,912.824
17-Mar-2020 18 3,912.824
18-Mar-2020 18 3,912.824
19-Mar-2020 18 3,912.824
20-Mar-2020 18 3,912.824
21-Mar-2020 18 3,912.848
22-Mar-2020 18 3,912.848
23-Mar-2020 18 3,912.967
24-Mar-2020 18 3,912.967
25-Mar-2020 18 3,914.484
26-Mar-2020 18 3,914.788
27-Mar-2020 19 3,914.788
28-Mar-2020 19 3,914.791
29-Mar-2020 19 3,914.921
30-Mar-2020 19 3,915.037
31-Mar-2020 20 3,916.263
01-Apr-2020 21 3,917.099
02-Apr-2020 22, 23 3,919.880
03-Apr-2020 23 3,919.880
04-Apr-2020 24 3,921.680
05-Apr-2020 25 3,923.589
06-Apr-2020 26 3,927.041
07-Apr-2020 27 3,928.852
08-Apr-2020 28, 29 3,930.672
09-Apr-2020 30, 31 3,935.330
10-Apr-2020 32, 33 3,939.303
11-Apr-2020 34.35 3,943.280
12-Apr-2020 35 3,943.280
13-Apr-2020 35 3,943.280
14-Apr-2020 36, 37 3,948.433
15-Apr-2020 38, 39, 40 3,952.240
16-Apr-2020 40 3,952.378
17-Apr-2020 40 3,952.378
18-Apr-2020 40 3,952.378
19-Apr-2020 40 3,952.378
20-Apr-2020 40 3,952.378
21-Apr-2020 40 3,952.378
22-Apr-2020 40 3,952.379
23-Apr-2020 41, 42, 43, 44 3,961.310
24-Apr-2020 44 3,961.310
25-Apr-2020 45, 46, 47, 48 3,963.058
26-Apr-2020 49, 50, 51, 52 3,968.422
27-Apr-2020 52 3,973.931
28-Apr-2020 53 3,975.695
29-Apr-2020 54 3,978.363
30-Apr-2020 54 3,978.363
01-May-2020 3,978.363
02-May-2020 55 3,979.298
03-May-2020 56, 57, 58 3,984.711
04-May-2020 59, 60, 61 3,990.625
05-May-2020 62, 63, 64, 65 3,997.331
06-May-2020 66, 67, 68, 69 3,999.784
07-May-2020 70, 71, 72 4,006.371
08-May-2020 73 4,011.751
09-May-2020 73 4,011.751
10-May-2020 74, 75 4,013.899
11-May-2020 76, 77, 78, 79 4,022.612
12-May-2020 80, 81, 82, 83 4,029.818
13-May-2020 84, 85, 86 4,037.743
14-May-2020 87, 88, 89, 90, 91, 92, 93 4,047.665
15-May-2020 93 4,047.665
16-May-2020 94, 95, 96 4,053.250
17-May-2020 97, 98, 99 4,058.307
18-May-2020 100, 101 4,062.261
19-May-2020 102, 103, 104 4,066.627
20-May-2020 105, 106, 107, 108, 109, 110 4,078.469
21-May-2020 111, 112, 113, 114, 115, 116 4,084.005
22-May-2020 117, 118 4,091.149
23-May-2020 119 4,094.833
24-May-2020 119 4,094.833
25-May-2020 119 4,094.833
26-May-2020 119 4,094.833
27-May-2020 119 4,094.833
28-May-2020 119 4,094.833
29-May-2020 119 4,094.833
30-May-2020 119 4,094.833
31-May-2020 119 4,094.833
01-Jun-2020 119 4,094.834
02-Jun-2020 120 4,098.301
03-Jun-2020 121, 122, 123, 124 4,105.521
04-Jun-2020 125, 126, 127, 128, 129 4,114.637
05-Jun-2020 130 4,116.437
06-Jun-2020 130 4,116.437
07-Jun-2020 131, 132, 133, 134, 135, 136, 137 4,129.011
08-Jun-2020 138, 139, 140, 141, 142, 143 4,138.127
09-Jun-2020 143 4,138.127
10-Jun-2020 143 4,138.183
11-Jun-2020 143 4,138.183
12-Jun-2020 143 4,138.183
13-Jun-2020 143 4,138.183
14-Jun-2020 143 4,138.183
15-Jun-2020 143 4,138.183
16-Jun-2020 143 4,138.183
17-Jun-2020 143 4,138.183
18-Jun-2020 143 4,138.183
19-Jun-2020 143 4,138.183
20-Jun-2020 143 4,138.183
21-Jun-2020 144, 145, 146 4,144.958
22-Jun-2020 147,148,149,150,151 4,154.275
23-Jun-2020 152, 153, 154, 155, 156, 157,158 4,163.774
24-Jun-2020 159, 160, 161, 162, 163, 164 4,175.897
25-Jun-2020 165, 166, 167, 168 4,181.273
26-Jun-2020 169, 170, 171, 172, 173, 174 4,192.104
27-Jun-2020 174 4,192.104
28-Jun-2020 175, 176, 177, 178, 179, 180, 181 4,206.644
29-Jun-2020 182, 183, 184, 185, 186, 187, 188 4,219.206
30-Jun-2020 189, 190, 191, 192, 193, 194, 195 4,235.365
01-Jul-2020 196, 197, 198, 199, 200, 201, 202, 203, 204, 205 4,251.621
02-Jul-2020 206, 207, 208, 209, 210, 211 4,260.681
03-Jul-2020 211 4,260.681
04-Jul-2020 211 4,260.708
05-Jul-2020 212, 213, 214, 215, 216 4,270.724
06-Jul-2020 217, 218, 219, 220, 221, 222 4,282.321
07-Jul-2020 223, 224, 225, 226, 227, 228, 229, 230, 231, 232 4,298.779
08-Jul-2020 233, 234, 235, 236, 237, 238, 239 4,313.022
09-Jul-2020 240, 241, 242, 243, 244, 245, 246, 247 4,327.422
10-Jul-2020 248, 249, 250 4,331.130
11-Jul-2020 250 4,331.130
12-Jul-2020 250 4,331.130
13-Jul-2020 250 4,331.130
14-Jul-2020 250 4,331.130
15-Jul-2020 250 4,331.130
16-Jul-2020 250 4,331.130
17-Jul-2020 250 4,331.130
18-Jul-2020 250 4,331.130
19-Jul-2020 251, 252, 253, 254 4,339.320
20-Jul-2020 255, 256, 257, 258, 258, 260, 261 4,350.850
21-Jul-2020 262, 263, 264 4,356.451
22-Jul-2020 265 4,358.060
23-Jul-2020 266 4,361.690
24-Jul-2020 267, 268, 269 4,367.090
25-Jul-2020 269 4,367.090
26-Jul-2020 270, 271, 272 4,372.035
27-Jul-2020 273, 274, 275, 276 4,379.018
28-Jul-2020 277, 278, 279, 280 4,385.637
29-Jul-2020 281, 282, 283, 284 4,392.441
30-Jul-2020 285 4,394.121
31-Jul-2020 285 4,394.121
01-Aug-2020 285 4,394.121
02-Aug-2020 285 4,394.121
03-Aug-2020 285 4,394.358
04-Aug-2020 285 4,394.358
05-Aug-2020 285 4,394.358
06-Aug-2020 285 4,394.358
07-Aug-2020 285 4,394.358
08-Aug-2020 285 4,394.358
09-Aug-2020 285 4,394.465
10-Aug-2020 285 4,394.465
11-Aug-2020 285 4,394.466
12-Aug-2020 285 4,394.466
13-Aug-2020 285 4,394.466
14-Aug-2020 285 4,394.467
15-Aug-2020 285 4,394.467
16-Aug-2020 285 4,394.467
17-Aug-2020 285 4,394.467
18-Aug-2020 285 4,394.476
19-Aug-2020 285 4,394.476
20-Aug-2020 285 4,394.477
21-Aug-2020 285 4,394.477
22-Aug-2020 285 4,394.477
23-Aug-2020 286, 287, 288 4,400.710
24-Aug-2020 289, 290, 291, 292 4,406.826
25-Aug-2020 293, 294 4,410.336
26-Aug-2020 295, 296, 297, 298, 299, 300 4,421.162
27-Aug-2020 301, 302, 303, 304, 305 4,430.162
28-Aug-2020 306, 307, 308, 309, 310 4,438.659
29-Aug-2020 310 4,438.659
30-Aug-2020 311, 312, 313 4,444.659
31-Aug-2020 314, 315, 316, 317, 318 4,453.811
01-Sep-2020 319, 320, 321, 322 4,460.821
02-Sep-2020 322 4,460.908
03-Sep-2020 323, 324, 325, 326, 327, 328, 329 4,473.994
04-Sep-2020 330, 331, 332, 333, 334, 335, 336, 337 4,489.194
05-Sep-2020 337 4,489.194
06-Sep-2020 338, 339, 340, 341, 342, 343, 344 4,500.761
07-Sep-2020 345, 346, 347, 348, 349, 350, 351, 352 4,514.928
08-Sep-2020 353, 354, 355, 356 4,522.351
09-Sep-2020 357, 358, 359, 360, 361, 362, 363, 364 4,536.737
10-Sep-2020 365, 366, 367, 368, 369, 370, 371 4,550.442
11-Sep-2020 372, 373, 374, 375, 376, 377, 378 4,563.559
12-Sep-2020 378 4,563.559
13-Sep-2020 379 4,563.676
14-Sep-2020 379 4,563.682
15-Sep-2020 380, 381 4,568.899
16-Sep-2020 382, 383, 384, 385, 386, 387, 388, 389 4,581.634
17-Sep-2020 390, 391, 392, 393, 394, 395 4,592.691
18-Sep-2020 396, 397, 398, 399, 400, 401, 402, 403 4,607.239
19-Sep-2020 403 4,607.239
20-Sep-2020 404, 405, 406, 407, 408, 409, 410, 411 4,621.571
21-Sep-2020 412, 413, 414, 415, 416, 417, 418, 419 4,636.586
22-Sep-2020 420, 421, 422, 423, 424, 425, 426 4,648.637
23-Sep-2020 427, 428, 429, 430, 431, 432, 433, 434, 435, 436, 437, 438, 439 4,671.786
24-Sep-2020 440 4,673.659
25-Sep-2020 440 4,673.659
26-Sep-2020 440 4,673.659
27-Sep-2020 441, 442, 443, 444, 445, 446, 447 4,686.306
28-Sep-2020 448, 449, 450, 451, 452, 453 4,697.174
29-Sep-2020 454, 455, 456, 457, 458, 459, 460, 461, 462, 463, 464, 465 4,718.699
30-Sep-2020 466, 467, 468, 469, 470, 471, 472, 473, 474 4,735.766
01-Oct-2020 475, 476 4,739.969
02-Oct-2020 476 4,739.969
03-Oct-2020 476 4,739.969
04-Oct-2020 477 4,740.356
05-Oct-2020 478 4,742.174
06-Oct-2020 479, 480, 481, 482 4,752.112
07-Oct-2020 1, 2, 3, 4,5, 6, 7, 8
08-Oct-2020 9, 10, 11, 12, 13, 14, 15
09-Oct-2020 16, 17, 18, 19, 20, 21, 22, 23
10-Oct-2020 24, 25, 26, 27, 28, 29, 30, 31, 32
11-Oct-2020 33, 34, 35, 36, 37, 38, 39, 40, 41
12-Oct-2020 42, 43, 44, 45, 46, 47, 48, 49, 50
13-Oct-2020 50
14-Oct-2020 50
15-Oct-2020 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61
16-Oct-2020 62, 63, 64, 65
17-Oct-2020 62, 63, 64, 65
18-Oct-2020 62, 63, 64, 65
19-Oct-2020 65
20-Oct-2020 65
21-Oct-2020 65
22-Oct-2020 65
23-Oct-2020 65
24-Oct-2020 65
25-Oct-2020 65
26-Oct-2020 1 EXT, 2 EXT 4,871.360
27-Oct-2020 3 EXT, 4 EXT, 5 EXT, 6 EXT 4,878.560
28-Oct-2020 7 EXT 4,880.360
29-Oct-2020 483 4,882.160
30-Oct-2020 483 4,882.160
31-Oct-2020 483 4,882.160
01-Nov-2020 483 4,882.160
02-Nov-2020 484, 485 4,883.500
03-Nov-2020 486 4,885.070
04-Nov-2020 487 4,886.979
05-Nov-2020 488, 489, 490, 491 4,894.922
06-Nov-2020 491 4,894.922
07-Nov-2020 492, 493, 494, 495 4,902.122
08-Nov-2020 496, 497, 498, 499, 500 4,910.504
09-Nov-2020 500 4,911.149
10-Nov-2020 501, 502 4,913.989
11-Nov-2020 503, 504, 505, 506, 507, 508, 509 4,925.369
12-Nov-2020 510, 511, 512, 513, 514, 515, 516 4,939.229
13-Nov-2020 517, 518, 519, 520, 521, 522 4,950.029
14-Nov-2020 522 4,950.029
15-Nov-2020 523, 524, 525, 526 4,958.546
16-Nov-2020 527, 528, 529, 530, 531, 532, 533, 534, 535, 536 4,975.309
17-Nov-2020 537, 538, 539, 540, 541, 542, 543 4,988.004
18-Nov-2020 543 4,988.004
19-Nov-2020 543 4,988.004
20-Nov-2020 543 4,988.004
21-Nov-2020 544, 545, 546, 547, 548, 549, 550 5,000.604
22-Nov-2020 551, 552, 553, 554, 555, 556, 557 5,014.438
23-Nov-2020 558, 559, 560, 561, 562, 563, 564, 565, 566, 567, 568, 569 5,036.176
24-Nov-2020 570, 571, 572, 573, 574, 575, 576, 577, 578 5,052.786
25-Nov-2020 579,580, 581, 582, 583, 584, 585, 586, 587 5,067.813
26-Nov-2020 588,589, 590, 591 5,074.397
27-Nov-2020 591 5,074.397
28-Nov-2020 592, 593, 594, 595, 596, 597, 598 5,086.997
29-Nov-2020 599, 600, 601, 602, 603, 604, 605, 606, 607, 608 5,105.042
30-Nov-2020 609, 610, 611, 612, 613, 614 5,115.852
01-Dec-2020 615, 616, 617 5,118.310
02-Dec-2020 617, 618, 618, 620, 621, 622, 623 5,133.670
03-Dec-2020 624, 625, 626, 627 5,139.270
04-Dec-2020 627 5,139.270
05-Dec-2020 628, 629, 630, 631, 632, 633 5,150.070
06-Dec-2020 634, 635, 636, 637, 638 5,160.920
07-Dec-2020 639 5,160.920
08-Dec-2020 640, 641, 642, 643, 644, 645, 646 5,173.555
09-Dec-2020 647, 648, 649, 650, 651, 652 5,184.337
10-Dec-2020 652 5,184.337
11-Dec-2020 652 5,184.337
12-Dec-2020 652 5,184.337
13-Dec-2020 652 5,184.337
14-Dec-2020 653 5,186.119
15-Dec-2020 654, 655, 656, 657, 658 5,195.301
16-Dec-2020 659, 660, 661, 662, 663 5,204.191
17-Dec-2020 664,665, 666 5,209.570
18-Dec-2020 666 5,209.570
19-Dec-2020 666 5,209.570
20-Dec-2020 667, 668, 669, 670, 671, 672, 673, 674, 675, 676, 677; 678 5,231.240
21-Dec-2020 679, 680, 681, 682, 683, 684 5,242.061
22-Dec-2020 685, 686, 687, 688, 689, 690, 691, 692, 693 5,258.289
23-Dec-2020 694, 695, 696, 697, 698, 699, 700, 701 5,272.730
24-Dec-2020 702, 703, 704, 705, 706, 707, 708, 709, 710, 711 5,290.764
25-Dec-2020 711 5,290.764
26-Dec-2020 712, 713, 714, 715, 716 5,299.764
27-Dec-2020 717, 718, 719, 720, 721 5,308.800
28-Dec-2020 722, 723, 724, 725, 726, 727, 728, 729, 730 5,326.800
29-Dec-2020 731, 732, 733, 734, 735, 736, 737 5,337.634
30-Dec-2020 738, 739, 740 5,344.800
31-Dec-2020 741, 742, 743, 744, 745, 746, 747, 748 5,357.480
01-Jan-2021 748 5,357.480
02-Jan-2021 749, 750, 751 5,362.880
03-Jan-2021 752, 753, 754 5,368.313
04-Jan-2021 755, 756, 757, 758 5,375.521
05-Jan-2021 758 5,375.521
06-Jan-2021 759, 760, 761, 762 5,382.737
07-Jan-2021 763, 764, 765, 766, 767, 768, 769 5,395.355
08-Jan-2021 769 5,395.355
09-Jan-2021 770, 771, 772, 773, 774, 775, 776 5,407.955
10-Jan-2021 777, 778, 779, 780, 781, 782, 783, 784 5,422.419
11-Jan-2021 785 5,424.208
12-Jan-2021 786, 787, 788, 789, 790, 791, 792, 793, 794, 795, 796 5,444.070
13-Jan-2021 797, 798, 799, 800, 801, 802, 803, 804, 805,806, 807 5,463.899
14-Jan-2021 808, 809, 810, 811, 812 5,473.324
15-Jan-2021 812 5,473.324
16-Jan-2021 813, 814, 815, 816, 817, 818, 819 5,485.001
17-Jan-2021 820, 821, 822, 823, 824, 825, 826, 827, 828 5,501.800
18-Jan-2021 829, 830, 831, 832, 833, 834, 835, 836, 837, 838 5,519.715
19-Jan-2021 839, 840, 841, 842 5,526.916
20-Jan-2021 843, 844, 845, 846, 847, 848 5,537.879
21-Jan-2021 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13
22-Jan-2021 13
23-Jan-2021 13
24-Jan-2021 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26
25-Jan-2021 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41
26-Jan-2021 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54
27-Jan-2021 55, 56, 57, 58, 59, 60, 61, 62, 63, 64
28-Jan-2021 65, 66, 67, 68, 69, 70, 71, 72, 73, 74
29-Jan-2021 74
30-Jan-2021 74
31-Jan-2021 74
01-Feb-2021 74
02-Feb-2021 74
03-Feb-2021 74
04-Feb-2021 74
05-Feb-2021 74
06-Feb-2021 74
07-Feb-2021 74
08-Feb-2021 74
09-Feb-2021 74
10-Feb-2021 74 5,678.470 3
11-Feb-2021 1 EXT, 2 EXT, 3 EXT, 4 EXT 5,679.006 3
12-Feb-2021 1 EXT, 2 EXT, 3 EXT, 4 EXT 5,679.006 3
13-Feb-2021 5 EXT, 6 EXT, 7 EXT, 8 EXT 5,686.206 3
14-Feb-2021 849, 850, 851 5,691.606 3
15-Feb-2021 851 5,691.612 3
16-Feb-2021 852 5,693.776 3
17-Feb-2021 853 5,695.928 3
18-Feb-2021 854, 855, 856, 857, 858, 859 5,706.414 3
19-Feb-2021 860, 861, 862, 863, 864 5,715.924 3
20-Feb-2021 864 5,715.924 3
21-Feb-2021 864 5,715.924 3
22-Feb-2021 865, 866, 867, 868, 869, 870, 871, 872 5,731.280 3
23-Feb-2021 873, 874, 875, 876, 877, 878, 879 5,741.970 3
24-Feb-2021 879 5,742.556 3
25-Feb-2021 879 5,742.556 3
26-Feb-2021 880, 881, 882, 883 5,749.616 3
27-Feb-2021 884, 885, 886 5,754.587 3
28-Feb-2021 886 5,754.587 3
01-Mar-2021 887 5,756.519 3
02-Mar-2021 888, 889, 890, 891 5,763.743 3

03-Mar-2021 891 5,763.743 3

04-Mar-2021 891 5,763.743 3

05-Mar-2021 891 5,763.743 3

06-Mar-2021 891 5,763.743 3

07-Mar-2021 891 5,763.743 3

08-Mar-2021 891 5,763.743 3

09-Mar-2021 891 5,763.743 3

10-Mar-2021 891 5,763.743 3

11-Mar-2021 892, 893, 894 5,769.546 3

12-Mar-2021 895, 896, 897, 898, 899, 900, 901, 902, 903 5,785.746 3
13-Mar-2021 904, 905, 906, 907, 908, 909, 910, 911, 912 5,801.946 3
14-Mar-2021 913, 914, 915, 916, 917, 918, 919, 920, 921, 922 5,819.560 3

15-Mar-2021 923, 924, 925, 926, 927, 928, 929, 930, 931, 932, 933 5,836.108 3

16-Mar-2021 934, 935, 936, 937, 938, 939, 940, 941, 942, 943 5,851.580 3

17-Mar-2021 944, 945, 946, 947, 948, 949, 950, 951, 952 5,863.030 3
18-Mar-2021 953, 954, 955, 956, 957 5,870.116 3

19-Mar-2021 958, 959, 960, 961, 962, 963, 964, 965 5,880.912 3

20-Mar-2021 965, 966 5,882.435 3

21-Mar-2021 966 5,882.435 3


22-Mar-2021 966 5,882.435 3
23-Mar-2021 966 5,882.511 3

24-Mar-2021 967, 968, 969, 970, 971, 972 5,891.451 3

25-Mar-2021 973, 974, 975, 976, 977, 978, 979, 980, 981, 982 5,904.760 3

26-Mar-2021 983, 984, 985, 986, 987, 988, 989, 990 5,915.960 3

27-Mar-2021 991, 992, 993, 994, 995, 996, 997, 998 5,927.160 3

28-Mar-2021 999, 1000, 1001, 1002, 1003, 1003, 1005, 1006 5,938.870 3

29-Mar-2021 1007, 1008, 1009, 1010, 1011, 1012, 1013 5,948.646 3

30-Mar-2021 1014, 1015, 1016, 1017, 1018, 1019, 1020, 1021 5,959.697 3

31-Mar-2021 1022, 1023, 1024, 1025, 1026, 1027, 1028, 1029, 1030, 1031 5,973.720 3

01-Apr-2021 1032, 1033, 1034, 1035, 1036, 1037, 1038, 1039, 1040, 1041, 1042, 1043 5,990.550 3

02-Apr-2021 1043 5,990.550 3

03-Apr-2021 1044, 1045, 1046, 1047, 1048, 1049, 1050 6,000.350 3

04-Apr-2021 1051, 1052, 1053, 1054, 1055, 1056, 1057 6,010.270 3

05-Apr-2021 1057 6,010.510 3


06-Apr-2021 1058, 1059, 1060, 1061, 1062, 1063, 1064, 1065, 1066 6,024.250 3

07-Apr-2021 1067, 1068, 1069, 1070, 1071, 1072, 1073 6,033.912 3

08-Apr-2021 1074, 1075, 1076, 1077 6,042.410 3

09-Apr-2021 1078, 1079, 1080, 1081, 1082, 1083, 1084, 1085, 1086, 1087, 1088, 1089 6,059.210 3

10-Apr-2021 1090, 1091, 1092, 1093, 1094, 1095, 1096, 1097, 1098, 1099, 1100, 1101 6,076.010 3

11-Apr-2021 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112 6,087.315 3

12-Apr-2021 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121, 1122 6,102.482 3

13-Apr-2021 1123, 1124, 1125, 1126, 1127, 1128, 1129, 1130, 1131, 1132 6,116.579 3

14-Apr-2021 1133, 1134, 1135, 1136, 1137, 1138, 1139, 1140, 1141, 11042, 1043, 1144 6,132.055 3

15-Apr-2021 1145, 1146, 1147, 1148, 1149 6,141.567 3

16-Apr-2021 1150, 1151, 1152, 1153, 1154, 1155, 1156 6,153.167 3


17-Apr-2021 1157, 1158, 1159, 1160, 1161, 1162, 1163 6,165.767 3
18-Apr-2021 1164, 1165, 1166, 1167, 1168, 1169, 1170 6,179.432 3
19-Apr-2021 1171, 1172, 1173, 1174, 1175, 1176, 1177, 1178, 1179, 1180 6,197.280 3
20-Apr-2021 1181, 1182, 1183, 1184, 1185, 1186, 1187, 1188 6,211.840 3
21-Apr-2021 1189, 1190, 1191, 1192, 1193, 1194, 1195, 1196, 1197 6,226.270 3
22-Apr-2021 1197 6,226.270 3
23-Apr-2021 1198, 1199, 1200, 1201, 1202, 1203, 1204, 1205 6,240.670 3

24-Apr-2021 1205 6,240.670 3

25-Apr-2021 1205 6,240.670 3

26-Apr-2021 1205 6,240.670 3

27-Apr-2021 1205 6,240.670 3

28-Apr-2021 1205 6,240.670 3

29-Apr-2021 1206, 1207 6,244.410 3

30-Apr-2021 1208, 1209 6,248.010 3

01-May-2021 1209 6,248.010 3

02-May-2021 1210, 1211, 1212, 1213, 1214 6,258.748 3

03-May-2021 1215, 1216, 1217, 1218, 1219, 1220, 1221 6,269.553 3

04-May-2021 1221 6,269.553 3

05-May-2021 1222 6,271.330 3

06-May-2021 1222 6,271.330 3

07-May-2021 1223, 1224, 1225 6,276.730 3

08-May-2021 1226, 1227, 1228, 1229, 1230, 1231, 1232, 1233, 1234 6,292.930 3

09-May-2021 1235, 1236, 1237, 1238, 1239, 1240, 1241, 1242, 1243 6,309.188 3
10-May-2021 1244, 1245,1246, 1247, 1248, 1249, 1250 6,323.584 3
11-May-2021 1251, 1252, 1253, 1254, 1255, 1256, 1257 6,336.216 3

12-May-2021 1258, 1259, 1260, 1261, 1262, 1263, 1264 6,347.029 3

13-May-2021 1265, 1266, 1267, 1268, 1269, 1270 6,359.657 3


14-May-2021 1270 6,359.657 3
15-May-2021 1270 6,359.657 3

16-May-2021 1271, 1272, 1273, 1274, 1275, 1276, 1277, 1278, 1279, 1280, 1281 6,377.610 3

17-May-2021 1282, 1283, 1284, 1285, 1286, 1287, 1288, 1289, 1290, 1291, 1292 6,397.420 3

18-May-2021 1293, 1294, 1295, 1296, 1297, 1298, 1299, 1300 6,411.820 3

19-May-2021 1301, 1302, 1303, 1304, 1305, 1306, 1307, 1308, 1309, 1310, 1311 6,431.640 3

20-May-2021 1312, 1313, 1314, 1315, 1316, 1317, 1318, 1319, 1320, 1321 6,449.670 3

21-May-2021 1322, 1323, 1324, 1325, 1326, 1327, 1328, 1329, 1330, 1331 6,467.670 3

22-May-2021 1332, 1333, 1334, 1335, 1336, 1337, 1338, 1339 6,483.593 3

23-May-2021 1339 6,483.593 3

24-May-2021 1340, 1341, 1342, 1343, 1344, 1345, 1346, 1347, 1348 6,498.786 3

25-May-2021 1349, 1350, 1351, 1352, 1353, 1354, 1355 6,512.770 3

26-May-2021 1356, 1357, 1358 6,516.360 3

27-May-2021 1359, 1360, 1361, 1362, 1363, 1364, 1365, 1366, 1367, 1368 6,534.250 3

28-May-2021 1369, 1370, 1371, 1372, 1373, 1374, 1375 6,546.850 3

29-May-2021 1376, 1377, 1378, 1379, 1380, 1381, 1382 6,559.450 3

30-May-2021 1383, 1384, 1385, 1386, 1387, 1388, 1389 6,572.346 3

31-May-2021 1390, 1391 6,575.730 3

01-Jun-2021 1392, 1393, 1394, 1395, 1396, 1397, 1398 6,588.394 3

02-Jun-2021 1399, 1400, 1401, 1402, 1403, 1404, 1405, 1406 6,602.740 3

03-Jun-2021 1407, 1408, 1409, 1410, 1411, 1412, 1413, 1414, 1415, 1416, 1417, 1418 6,624.918 3

04-Jun-2021 1419, 1420, 1421, 1422, 1423, 1424, 1425, 1426, 1427, 1428, 1429, 1430 6,637.730 3

05-Jun-2021 1431, 1432, 1433, 1434, 1435, 1436 6,648.530 3


06-Jun-2021 T1 3
07-Jun-2021 T2, T3, T4, T5, T6, T7, T8, T9, T10, T11, T12, T13, T14, T15, T16, T17 3
08-Jun-2021 T18, T19, T20, T21, T22, T23, T24 3
09-Jun-2021 T25, T26, T27, T28, T29, T30, T31, T32, T33, T34, T35, T37, T37, T38 3

10-Jun-2021 T39, T40, T41, T42, T43, T44, T45, T46, T47, T48 3
11-Jun-2021 T49, T50 T51 3
12-Jun-2021 T51 3
13-Jun-2021 T51 3
14-Jun-2021 T51 3
15-Jun-2021 T51 3
16-Jun-2021 T51 3
17-Jun-2021 T51 3
18-Jun-2021 T51 3
19-Jun-2021 T51 3
20-Jun-2021 T51 3
21-Jun-2021 T51 3
22-Jun-2021 T51 3
23-Jun-2021 T51 6,776.960 3
24-Jun-2021 1 EXT, 2 EXT 3
25-Jun-2021 2 EXT 3
26-Jun-2021 2 EXT 3
27-Jun-2021 2 EXT 3
28-Jun-2021 2 EXT 3
29-Jun-2021 3 EXT 3
30-Jun-2021 3 EXT 6,776.490 3
01-Jul-2021 3
4 EXT, 5 EXT, 6 EXT 6,782.263

02-Jul-2021 3
7 EXT, 8 EXT (1,40 m), 1437 6,785.985

03-Jul-2021 3
1438, 1439, 1440, 1441, 1442, 1443 6,796.785

04-Jul-2021 3
1444, 1445, 1446, 1447, 1448, 1449 6,807.585

05-Jul-2021 3
1450, 1451, 1452, 1453, 1454, 1455, 1456, 1457, 1458, 1459 6,825.625

06-Jul-2021 3
1460, 1461, 1462, 1463, 1464, 1465, 1466, 1467, 1468 6,841.857

07-Jul-2021 3
1469, 1470, 1471, 1472, 1473, 1474, 1475, 1476, 1477, 1478, 1479, 1480, 1481,1482 6,865.272

08-Jul-2021 3
1483, 1484, 1485, 1486, 1487, 1488, 1489, 1490, 1491, 1492 6,883.631

09-Jul-2021 3
1493, 1494, 1495, 1496, 1497, 1498, 1499, 1500, 1501, 1502 6,901.631

10-Jul-2021 3
1503, 1504, 1505, 1506, 1507, 1508, 1508, 1510, 1511, 1512 6,921.208

11-Jul-2021 3
1512 6,921.208

12-Jul-2021 3
1513, 1514, 1515 6,927.710

13-Jul-2021 3
1516 6,928.724

14-Jul-2021 3
1516 6,928.724

15-Jul-2021 3
1516 6,928.724

16-Jul-2021
1517, 1518, 1519 6,934.124 2

17-Jul-2021
1520, 1521, 1522 6,939.524 2

18-Jul-2021
1523, 1524, 1525, 1526 6,946.330 2

19-Jul-2021
1526 6,946.424 2

20-Jul-2021
1526 6,946.453 0

21-Jul-2021 1526 6,946.453 0


22-Jul-2021 1526 6,946.453 0
23-Jul-2021 1526 6,946.453 0
24-Jul-2021 1526 6,946.453 1
25-Jul-2021 1526 6,946.534 1
26-Jul-2021 1526 6,946.739 0
27-Jul-2021 1526 6,946.739 1
28-Jul-2021 1526 6,946.960 1
29-Jul-2021 1526 6,946.960 1
30-Jul-2021 1526 6,946.960 1
31-Jul-2021 1526 6,946.960 1
01-Aug-2021 1526 6,946.960 1
02-Aug-2021 1526 6,947.177 1
03-Aug-2021 1526 6,947.177 1
04-Aug-2021
1526 6,947.177 1

05-Aug-2021 1527, 1528, 1529, 1530, 1531, 1232, 1533, 1534 6,960.670 3
06-Aug-2021 1534 6,960.670 3
07-Aug-2021 1535, 1536, 1537, 1538, 1540, 1541, 1542, 1543, 6,976.900 3
08-Aug-2021 1544, 1545, 1546, 1547, 1548, 1549, 1550, 1551, 1552 6,994.996 3
09-Aug-2021 1553, 1554, 1555, 1556, 1557, 1558, 1559, 1560, 1561 7,009.440 3
10-Aug-2021 1561 7,009.440 3
11-Aug-2021 1561 7,009.440 3
12-Aug-2021 1562, 1563 7,014.643 3
13-Aug-2021 1563 7,014.643 3
14-Aug-2021 1564, 1565, 1566, 1567, 1568, 1569, 1570, 1571 7,030.643 3
15-Aug-2021 1572, 1573, 1574, 1575, 1576, 1577, 1578 7,041.616 3
16-Aug-2021
1579, 1580, 1581, 1582, 1583, 1584 7,050.860 3

17-Aug-2021 1584 7,050.860 3

18-Aug-2021 1584 7,050.860 3

19-Aug-2021 1584 7,050.860 3


20-Aug-2021 1584 7,050.860 3
21-Aug-2021 1585, 1586, 1587, 1588, 1589, 1590, 1591, 1592 7,065.360 3
22-Aug-2021 1593, 1594, 1595, 1596, 1597, 1598 7,076.160 3
23-Aug-2021 1598 7,076.160 3
24-Aug-2021 1598 7,076.160 3
25-Aug-2021 1598 7,076.160 3
26-Aug-2021 1599, 1600, 1601, 1602, 1603, 1604, 1605, 1606, 1607, 1608 7,094.157 3
27-Aug-2021 1608 7,094.157 3
28-Aug-2021 1609, 1610, 1611, 1612, 1613 7,103.157 3
29-Aug-2021 1614, 1615, 1616, 1617, 1618, 1619, 1620, 1621 7,117.345 3
30-Aug-2021 1622, 1623, 1624, 1625, 1626 7,126.643 3
31-Aug-2021 1627, 1628, 1629, 1630, 1631 7,135.494 3

01-Sep-2021 1632, 1633 7,139.010 3

02-Sep-2021 1634, 1635, 1636, 1638 7,150.010 3

03-Sep-2021 1639, 1640, 1641 7,155.410 3

04-Sep-2021 1642, 1643, 1644 7,160.910 3

05-Sep-2021 1645, 1646, 1647 7,164.287 3

06-Sep-2021 1648, 1649, 1650 7,170.750 3

07-Sep-2021 1651, 1652, 1653, 1654 7,177.048 3

08-Sep-2021 1655, 1656, 1657, 1658, 1659, 1660 7,187.860 3

09-Sep-2021 1661 7,189.690 3

10-Sep-2021 1661 7,189.704 3

11-Sep-2021 1661 7,189.704 3


12-Sep-2021 1661 7,189.704 3
13-Sep-2021 1661 7,189.704 3

14-Sep-2021 1661 7,189.704 3

15-Sep-2021 1661 7,189.704 3

16-Sep-2021 1661 7,189.704 3

17-Sep-2021 1661 7,189.704 3

18-Sep-2021 1662 7,191.424 3

19-Sep-2021 1663, 1664, 1665, 1666, 1667 7,200.297 3


20-Sep-2021 1668, 1669, 1670, 1671, 1672, 1673 7,211.140 3
21-Sep-2021 1674, 1675, 1676, 1677, 1678, 1679, 1680 7,223.720 3
22-Sep-2021 1681, 1682, 1683, 1684, 1685, 1686, 1687 7,236.320 3
23-Sep-2021 1688, 1689, 1690, 1691, 1692 7,245.450 3
24-Sep-2021 1692 7,245.450 0
25-Sep-2021 1693, 1694, 1695, 1696, 1697, 1698, 1699, 1700, 1701 7,261.690 3
26-Sep-2021 1702, 1703, 1704, 1705, 1706, 1707 7,272.420 3
27-Sep-2021 1708, 1709, 1710, 1711, 1712, 1713, 1714, 1715, 1716 7,288.790 3
28-Sep-2021 1717, 1718, 1719, 1720, 1721, 1722, 1723, 1724, 1725 7,304.990 3
29-Sep-2021 1726, 1727, 1728, 1729, 1730, 1731, 1732, 1733 7,319.420 3
30-Sep-2021
1734, 1735, 1736, 1737, 1738, 1739 7,332.050 3

01-Oct-2021 1739 7,332.050 0


02-Oct-2021 1740, 1741 , 1742, 1743, 1744, 1745, 1746, 1747 7,346.450 3
03-Oct-2021 1748, 1749, 1750, 1751, 1752, 1753, 1754, 1755 7,359.000 3
04-Oct-2021

1756, 1757, 1758, 1759 7,366.300 3


05-Oct-2021 1760, 1761 7,370.000 3
06-Oct-2021
1762 7,371.722 3

07-Oct-2021 1762 7,371.722 3


08-Oct-2021 1762 7,371.722 3
09-Oct-2021 1762 7,371.722 3
10-Oct-2021 1762 7,371.722 3
11-Oct-2021 1762 7,371.722 3
12-Oct-2021 1762 7,371.722 3
13-Oct-2021 1762 7,371.722 3
14-Oct-2021
1762 7,371.722 3

15-Oct-2021 T1, T2, T3, T4, T5


16-Oct-2021 T6, T7, T8, T9, T10
17-Oct-2021 T11, T12, T13, T14, T15
18-Oct-2021 T16, T17, T18, T19, T20, T21
19-Oct-2021 T22, T23, T24, T25, T26, T27, T28, T29, T30, T31, T32, T33, T34, T35, T36, T37, T38, T39,
T44, T41, T42, T43, T44, T45, T46, T47, T48, T49, T50, T51, T52, T53, T54, T55
20-Oct-2021 T56, T57, T58, T59, T60, T61, T62, T63
21-Oct-2021 T63
22-Oct-2021 T64
23-Oct-2021 T65
24-Oct-2021 T66
25-Oct-2021 T66
26-Oct-2021 T66
27-Oct-2021 T66
28-Oct-2021 T66
29-Oct-2021 T66
30-Oct-2021 T66
31-Oct-2021 T66 7,371.722
01-Nov-2021 1 EXT, 2 EXT
02-Nov-2021 3 EXT 7,495.700

03-Nov-2021 3 EXT 7,496.516 3

04-Nov-2021 3
4 EXT, 5 EXT 7,497.534

05-Nov-2021 3
EXT 6 (1,40 m) 7,501.320
06-Nov-2021 EXT 6 (1,40 m) 7,501.320 3
07-Nov-2021 EXT 6 (1,40 m) 7,501.320 3
08-Nov-2021 EXT 7 (1,40 m) , EXT 8 (1,4 m), 1764 (1,8 m) 7,503.145 3
09-Nov-2021 1765, 1766, 1767, 1768 7,512.138 3
10-Nov-2021 1769 7,515.730 3

11-Nov-2021 1769 7,515.730 3

12-Nov-2021 1770, 1771, 1772, 1773, 1774 7,522.929 3

13-Nov-2021 1774 7,522.929 3

14-Nov-2021 1774 7,522.929 3

15-Nov-2021 1774 7,522.929 3

16-Nov-2021 1775 7,524.730 3

17-Nov-2021 1775 7,524.730 3

18-Nov-2021 1775 7,524.730 3

19-Nov-2021 1775 7,524.730 3

20-Nov-2021 3
1776, 1777 7,528.330
21-Nov-2021 3
1778, 1779, 1780, 1781 7,535.553

22-Nov-2021
1782, 1783, 1784, 1785, 1786, 1787, 1788, 1789 7,549.970 3

23-Nov-2021 1790, 1791, 1792, 1793, 1794, 1795, 1796, 1797, 1798 7,566.159 3
24-Nov-2021 1799 7,569.217 3

25-Nov-2021 1800, 1801, 1802, 1803, 1804, 1805 7,580.461 3


26-Nov-2021 1805 7,580.461 3

27-Nov-2021 1806, 1807, 1808, 1809, 1810, 1811. 1812, 1813 7,593.468 3

28-Nov-2021 1814, 1815, 1816, 1817, 1818 7,600.393 3

29-Nov-2021 1818 7,600.393 3

30-Nov-2021 1818 7,600.393 3

01-Dec-2021 1819, 1820, 1821, 1822 7,609.630 3

02-Dec-2021 1822 7,609.630 3

03-Dec-2021 1823, 1824 7,613.681 1

04-Dec-2021 1824 7,613.681 1

05-Dec-2021 1824 7,613.681 1


06-Dec-2021 1825, 1826, 1827, 1828, 1829 7,622.816 3

07-Dec-2021 1830, 1831, 1832, 1833, 1834 7,630.941 3

08-Dec-2021 1835, 1836, 1837, 1838, 1839, 1840, 1841, 1842, 1843 7,647.247 3

09-Dec-2021 1844, 1845, 1846, 1847, 1848 7,657.908 3

10-Dec-2021 1848 7,657.908 3

11-Dec-2021 1849 7,657.975 3

12-Dec-2021 1849 7,657.975 3

13-Dec-2021 1849 7,657.975 3

14-Dec-2021 1849 7,657.975 1

15-Dec-2021 1849 7,657.975 1

16-Dec-2021 1849 7,657.975 1

17-Dec-2021 1849 1

7,657.990
18-Dec-2021 1849 1

7,657.990
19-Dec-2021 1849 3

7,657.990

20-Dec-2021 1850 7,659.883 3

21-Dec-2021 1851,1852,1853,1854 7,667.089 3

22-Dec-2021 1854 7,667.089 3

23-Dec-2021 1855,1856,1857 7,672.472 3

24-Dec-2021 1857 7,672.536 3


25-Dec-2021 1857 7,672.536 3
26-Dec-2021 1857 7,672.536 3
27-Dec-2021 1857 7,672.536 3

28-Dec-2021 3
1858,1859,1860,1861,1862,1863,1864,1865 7,686.900

29-Dec-2021 1866,1867,1868,1869,1870,1871,1872,1873,1874,1875,1876 7,706.964 3


30-Dec-2021 3
1877,1879,1880,1881,1882,1883,1884,1885 7,722.930

31-Dec-2021 1886,1887,1888 7,728.331 3

01-Jan-2022 1888 7,728.331 0


02-Jan-2022 1888 7,728.331 3

03-Jan-2022 1889,1890,1891,1992,1893,1894,1895 7,739.129 3

04-Jan-2022 1896, 1897, 1898, 1899, 1900, 1901 7,752.497 3

05-Jan-2022 1902, 1903, 1904, 1905 7,760.722 3

06-Jan-2022 1906, 1907, 1908, 1909, 1910, 1911, 1912, 1913, 1914, 1915 7,778.625 3

07-Jan-2022 1916,1917,1918,1919,1920,1921,1922,1923,1924,1925 7,794.970 3

08-Jan-2022 1925 7,794.970 0


09-Jan-2022 1926,1927,1928,1929,1930,1931,1932,1933,1934,1935 7,812.990 3
10-Jan-2022 1936.1937 7,816.620 3

11-Jan-2022 1938,1939,1940,1941 7,823.840 3

12-Jan-2022 1942, 1943, 1944, 1945, 1946, 1947, 1948, 1949 7,838.790 3

13-Jan-2022 1950, 1951, 1952, 1953 7,845.440 3

14-Jan-2022 1954, 1955, 1956, 1957, 1959, 1959, 1960, 1961, 1962, 1963, 1964, 1965, 1966 7,868.840 3

15-Jan-2022 1966 7,868.840 0


16-Jan-2022 1967, 1968, 1969, 1970, 1971, 1972, 1973 7,881.530 3

17-Jan-2022 3
1973 7,882.198

18-Jan-2022 3
1974, 1975, 1976, 1977, 1978, 1979, 1980, 1981 7,895.812

19-Jan-2022 3
1981 7,895.812

20-Jan-2022 3
1982, 1983, 1984 7,901.298
21-Jan-2022 1984 7,901.298 0

22-Jan-2022
1985, 1986, 1987, 1988, 1989, 1990, 1991 7,913.898 3
23-Jan-2022 1992, 1993, 1994, 1995, 1996, 1997 7,924.754 3

24-Jan-2022 3
1998, 1999, 2000, 2001 7,932.433

25-Jan-2022 2001 7,932.433 1

26-Jan-2022 2001 7,932.433 1

27-Jan-2022 2001 7,932.433 1

28-Jan-2022 2001 7,932.433 1


29-Jan-2022 2001 7,932.433 1

30-Jan-2022 2001 7,932.433 1

31-Jan-2022 2001 7,932.433 1

01-Feb-2022 2001 7,932.433 1

02-Feb-2022 2001 7,932.433 1

03-Feb-2022 2001 7,932.433 1


04-Feb-2022 2002, 2003, 2004 7,937.833 3
05-Feb-2022 2004 7,937.833 0

06-Feb-2022 2005, 2006, 2007, 2008, 2009, 2010 7,949.750 3

07-Feb-2022 2011 7,951.420 3

08-Feb-2022 2012, 2013, 2014 7,956.981 3

09-Feb-2022 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022, 2023, 2024 7,974.167 3

10-Feb-2022 2025, 2026, 2027, 2028, 2029, 2030, 2031 7,987.802 3

11-Feb-2022 3
2032, 2033, 2034, 2035, 2036, 2037, 2038, 2039, 2040 8,004.002
12-Feb-2022 2040 8,004.002 3

13-Feb-2022 2041, 2042, 2043, 2044, 2045, 2046 8,013.022 3

14-Feb-2022 2047, 2048, 2049, 2050, 2051 8,022.030 3

15-Feb-2022 2052, 2053, 2054, 2055, 2056, 2057, 2058, 2059, 2060, 2061, 2062 8,041.880 3

16-Feb-2022 2063, 2064, 2065, 2066, 2067, 2068, 2069, 2070, 2071, 2072, 2073 8,061.740 3
17-Feb-2022 2074, 2075, 2076, 2077, 2078, 2079, 2080, 2081 8,076.140 3

18-Feb-2022 2081 8,076.140 3

19-Feb-2022 2081 8,076.140 3

20-Feb-2022 2082, 2083, 2084, 2085, 2086, 2087, 2088, 2089, 2090, 2091, 2092 8,094.137 3

21-Feb-2022 2093, 2094, 2095, 2096, 2097, 2098, 2099, 2100, 2101, 2102, 2103, 2104, 2105 8,117.585 3

22-Feb-2022 2106, 2107, 2108, 2109, 2110, 2111, 2112, 2113, 2114, 2115 8,133.816 3

23-Feb-2022 2116, 2117, 2118, 2119, 2120 8,144.652 3

24-Feb-2022 2121, 2122, 2123, 2124, 2125, 2126 8,155.793 3

25-Feb-2022 2127, 2128, 2129, 2130, 2131, 2132, 2133, 2134, 2135, 2136, 2137 8,175.593 3

26-Feb-2022 2137 8,175.593 0

27-Feb-2022 2138, 2139, 2140, 2141, 2142, 2143, 2144, 2145, 2146, 2147, 2148 8,196.902 4

28-Feb-2022 2149, 2150, 2151, 2152, 2153, 2154, 2155, 2156, 2157 8,213.113 4

01-Mar-2022 2158, 2159, 2160, 2161, 2162, 2163, 2164, 2165, 2166, 2167 8,232.791 4

02-Mar-2022 2168, 2169, 2170, 2171, 2172, 2173, 2174, 2175, 2176, 2177, 2178 8,250.978 4

03-Mar-2022 2179, 2180, 2181, 2182, 2183, 2184, 2185, 2186, 2187, 2188, 2189 8,270.532 4
04-Mar-2022 2190, 2191, 2192, 2193, 2194 8,279.829 4

05-Mar-2022 2194 8,279.829 4

06-Mar-2022 2194 8,279.829 4

07-Mar-2022 2194 8,279.829 4

08-Mar-2022 2194 8,279.829 4

09-Mar-2022 2194 8,279.829 4

10-Mar-2022 2195, 2196, 2197 8,287.031 4

11-Mar-2022 2198, 2199, 2200, 2201, 2202, 2203 8,297.831 4

12-Mar-2022 2204, 2205, 2206, 2207, 2208, 2209, 2210 8,310.431 4

13-Mar-2022 2211, 2212, 2213, 2214, 2215, 2216, 2217 8,321.266 4

14-Mar-2022 2218, 2219, 2220, 2221, 2222, 2223, 2224, 2225, 2226, 2227 8,336.900 4

15-Mar-2022 2228, 2229, 2230, 2231, 2232, 2233, 2234 8,351.884 4

16-Mar-2022 2235, 2236, 2237, 2238, 2239, 2240, 2241, 2242, 2243 8,369.621 4

17-Mar-2022 2244, 2245, 2246, 2247, 2248, 2249, 2250, 2251, 2252 8,384.342 4

18-Mar-2022 8,384.342
2252 1

19-Mar-2022 8,384.342
2252 1

20-Mar-2022 8,384.342
2252 1
21-Mar-2022 8,384.342
2252 1

22-Mar-2022 2253, 2254, 2255, 2256, 2257, 2258, 2259, 2260, 2262, 2263 8,404.190 4

23-Mar-2022 2264, 2265, 266, 2267, 2268, 2269, 2270 8,419.185 4

24-Mar-2022 2271, 2272, 273, 2273, 2274, 2275, 2276, 2277, 2278, 2279, 2280, 2281 8,436.774 4

25-Mar-2022 4

2282, 2283, 2284, 2285 8,443.974


26-Mar-2022 2285 8,443.974 0
27-Mar-2022

2286, 2287, 2288, 2289, 2290, 2291 8,454.975 4


28-Mar-2022 2292, 2293, 2294, 2295, 2296, 2297, 2298, 2299, 2300 8,471.030 4
29-Mar-2022 2301, 2302, 2303, 2304, 2305 8,481.828 4
30-Mar-2022 2306, 2307, 2308, 2309, 2310, 2311, 2312, 2313, 2314 8,496.426 4

31-Mar-2022 2315, 2316, 2317, 2318, 2319, 2320, 2321, 2322, 2223 8,512.472 4

01-Apr-2022 2224, 2225, 2226, 2227, 2228, 2229, 2230, 2231 8,526.872 4

02-Apr-2022 2332 8,528.631 4

03-Apr-2022 2333, 2334, 2335, 2336 8,535.891 4

04-Apr-2022 2337, 2338 8,539.473 4

05-Apr-2022 2339, 2340, 2341, 2342, 2343 8,548.488 4

06-Apr-2022 2344, 2345, 2346, 2347, 2348, 2349, 2350, 2351 8,560.084 4

07-Apr-2022 2352, 2353, 2354, 2355, 2356, 2357, 2358, 2359, 2360, 2361 8,574.060 4

08-Apr-2022 2362 8,577.176 4

09-Apr-2022 2362 8,577.176 4

10-Apr-2022 2362 8,577.176 4


11-Apr-2022 2362 8,577.176 4

12-Apr-2022 2362 8,577.176 4

13-Apr-2022 2362 8,577.176 4

14-Apr-2022 2362 8,577.288 4

15-Apr-2022 2363, 2364, 2365, 2366, 2367 8,584.288 4


16-Apr-2022 2368, 2369, 2370, 2371, 2372, 2373, 2374, 2375 8,595.488 4

17-Apr-2022 2376, 2377, 2378, 2379, 2380, 2381, 2382, 2383 8,604.880 4

18-Apr-2022 2384, 2385, 2386, 2387, 2388 8,611.990 4


19-Apr-2022 2389, 2390, 2391, 2392, 2393 8,618.923 4

20-Apr-2022 2394, 2395, 2396, 2397, 2398, 2399, 2400, 2401, 2402, 2403, 2404 8,633.031 4

21-Apr-2022 2405, 2406, 2407, 2408 8,641.429 3


22-Apr-2022 2409, 2410, 2411, 2412, 2413, 2414, 2415 8,651.229 3

23-Apr-2022 2416, 2417, 2418, 2419, 2420, 2421, 2422, 2423 8,662.429 3

24-Apr-2022 2424, 2425, 2426, 2427, 2428, 2429, 2430, 2431 8,673.686 3

25-Apr-2022 2432, 2433, 2434, 2435, 2436, 2437, 2438, 2439, 2440 8,686.649 3

26-Apr-2022 2441, 2442, 2443, 2444, 2445, 2446 8,693.270 3


27-Apr-2022 2447, 2448, 2449, 2450, 2451, 2452, 2453, 2454, 2455 8,705.890 3

28-Apr-2022 2456, 2457, 2458, 2459 8,711.579 3

29-Apr-2022 2460, 2461, 2462, 2463, 2464, 2465, 2466, 2467, 2468, 2469 8,725.579 3

30-Apr-2022 2470, 2471, 2472, 2473, 2474, 2475, 2476, 2477, 2478 8,738.779 3

01-May-2022 2479, 2480, 2481, 2482 8,743.770 3

02-May-2022 2482 8,743.770 3


03-May-2022 2482 8,743.770 3
04-May-2022 2482 8,743.770 3
05-May-2022 2483, 2484, 2485 8,748.650 3

06-May-2022 2486, 2487, 2488, 2489, 2490, 2491, 2492 8,758.450 3

07-May-2022 2493, 2494, 2495, 2496, 2497, 2498, 2499, 2500 8,769.080 3

08-May-2022 2500 8,769.080 3


09-May-2022 2501, 2502, 2503, 2504, 2505, 2506, 2507, 2508 8,780.289 3
10-May-2022 2508 8,780.289 3
11-May-2022 3
2509, 2510, 2511, 2512, 2513, 2514, 2515, 2516 8,791.360

12-May-2022 2517, 2518, 2519, 2520, 2521, 2522, 2523, 2524 8,802.937 3

13-May-2022
2525, 2526, 2527, 2528 8,808.537 3

14-May-2022
2529, 2530, 2531, 2532 8,813.737 3

15-May-2022
2533, 2534, 2535, 2536 8,819.404 3
16-May-2022 2537, 2538, 2539, 2540, 2541, 2542, 2543, 2544, 2545 8,833.621 3

17-May-2022 2546, 2547, 2548, 2549, 2550, 2551, 2552, 2553, 2554 8,849.882 3

18-May-2022 2555, 2556, 2557, 2558, 2559, 2560, 2561 8,862.513 3

19-May-2022 2562, 2563, 2564 8,867.892 3

20-May-2022 2565, 2566, 2567 8,873.292 3


21-May-2022 2568, 2569 8,876.800 3
22-May-2022 2569 8,877.425 3
23-May-2022 2569
24-May-2022 2569
25-May-2022 2569
26-May-2022 2569

27-May-2022 2569

28-May-2022 2569

29-May-2022 2569

30-May-2022 2569

31-May-2022 2569
01-Jun-2022 2569

02-Jun-2022 2570, 2571, 2572

03-Jun-2022 2572

04-Jun-2022 2572

05-Jun-2022 T1, T2, T3, T4, T5


06-Jun-2022 T6, T7, T8, T9, T10
07-Jun-2022 T11, T12, T13, T14, T15
08-Jun-2022 T16, T17, T18, T19, T20, T21
09-Jun-2022 T22, T23, T24, T25, T26, T27, T28,
10-Jun-2022 T29, T30, T31, T32, T34, T35, T36
11-Jun-2022 T37, T38
T38
12-Jun-2022

T38
13-Jun-2022

T38
14-Jun-2022
CIPAL
METRO D´ALGER
ION EL HARRACH CENTRE - BAB EZZOUAR - AÉROPORT INTERNATIONAL D´ARGER

CONTRÔLE DE PRODUCTIVITÉ TBM - EPB AL KAHINA

LONGUEUR PARTIEL LONGUEUR TOTAL EXCAVATION PK ANNEAUX PRODUCTION QUOTIDIENNE


EXCAVÉE (m) ACCUMULÉE (m) ANNEAUX DE VOUSSOIRS

0.000 0.000 3,863.820


1.540 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
0.000 1.540 3,865.360 0
1.076 2.616 3,866.436 0
0.450 3.066 3,866.886 0
0.406 3.472 3,867.292 0
2.246 5.718 3,869.538 0
0.400 6.118 3,869.938 0
0.400 6.518 3,870.338 0
0.717 7.235 3,871.055 0
2.428 9.663 3,873.483 1
0.889 10.552 3,874.372 1
3.569 14.121 3,877.941 1
0.970 15.091 3,878.911 1
0.000 15.091 3,878.911 0
0.000 15.091 3,878.911 0
0.000 15.091 3,878.911 0
0.000 15.091 3,878.911 0
1.080 16.171 3,879.991 0
2.236 18.407 3,882.227 1
0.378 18.785 3,882.605 1
1.620 20.405 3,884.225 1
0.400 20.805 3,884.625 0
0.400 21.205 3,885.025 0
0.947 22.152 3,885.972 1
1.645 23.797 3,887.617 1
2.322 26.119 3,889.939 1
2.230 28.349 3,892.169 1
0.000 28.349 3,892.169 1
0.000 28.349 3,892.169 0
0.000 28.349 3,892.169 0
0.000 28.349 3,892.169 0
1.763 30.112 3,893.932 0
1.531 31.643 3,895.463 1
0.000 31.643 3,895.463 0
1.095 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.000 32.738 3,896.558 0
0.618 33.356 3,897.176 1
0.000 33.356 3,897.176 0
1.955 35.311 3,899.131 1
1.405 36.716 3,900.536 1
1.702 38.418 3,902.238 1
0.000 38.418 3,902.238 0
0.000 38.418 3,902.238 0
0.000 38.418 3,902.238 0
0.079 38.497 3,902.317 0
1.630 40.127 3,903.947 0
0.095 40.222 3,904.042 1
0.000 40.222 3,904.042 0
0.000 40.222 3,904.042 0
0.000 40.222 3,904.042 0
0.000 40.222 3,904.042 0
0.126 40.348 3,904.168 0
0.046 40.394 3,904.214 0
0.032 40.426 3,904.246 0
0.073 40.499 3,904.319 0
0.000 40.499 3,904.319 0
0.000 40.499 3,904.319 0
0.000 40.499 3,904.319 0
0.005 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.000 40.504 3,904.324 0
0.024 40.528 3,904.348 0
0.000 40.528 3,904.348 0
0.119 40.647 3,904.467 0
0.000 40.647 3,904.467 0
1.517 42.164 3,905.984 0
0.304 42.468 3,906.288 0
0.000 42.468 3,906.288 1
0.003 42.471 3,906.291 0
0.130 42.601 3,906.421 0
0.116 42.717 3,906.537 0
1.226 43.943 3,907.763 1
0.836 44.779 3,908.599 1
2.781 47.560 3,911.380 2
0.000 47.560 3,911.380 0
1.800 49.360 3,913.180 1
1.909 51.269 3,915.089 1
3.452 54.721 3,918.541 1
1.811 56.532 3,920.352 1
1.820 58.352 3,922.172 2
4.658 63.010 3,926.830 2
3.973 66.983 3,930.803 2
3.977 70.960 3,934.780 2
0.000 70.960 3,934.780 0
0.000 70.960 3,934.780 0
5.153 76.113 3,939.933 2
3.807 79.920 3,943.740 3
0.138 80.058 3,943.878 0
0.000 80.058 3,943.878 0
0.000 80.058 3,943.878 0
0.000 80.058 3,943.878 0
0.000 80.058 3,943.878 0
0.000 80.058 3,943.878 0
0.001 80.059 3,943.879 0
8.931 88.990 3,952.810 4
0.000 88.990 3,952.810 0
1.748 90.738 3,954.558 4
5.364 96.102 3,959.922 4
5.509 101.611 3,965.431 0
1.764 103.375 3,967.195 1
2.668 106.043 3,969.863 1
0.000 106.043 3,969.863 0
0.000 106.043 3,969.863 0
0.935 106.978 3,970.798 1
5.413 112.391 3,976.211 3
5.914 118.305 3,982.125 3
6.706 125.011 3,988.831 4
2.453 127.464 3,991.284 4
6.587 134.051 3,997.871 3
5.380 139.431 4,003.251 1
0.000 139.431 4,003.251 0
2.148 141.579 4,005.399 2
8.713 150.292 4,014.112 4
7.206 157.498 4,021.318 4
7.925 165.423 4,029.243 3
9.922 175.345 4,039.165 7
0.000 175.345 4,039.165 0
5.585 180.930 4,044.750 3
5.057 185.987 4,049.807 3
3.954 189.941 4,053.761 2
4.366 194.307 4,058.127 3
11.842 206.149 4,069.969 6
5.536 211.685 4,075.505 6
7.144 218.829 4,082.649 2
3.684 222.513 4,086.333 1
0.000 222.513 4,086.333 0
0.000 222.513 4,086.333 0
0.000 222.513 4,086.333 0
0.000 222.513 4,086.333 0
0.000 222.513 4,086.333 0
0.000 222.513 4,086.333 0
0.000 222.513 4,086.333 0
0.000 222.513 4,086.333 0
0.001 222.514 4,086.334 0
3.467 225.981 4,089.801 1
7.220 233.201 4,097.021 4
9.116 242.317 4,106.137 5
1.800 244.117 4,107.937 1
0.000 244.117 4,107.937 0
12.574 256.691 4,120.511 7
9.116 265.807 4,129.627 6
0.000 265.807 4,129.627 0
0.056 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
0.000 265.863 4,129.683 0
6.775 272.638 4,136.458 3
9.317 281.955 4,145.775 5
9.499 291.454 4,155.274 7
12.123 303.577 4,167.397 6
5.376 308.953 4,172.773 4
10.831 319.784 4,183.604 6
0.000 319.784 4,183.604 0
14.540 334.324 4,198.144 7
12.562 346.886 4,210.706 7
16.159 363.045 4,226.865 7
16.256 379.301 4,243.121 10
9.060 388.361 4,252.181 6
0.000 388.361 4,252.181 0
0.027 388.388 4,252.208 0
10.016 398.404 4,262.224 5
11.597 410.001 4,273.821 6
16.458 426.459 4,290.279 10
14.243 440.702 4,304.522 7
14.400 455.102 4,318.922 8
3.708 458.810 4,322.630 3
0.000 458.810 4,322.630 0
0.000 458.810 4,322.630 0
0.000 458.810 4,322.630 0
0.000 458.810 4,322.630 0
0.000 458.810 4,322.630 0
0.000 458.810 4,322.630 0
0.000 458.810 4,322.630 0
0.000 458.810 4,322.630 0
8.190 467.000 4,330.820 4
11.530 478.530 4,342.350 7
5.601 484.131 4,347.951 3
1.609 485.740 4,349.560 1
3.630 489.370 4,353.190 1
5.400 494.770 4,358.590 3
0.000 494.770 4,358.590 0
4.945 499.715 4,363.535 3
6.983 506.698 4,370.518 4
6.619 513.317 4,377.137 4
6.804 520.121 4,383.941 4
1.680 521.801 4,385.621 1
0.000 521.801 4,385.621 0
0.000 521.801 4,385.621 0
0.000 521.801 4,385.621 0
0.237 522.038 4,385.858 0
0.000 522.038 4,385.858 0
0.000 522.038 4,385.858 0
0.000 522.038 4,385.858 0
0.000 522.038 4,385.858 0
0.000 522.038 4,385.858 0
0.107 522.145 4,385.965 0
0.000 522.145 4,385.965 0
0.001 522.146 4,385.966 0
0.000 522.146 4,385.966 0
0.000 522.146 4,385.966 0
0.001 522.147 4,385.967 0
0.000 522.147 4,385.967 0
0.000 522.147 4,385.967 0
0.000 522.147 4,385.967 0
0.009 522.156 4,385.976 0
0.000 522.156 4,385.976 0
0.001 522.157 4,385.977 0
0.000 522.157 4,385.977 0
0.000 522.157 4,385.977 0
6.233 528.390 4,392.210 3
6.116 534.506 4,398.326 4
3.510 538.016 4,401.836 2
10.826 548.842 4,412.662 6
9.000 557.842 4,421.662 5
8.497 566.339 4,430.159 5
0.000 566.339 4,430.159 0
6.000 572.339 4,436.159 3
9.152 581.491 4,445.311 5
7.010 588.501 4,452.321 4
0.087 588.588 4,452.408 0
13.086 601.674 4,465.494 7
15.200 616.874 4,480.694 8
0.000 616.874 4,480.694 0
11.567 628.441 4,492.261 7
14.167 642.608 4,506.428 8
7.423 650.031 4,513.851 4
14.386 664.417 4,528.237 8
13.705 678.122 4,541.942 7
13.117 691.239 4,555.059 7
0.000 691.239 4,555.059 0
0.117 691.356 4,555.176 1
0.006 691.362 4,555.182 0
5.217 696.579 4,560.399 2
12.735 709.314 4,573.134 8
11.057 720.371 4,584.191 6
14.548 734.919 4,598.739 8
0.000 734.919 4,598.739 0
14.332 749.251 4,613.071 8
15.015 764.266 4,628.086 8
12.051 776.317 4,640.137 7
23.149 799.466 4,663.286 13
1.873 801.339 4,665.159 1
0.000 801.339 4,665.159 0
0.000 801.339 4,665.159 0
12.647 813.986 4,677.806 7
10.868 824.854 4,688.674 6
21.525 846.379 4,710.199 12
17.067 863.446 4,727.266 9
4.203 867.649 4,731.469 2
0.000 867.649 4,731.469 0
0.000 867.649 4,731.469 0
0.387 868.036 4,731.856 1
1.818 869.854 4,733.674 1
9.938 879.792 4,743.612 4
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0.000 4,862.860 0
7.200 7.200 4,870.060 0
1.800 9.000 4,871.860 0
1.800 10.800 4,873.660 1
0.000 10.800 4,873.660 0
0.000 10.800 4,873.660 0
0.000 10.800 4,873.660 0
1.340 12.140 4,875.000 2
1.570 13.710 4,876.570 1
1.909 15.619 4,878.479 1
7.943 23.562 4,886.422 4
0.000 23.562 4,886.422 0
7.200 30.762 4,893.622 4
8.382 39.144 4,902.004 5
0.645 39.789 4,902.649 0
2.840 42.629 4,905.489 2
11.380 54.009 4,916.869 7
13.860 67.869 4,930.729 7
10.800 78.669 4,941.529 6
0.000 78.669 4,941.529 0
8.517 87.186 4,950.046 4
16.763 103.949 4,966.809 10
12.695 116.644 4,979.504 7
0.000 116.644 4,979.504 0
0.000 116.644 4,979.504 0
0.000 116.644 4,979.504 0
12.600 129.244 4,992.104 7
13.834 143.078 5,005.938 7
21.738 164.816 5,027.676 12
16.610 181.426 5,044.286 9
15.027 196.453 5,059.313 9
6.584 203.037 5,065.897 4
0.000 203.037 5,065.897 0
12.600 215.637 5,078.497 7
18.045 233.682 5,096.542 10
10.810 244.492 5,107.352 6
2.458 246.950 5,109.810 3
15.360 262.310 5,125.170 7
5.600 267.910 5,130.770 4
0.000 267.910 5,130.770 0
10.800 278.710 5,141.570 6
10.850 289.560 5,152.420 5
0.000 289.560 5,152.420 1
12.635 302.195 5,165.055 7
10.782 312.977 5,175.837 6
0.000 312.977 5,175.837 0
0.000 312.977 5,175.837 0
0.000 312.977 5,175.837 0
0.000 312.977 5,175.837 0
1.782 314.759 5,177.619 1
9.182 323.941 5,186.801 5
8.890 332.831 5,195.691 5
5.379 338.210 5,201.070 3
0.000 338.210 5,201.070 0
0.000 338.210 5,201.070 0
21.670 359.880 5,222.740 12
10.821 370.701 5,233.561 6
16.228 386.929 5,249.789 9
14.441 401.370 5,264.230 8
18.034 419.404 5,282.264 10
0.000 419.404 5,282.264 0
9.000 428.404 5,291.264 5
9.036 437.440 5,300.300 5
18.000 455.440 5,318.300 9
10.834 466.274 5,329.134 7
7.166 473.440 5,336.300 3
12.680 486.120 5,348.980 8
0.000 486.120 5,348.980 0
5.400 491.520 5,354.380 3
5.433 496.953 5,359.813 3
7.208 504.161 5,367.021 4
0.000 504.161 5,367.021 0
7.216 511.377 5,374.237 4
12.618 523.995 5,386.855 7
0.000 523.995 5,386.855 0
12.600 536.595 5,399.455 7
14.464 551.059 5,413.919 8
1.789 552.848 5,415.708 1
19.862 572.710 5,435.570 11
19.829 592.539 5,455.399 11
9.425 601.964 5,464.824 5
0.000 601.964 5,464.824 0
11.677 613.641 5,476.501 7
16.799 630.440 5,493.300 9
17.915 648.355 5,511.215 10
7.201 655.556 5,518.416 4
10.963 666.519 5,529.379 6
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0
0.000 0.000 0
0.536 0.536 5,670.506 0
0.000 0.536 5,670.506 0
7.200 7.736 5,677.706 0
5.400 13.136 5,683.106 3
0.006 13.142 5,683.112 0
2.164 15.306 5,685.276 1
2.152 17.458 5,687.428 1
10.486 27.944 5,697.914 6
9.510 37.454 5,707.424 5
0.000 37.454 5,707.424 0
0.000 37.454 5,707.424 0
15.356 52.810 5,722.780 8
10.690 63.500 5,733.470 7
0.586 64.086 5,734.056 0
0.000 64.086 5,734.056 0
7.060 71.146 5,741.116 4
4.971 76.117 5,746.087 3
0.000 76.117 5,746.087 0
1.932 78.049 5,748.019 1
7.224 85.273 5,755.243 4

0.000 85.273 5,755.243 0

0.000 85.273 5,755.243 0

0.000 85.273 5,755.243 0

0.000 85.273 5,755.243 0

0.000 85.273 0
5,755.243

0.000 85.273 5,755.243 0

0.000 85.273 5,755.243 0

0.000 85.273 5,755.243 0

5.803 91.076 5,761.046 3

16.200 107.276 5,777.246 9


16.200 123.476 5,793.446 9
17.614 141.090 5,811.060 10

16.548 157.638 5,827.608 11

15.472 173.110 5,843.080 10

11.450 184.560 5,854.530 9


7.086 191.646 5,861.616 5

10.796 202.442 5,872.412 8

1.523 203.965 5,873.935 2

0.000 203.965 5,873.935 0


0.000 203.965 5,873.935 0
0.076 204.041 5,874.011 0

8.940 212.981 5,882.951 6

13.309 226.290 5,896.260 10

11.200 237.490 5,907.460 8

11.200 248.690 5,918.660 8

11.710 260.400 5,930.370 8

9.776 270.176 5,940.146 7

11.051 281.227 5,951.197 8

14.023 295.250 5,965.220 10

16.830 312.080 5,982.050 12

0.000 312.080 5,982.050 0

9.800 321.880 5,991.850 7

9.920 331.800 6,001.770 7

0.240 332.040 6,002.010 0


13.740 345.780 6,015.750 9

9.662 355.442 6,025.412 7

8.498 363.940 6,033.910 4

16.800 380.740 6,050.710 12

16.800 397.540 6,067.510 12

11.305 408.845 6,078.815 11

15.167 424.012 6,093.982 10

14.097 438.109 6,108.079 10

15.476 453.585 6,123.555 12

9.512 463.097 6,133.067 5

11.600 474.697 6,144.667 7


12.600 487.297 6,157.267 7
13.665 500.962 6,170.932 7
17.848 518.810 6,188.780 10
14.560 533.370 6,203.340 9
14.430 547.800 6,217.770 9
0.000 547.800 6,217.770 0
14.400 562.200 6,232.170 8

0.000 562.200 6,232.170 0

0.000 562.200 6,232.170 0

0.000 562.200 6,232.170 0

0.000 562.200 6,232.170 0

0.000 562.200 6,232.170 0

3.740 565.940 6,235.910 2

3.600 569.540 6,239.510 2

0.000 569.540 6,239.510 0

10.738 580.278 6,250.248 5

10.805 591.083 6,261.053 7

0.000 591.083 6,261.053 0

1.777 592.860 6,262.830 0

0.000 592.860 6,262.830 0

5.400 598.260 6,268.230 3

16.200 614.460 6,284.430 9

16.258 630.718 6,300.688 9


14.396 645.114 6,315.084 7
12.632 657.746 6,327.716 7

10.813 668.559 6,338.529 7

12.628 681.187 6,351.157 6


0.000 681.187 6,351.157 0
0.000 681.187 6,351.157 0

17.953 699.140 6,369.110 11

19.810 718.950 6,388.920 11

14.400 733.350 6,403.320 8

19.820 753.170 6,423.140 11

18.030 771.200 6,441.170 10

18.000 789.200 6,459.170 10

15.923 805.123 6,475.093 8

0.000 805.123 6,475.093 0

15.193 820.316 6,490.286 9

13.984 834.300 6,504.270 7

3.590 837.890 6,507.860 3

17.890 855.780 6,525.750 10

12.600 868.380 6,538.350 7

12.600 880.980 6,550.950 7

12.896 893.876 6,563.846 7

3.384 897.260 6,567.230 2

12.664 909.924 6,579.894 7

14.346 924.270 6,594.240 8

22.178 946.448 6,616.418 12

12.812 959.260 6,629.230 12

10.800 970.060 6,640.030 6


0.000

5.303 5.303 6,773.763

3.722 9.025 6,777.485 1

10.8 19.825 6,788.285 6

10.8 30.625 6,799.085 6

18.04 48.665 6,817.125 10

16.232 64.897 6,833.357 9

23.415 88.312 6,856.772 14

18.359 106.671 6,875.131 10

18 124.671 6,893.131 10

19.577 144.248 6,912.708 10

0 144.248 6,912.708 0

6.502 150.750 6,919.210 3

1.014 151.764 6,920.224 1

0 151.764 6,920.224 0

0 151.764 6,920.224 0

5.4 157.164 6,925.624 3

5.4 162.564 6,931.024 3

6.806 169.370 6,937.830 4

0.094 169.464 6,937.924 0

0.029 169.493 6,937.953 0

0 169.493 6,937.953 0
0 169.493 6,937.953 0
0 169.493 6,937.953 0
0 169.493 6,937.953 0
0.081 169.574 6,938.034 0
0.205 169.779 6,938.239 0
0 169.779 6,938.239 0
0.221 170.000 6,938.460 0
0 170.000 6,938.460 0
0 170.000 6,938.460 0
0 170.000 6,938.460 0
0 170.000 6,938.460 0
0.217 170.217 6,938.677 0
0 170.217 6,938.677 0

0 170.217 6,938.677 0

13.493 183.710 6,952.170 8


0 183.710 6,952.170 0
16.23 199.940 6,968.400 8
18.096 218.036 6,986.496 9
14.444 232.480 7,000.940 9
0 232.480 7,000.940 0
0 232.480 7,000.940 0
5.203 237.683 7,006.143 2
0 237.683 7,006.143 0
16 253.683 7,022.143 8
10.973 264.656 7,033.116 7

9.244 273.900 7,042.360 6

0 273.900 7,042.360 0

0 273.900 7,042.360 0

0 273.900 7,042.360 0
0 273.900 7,042.360 0
14.5 288.400 7,056.860 8
10.8 299.200 7,067.660 6
0 299.200 7,067.660 0
0 299.200 7,067.660 0
0 299.200 7,067.660 0
17.997 317.197 7,085.657 10
0 317.197 7,085.657 0
9 326.197 7,094.657 5
14.188 340.385 7,108.845 8
9.298 349.683 7,118.143 5
8.851 358.534 7,126.994 5

3.516 362.050 7,130.510 2

11 373.050 7,141.510 4

5.4 378.450 7,146.910 3

5.5 383.950 7,152.410 3

3.377 387.327 7,155.787 3

6.463 393.790 7,162.250 3

6.298 400.088 7,168.548 4

10.812 410.900 7,179.360 6

1.83 412.730 7,181.190 1

0.014 412.744 7,181.204 0

0 412.744 7,181.204 0
0 412.744 7,181.204 0
0 412.744 7,181.204 0

0 412.744 7,181.204 0

0 412.744 7,181.204 0

0 412.744 7,181.204 0

0 412.744 7,181.204 0

1.72 414.464 7,182.924 1

8.873 423.337 7,191.797 5


10.843 434.180 7,202.640 6
12.58 446.760 7,215.220 7
12.6 459.360 7,227.820 7
9.13 468.490 7,236.950 5
0 468.490 7,236.950 0
16.24 484.730 7,253.190 9
10.73 495.460 7,263.920 6
16.37 511.830 7,280.290 9
16.2 528.030 7,296.490 9
14.43 542.460 7,310.920 8
12.63
555.090 7,323.550 6

0 555.090 7,323.550 0
14.4 569.490 7,337.950 8
12.55 582.040 7,350.500 8
7.3

589.340 7,357.800 4
3.7 593.040 7,361.500 2
1.722
594.762 7,363.222 1

0 594.762 7,363.222 0
0 594.762 7,363.222 0
0 594.762 7,363.222 0
0 594.762 7,363.222 0
0 594.762 7,363.222 0
0 594.762 7,363.222 0
0 594.762 7,363.222 0
0
594.762 7,363.222 0

0.000

0.816 0.816 7,488.016

1.018 1.834 7,489.034

3.786 5.620 7,492.820

0.000 5.620 7,492.820


0.000 5.620 7,492.820
1.825 7.445 7,494.645 2
8.993 16.438 7,503.638 4
3.592 20.030 7,507.230 1

0.000 20.030 7,507.230 0

7.199 27.229 7,514.429 4

0.000 27.229 7,514.429 0

0.000 27.229 7,514.429 0

0.000 27.229 7,514.429 0

1.801 29.030 7,516.230 1

0.000 29.030 7,516.230 0

0.000 29.030 7,516.230 0

0.000 29.030 7,516.230 0

3.600
32.630 7,519.830 2
7.223
39.853 7,527.053 4

14.417
54.270 7,541.470 8

16.189
70.459 7,557.659 9
3.058 73.517 7,560.717 1

11.244
84.761 7,571.961 6
0.000 84.761 7,571.961 0

13.007
97.768 7,584.968 8
6.925
104.693 7,591.893 5

0.000
104.693 7,591.893 0

0.000
104.693 7,591.893 0

9.237
113.930 7,601.130 4

0.000
113.930 7,601.130 0

4.051
117.981 7,605.181 2

0.000
117.981 7,605.181 0

0.000
117.981 7,605.181 0
9.135
127.116 7,614.316 5
8.125
135.241 7,622.441 5

16.306 151.547 7,638.747 9

10.661 162.208 7,649.408 5

0.000 162.208 7,649.408 0

0.067 162.275 7,649.475 1

0.000 162.275 7,649.475 0

0.000 162.275 7,649.475 0

0.000 162.275 7,649.475 0

0.000 162.275 7,649.475 0

0.000 162.275 7,649.475 0

0.015 0

162.290 7,649.490
0.000 0

162.290 7,649.490
0.000 0

162.290 7,649.490

1.893 164.183 7,651.383 0

7.206 171.389 7,658.589 4

0.000 171.389 7,658.589 0

5.383 176.772 7,663.972 3

0.064 176.836 7,664.036 0


0.000 176.836 7,664.036 0
0.000 176.836 7,664.036 0
0.000 7,664.036 0
176.836

14.364 8
191.200 7,678.400

20.064 211.264 7,698.464 11


15.966 8
227.230 7,714.430

5.401 7,719.831 3
232.631

0.000 232.631 7,719.831 0


0.000 7,719.831 0
232.631

10.798 7,730.629 7
243.429
13.368 7,743.997 6
256.797

8.225 7,752.222 4
265.022

17.903 7,770.125 10
282.925

16.345 7,786.470 9
299.270
0.000 299.270 7,786.470 0
18.020 317.290 7,804.490 10
3.630 7,808.120 2
320.920

7.220 7,815.340 4
328.140

14.950 7,830.290 8
343.090

6.650 7,836.940 4
349.740

23.400 7,860.340 13
373.140
0.000 373.140 7,860.340 0
12.690 7,873.030 7
385.830

0.668
386.498 7,873.698 0

13.614
400.112 7,887.312 8

0.000
400.112 7,887.312 0

5.486
405.598 7,892.798 3
0.000 405.598 7,892.798 0

12.600
418.198 7,905.398 7
10.856 429.054 7,916.254 6

7.679
436.733 7,923.933 4

0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0


0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0

0.000 436.733 7,923.933 0


5.400 442.133 7,929.333 3
0.000 442.133 7,929.333 0

11.917 454.050 7,941.250 6

1.670 455.720 7,942.920 1

5.561 461.281 7,948.481 3

17.186 478.467 7,965.667 10

13.635 492.102 7,979.302 7

16.200
508.302 7,995.502 9
0.000 508.302 7,995.502 0

9.020 517.322 8,004.522 6

9.008 526.330 8,013.530 5

19.850 546.180 8,033.380 11

19.860 566.040 8,053.240 11


14.400 580.440 8,067.640 8

0.000 580.440 8,067.640 0

0.000 580.440 8,067.640 0

17.997 598.437 8,085.637 11

23.448 621.885 8,109.085 13

16.231 638.116 8,125.316 10

10.836 648.952 8,136.152 5

11.141 660.093 8,147.293 6

19.800 679.893 8,167.093 11

0.000 679.893 8,167.093 0

21.309 701.202 8,188.402 11

16.211 717.413 8,204.613 9

19.678 737.091 8,224.291 10

18.187 755.278 8,242.478 11

19.554 774.832 8,262.032 11


9.297 784.129 8,271.329 5

0.000 784.129 8,271.329 0

0.000 784.129 8,271.329 0

0.000 784.129 8,271.329 0

0.000 784.129 8,271.329 0

0.000 784.129 8,271.329 0

7.202 791.331 8,278.531 3

10.800 802.131 8,289.331 6

12.600 814.731 8,301.931 7

10.835 825.566 8,312.766 7

15.634 841.200 8,328.400 10

14.984 856.184 8,343.384 7

17.737 873.921 8,361.121 9

14.721 888.642 8,375.842 9

0.000 888.642 8,375.842


0

0.000 888.642 8,375.842


0

0.000 888.642 8,375.842


0
0.000 888.642 8,375.842
0

19.848 908.490 8,395.690 10

14.995 923.485 8,410.685 7

17.589 941.074 8,428.274 12

7.200

948.274 8,435.474 5
0.000 948.274 8,435.474 0
11.001

959.275 8,446.475 6
16.055 975.330 8,462.530 9
10.798 986.128 8,473.328 5
14.598 1,000.726 8,487.926 9

16.046 1,016.772 8,503.972 9

14.400 1,031.172 8,518.372 8

1.759 1,032.931 8,520.131 9

7.260 1,040.191 8,527.391 4

3.582 1,043.773 8,530.973 2

9.015 1,052.788 8,539.988 5

11.596 1,064.384 8,551.584 8

13.976 1,078.360 8,565.560 10

3.116 1,081.476 8,568.676 1

0.000 1,081.476 8,568.676 0

0.000 1,081.476 8,568.676 0


0.000 1,081.476 8,568.676 0

0.000 1,081.476 8,568.676 0

0.000 1,081.476 8,568.676 0

0.112 1,081.588 8,568.788 0

7.000 1,088.588 8,575.788 5


11.200 1,099.788 8,586.988 8

9.392 1,109.180 8,596.380 8

7.110 1,116.290 8,603.490 5


6.933 1,123.223 8,610.423 5

14.108 1,137.331 8,624.531 11

8.398 1,145.729 8,632.929 8


9.800 1,155.529 8,642.729 7

11.200 1,166.729 8,653.929 8

11.257 1,177.986 8,665.186 8

12.963 1,190.949 8,678.149 9

6.621 1,197.570 8,684.770 6


12.620 1,210.190 8,697.390 9

5.689 1,215.879 8,703.079 4

14.000 1,229.879 8,717.079 10

13.200 1,243.079 8,730.279 9

4.991 1,248.070 8,735.270 4

0.000 1,248.070 8,735.270 0


0.000 1,248.070 8,735.270 0
0.000 1,248.070 8,735.270 0
4.880 1,252.950 8,740.150 3

9.800 1,262.750 8,749.950 7

10.630 1,273.380 8,760.580 9

0.000 1,273.380 8,760.580 0


11.209 1,284.589 8,771.789 8
0.000 1,284.589 8,771.789 0
11.071
1,295.660 8,782.860 8

11.577 1,307.237 8,794.437 8

5.600
1,312.837 8,800.037 4

5.200
1,318.037 8,805.237 4

5.667
1,323.704 8,810.904 4
14.217 1,337.921 8,825.121 9

16.261 1,354.182 8,841.382 9

12.631 1,366.813 8,854.013 7

5.379 1,372.192 8,859.392 3

5.400 1,377.592 8,864.792 3


3.508 1,381.100 8,868.300 2
0.625 1,381.725 8,868.925 0
0
0
0

0
0
3
0
0
RGER

OBSERVATIONS

TEST - 0
Debut d´excavation de la parois moulé
TEST- 1. Changement des 55 disques de la tête
TEST- 1. Changement des 55 disques de la tête
TEST- 1. Changement des 55 disques de la tête
Pas d´activité dans le TBM. Noel.
TEST- 1. Changement des 55 disques de la tête
TEST- 1. Changement des 55 disques de la tête
TEST- 1. Changement des 55 disques de la tête
TEST- 1. Changement des 55 disques de la tête
TEST 1. Verification partie de l´avant de la tete de coupe (nez)
TEST 1. Verification partie de l´avant de la tete de coupe (nez)
Pas d´activité dans le TBM. 1 Janvier.
TEST 1. Réglage TBM, calibrage et acquisition de donnée
TEST 1. Réglage TBM, calibrage et acquisition de donnée
TEST 1. Réglage TBM, calibrage et acquisition de donnée
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Creusement jet grouting.
TEST 1. Réglages TBM. Joint d ´etancheité.
TEST 1. Réglages TBM. Joint d ´etancheité.
TEST 1. Réglages TBM. Joint d ´etancheité.
TEST 1. Réglages TBM. Joint d ´etancheité.
TEST 1. Réglages TBM. Joint d ´etancheité.
TEST 2. Réglages TBM. Excavation.
TEST 2. Réglages TBM. Excavation.
EXCAVATION. Injection bi-composant. 1º anneau.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

SANS EXCAVATION
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

EXCAVATION MINIMALE POUR RAISONES OPERATIONELLES

EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
JOUR FÉRIE
JOUR FÉRIE
EXCAVATION.
EXCAVATION.
EXCAVATION.
JOUR FÉRIE
JUNCTION DE BANDE / CABLE DE MOYENNE TENSION
JUNCTION DE BANDE / CABLE DE MOYENNE TENSION
JUNCTION DE BANDE
BANDE MISE À TENSION, ¨WINCH¨
¨WINCH¨ NON OPERATIONNEL
EXCAVATION.
JOUR FÉRIE
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
¨WINCH¨ NON OPERATIONNEL
JOUR FÉRIE
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
JOUR FÉRIE
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
JOUR FÉRIE
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.

EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
USTHB
TBM EXT
TBM. Creusement jet grouting.
TBM. Creusement jet grouting.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION
SANS EXCAVATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
RABIA TAHAR
EXCAVATION.
SANS EXCAVATION- RUPTURE DU JOINT DE LA STATION
EXCAVATION.
EXCAVATION.
EXCAVATION.
EXCAVATION.
SANS EXCAVATION- RUPTURE DU TAPIS DU CONVOYEUR
SANS EXCAVATION- RUPTURE DU TAPIS DU CONVOYEUR
EXCAVATION.
PANNE DANS LE SYSTEME DE LA MOUSSE
ARRET A CAUSE DU FRONT DE TAILLE MIXTE (ROCHE)
ARRET A CAUSE DU FRONT DE TAILLE MIXTE (ROCHE)
FRONT MIXTE, DIFFICULTÉ D´EXCAVER
FRONT MIXTE, DIFFICULTÉ D´EXCAVER
CHANGEMENT DE RIPPERS POUR DES MOLETTES DE COUPE(60)
TERRAIN MIXTE, DIFFICULTÉ D´EXCAVER
PANNE DU CONVOYEUR VERTICAL A OUED SMAR
PANNE DU CONVOYEUR VERTICAL A OUED SMAR ET
CHANGEMENT DE RIPPERS POUR DES MOLETTES DE COUPE
PANNE DU CONVOYEUR VERTICAL A OUED SMAR ET
CHANGEMENT DE RIPPERS POUR DES MOLETTES DE COUPE
PANNE DU CONVOYEUR VERTICAL A OUED SMAR ET
CHANGEMENT DE RIPPERS POUR DES MOLETTES DE COUPE
PANNE DU CONVOYEUR VERTICAL A OUED SMAR ET
CHANGEMENT DE RIPPERS POUR DES MOLETTES DE COUPE
PANNE DU CONVOYEUR VERTICAL A OUED SMAR ET INSTALLATION DES DOUBLES MOLETTES DANS LA ZONE CENTRALE DE LA
TETE DE COUPE
POUR FACILITER LA RUPTURE DES MATERIAUX COMPACTS ET LA PENETRATION DU TERRAIN

PANNE DU CONVOYEUR VERTICAL, AMELIORATION DE L´INSTALLATION POUR LE DEVERSEMENT


DES DEBLAIS
PANNE DU CONVOYEUR VERTICAL, AMELIORATION DE L´INSTALLATION POUR LE DEVERSEMENT
DES DEBLAIS
PANNE DU CONVOYEUR VERTICAL, AMELIORATION DE L´INSTALLATION POUR LE DEVERSEMENT
DES DEBLAIS
EXCAVATION EN TERRAIN MIXTE AVEC DES NIVEAUX COMPACTS DE GRÉS ET DE GRAVIERS CIMENTÉS,
AVEC MOLETTES
EXCAVATION AVEC MOLETTES
EXCAVATION AVEC MOLETTES
EXCAVATION AVEC MOLETTES
EXCAVATION AVEC MOLETTES. ZONE DE TRAJECTOIRE EN COURBE PERCEPTIBLE, UTILISATION DE L´ANNEAU DE 1,4 M (927 -
1.1147) ASYMETRIE ET POUSSAGE DES VERINS DU TBM (THRUST CYLINDER).
ANNEAU 1,4 m - 927

EXCAVATION AVEC MOLETTES. ZONE DE TRAJECTOIRE EN COURBE PERCEPTIBLE, UTILISATION DE


L´ANNEAU DE 1,4 M ASYMETRIE ET POUSSAGE DES VERINS DU TBM (THRUST CYLINDER)
EXCAVATION AVEC MOLETTES. ZONE DE TRAJECTOIRE EN COURBE PERCEPTIBLE, UTILISATION DE L´ANNEAU DE 1,4 M
ASYMETRIE ET POUSSAGE DES VERINS DU TBM (THRUST CYLINDER). PANNE DU SYSTEME D´INJECTION BI-COMPOSANT.
INTERVENTION DANS LA CHAMBRE HYPERBARE POUR VERIFIER
L´ETAT DES MOLETTES DE COUPE

PANNE DU SYSTEME D´INJECTION BI-COMPOSANT.


EXCAVATION AVEC MOLETTES. ZONE DE TRAJECTOIRE EN COURBE PERCEPTIBLE, UTILISATION DE
L´ANNEAU DE 1,4 M ASYMETRIE ET POUSSAGE DES VERINS DU TBM (THRUST CYLINDER).
EXCAVATION AVEC MOLETTES. ZONE DE TRAJECTOIRE EN COURBE PERCEPTIBLE, UTILISATION DE
L´ANNEAU DE 1,4 M ASYMETRIE ET POUSSAGE DES VERINS DU TBM (THRUST CYLINDER).
TBM 'A L´ARRÊT À CAUSE DE LA DÉVIATION PARA RAPPORT AU TRACÉ DE PROJET
TBM 'A L´ARRÊT À CAUSE DE LA DÉVIATION PARA RAPPORT AU TRACÉ DE PROJET
TBM 'A L´ARRÊT À CAUSE DE LA DÉVIATION PARA RAPPORT AU TRACÉ DE PROJET
EXCAVATION EN COURBE AVEC LES MOLLETES. ASYMETRIE NOTABLE DANS LES VERINS DE POUSÉE,
AUGMENTATION REMARQUABLE DES PATHOLOGIES DUE À LA SURCHARGE SUR LA STRUCTURE DEFINITIVE

EXCAVATION EN COURBE AVEC LES MOLLETES. ASYMETRIE NOTABLE DANS LES VERINS DE POUSÉE,
AUGMENTATION REMARQUABLE DES PATHOLOGIES DUE À LA SURCHARGE SUR LA STRUCTURE DEFINITIVE

EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
ARRET TEMPORAIRE DE L´EXCAVATION A CAUSE DES PROBLEMES DE BLOCAGE DU
CONVOYEUR
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES VOUSSOIRS PIEDROIT
GAUCHE. DEVERSEMENT DE DEBLAIS DU CONVOYEUR DANS UNE ZONE EN COURBE, ET CELA OBLIGE UN NETTOYAGE DE
TUNNEL CONTINUE.AVEC UNE ACCUMLATIONE DE BOUES AU NIVEAU DU BOUCLIER FRONTAL, QUI PROVOQUE UN RETARD DANS
L´INSTALLATION DE L´ANNEAU DE
VOUSSOIRS, DUE AUX TRAVAUX DE RETRAIT DE CES DEVERSEMENT

EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
ARRET TEMPORAIRE EN RAISON DES PROBLEMES LIÉS AUX POMPES DE GRAISSE DU BOUCLIER
ARRIERE. ARRET POUR EXTENSION DU CABLE MOYEN-TENSION, ET AUSSI ARRET SUITE A L´EXTENSION DU TAPIS DU
CONVOYEUR

EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE. ANNEAU 1,8 m - 1147
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
ARRET D´ACTIVITÉ EN RAISON DU JOUR FERIÉ (SELI)
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE
DANS LES VOUSSOIRS PIEDROIT GAUCHE. ARRET TEMPORAIRE A CAUSE DE LA PANNE DANS L´ERECTEUR DE VOUSSOIRS, ET
DEFAILLANCES TEMPORAIRE DANS L´ALIMENTATION ELECTRIQUE

ARRET TEMPORAIRE EN RAISON DE LA DEFAILLANCE DE LA VENTOUSE DE L´ERECTEUR DE


VOUSSOIRS (ANCRAGE)
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE. APPARITION DE FISSURE DANS LES
VOUSSOIRS PIEDROIT GAUCHE.
ARRET TEMPORAIRE EN RAISON DE LA DEFAILLANCE DU CONVOYEUR A OUED SMAR
ARRET TEMPORAIRE EN RAISON DE LA DEFAILLANCE DE LA VENTOUSE DE L´ERECTEUR DE
VOUSSOIRS (ANCRAGE)
EXCAVATION AVEC DES MOLETTES DE COUPE EN ZONE DE COURBE.
INCIDENT DANS LE TRANSPORT EN RAISON DU VEHICULE MULTISERVICE DU TUNNEL (TSP) AVEC
L´ANNEAU DE VOUSSOIR, BASCULEMENT DE LA CHARGE DANS LA STATION USTHB.
EXCAVATION AVEC DES MOLETTES DE COUPE.
EXCAVATION AVEC DES MOLETTES DE COUPE.
EXCAVATION AVEC DES MOLETTES DE COUPE.
EXCAVATION AVEC DES MOLETTES DE COUPE.
EXCAVATION AVEC DES MOLETTES DE COUPE.
EXCAVATION AVEC DES MOLETTES DE COUPE.
ARRET TEMPORAIRE EN RAISON DE L´EXTENSION DE LA BANDE DU CONVOYEUR
EXCAVATION AVEC DES MOLETTES DE COUPE.
ARRET POUR LE REMPLACEMENT DES MOLETTES DE COUPE. NOUVELLE CONFIGURATION DE LA TETE
MIXTE AVEC RIPPERS ET MOLETTES. L´INTERVENTION DANS LA CHAMBRE D´EXCAVATION A COMMENCÉ LE VENDREDI 23/
AVRIL/2021

ARRET POUR LE REMPLACEMENT DES MOLETTES DE COUPE. NOUVELLE CONFIGURATION DE LA TETE


MIXTE AVEC RIPPERS ET MOLETTES. L´INTERVENTION DANS LA CHAMBRE D´EXCAVATION A COMMENCÉ LE VENDREDI 23/
AVRIL/2021

ARRET POUR LE REMPLACEMENT DES MOLETTES DE COUPE. NOUVELLE CONFIGURATION DE LA TETE MIXTE AVEC RIPPERS ET
MOLETTES. L´INTERVENTION DANS LA CHAMBRE D´EXCAVATION A COMMENCÉ
LE VENDREDI 23/ AVRIL/2021

ARRET POUR LE REMPLACEMENT DES MOLETTES DE COUPE. NOUVELLE CONFIGURATION DE LA TETE MIXTE AVEC RIPPERS ET
MOLETTES. L´INTERVENTION DANS LA CHAMBRE D´EXCAVATION A COMMENCÉ
LE VENDREDI 23/ AVRIL/2022

ARRET POUR LE REMPLACEMENT DES MOLETTES DE COUPE. NOUVELLE CONFIGURATION DE LA TETE


MIXTE AVEC RIPPERS ET MOLETTES. L´INTERVENTION DANS LA CHAMBRE D´EXCAVATION A COMMENCÉ LE VENDREDI 23/
AVRIL/2023

ARRET TEMPORAIRE A CAUSE DU BOUCHAGE DU SYSTEME DE GROUTING. NOUVELLE CONFIGURATION AVEC UNE TETE DE
COUPE MIXTE, RIPPERS (20), MOLETTES (36), DOUBLE MOLETTES (6)

ARRET TEMPORAIRE A CAUSE D´UNE PANNE DANS LE CONVOYEUR DANS LA ZONE EN COURBE DU
TRONÇON 7, AVEC UN IMPORTANT DEVERSEMENT DE DEBLAIS VERS LE TUNNEL
ARRET TEMPORAIRE A CAUSE D´UNE PANNE DANS LE CONVOYEUR DANS LA ZONE EN COURBE DU
TRONÇON 7, AVEC UN IMPORTANT DEVERSEMENT DE DEBLAIS VERS LE TUNNEL
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
ARRET TEMPORAIRE DE L´ACTIVITÉ A CAUSE D´UNE PANNE DU VEHICULE MULTISERVICES (MULTI
PURPOSE VEHICLE , MPV).
ARRET DE L´ACTIVITÉ A CAUSE D´UNE PANNE DU VEHICULE MULTISERVICES (MULTI-PURPOSE VEHICLE ,
MPV)
PANNE DU VEHICULE MULTISERVICES (TSP), PROUCTION TRÉS LIMITÉE, EN RAISON DE LA LIMITATION
D´INTRODUCTION DE VOUSSOIR QUI EST DE SEULEMENT DE 3 VOUSSOIRS PAR TRAJET POUR UN ANNEAUX QUI EST CONSTITUÉ
PAR 9 VOUSSOIRS

PANNE DU VEHICULE MULTISERVICES (TSP), PROUCTION TRÉS LIMITÉE, EN RAISON DE LA LIMITATION


D´INTRODUCTION DE VOUSSOIR QUI EST DE SEULEMENT DE 3 VOUSSOIRS PAR TRAJET POUR UN ANNEAUX QUI EST CONSTITUÉ
PAR 9 VOUSSOIRS

PANNE DU VEHICULE MULTISERVICES (TSP), PROUCTION TRÉS LIMITÉE, EN RAISON DE LA LIMITATION


D´INTRODUCTION DE VOUSSOIR QUI EST DE SEULEMENT DE 3 VOUSSOIRS PAR TRAJET POUR UN ANNEAUX QUI EST CONSTITUÉ
PAR 9 VOUSSOIRS

EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20), MOLETTES (36), DOUBLES
MOLETTES (6), PANNE DANS LES VEHICULES MULTI SERVICES (TSP) AVEC DES PROBLEMES MECANIQUES ET ELECTRONIQUES. L
´UN DES VEHICULES FONCTIONNE AVEC DES DIFFICLTÉ

EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20), MOLETTES (36), DOUBLES
MOLETTES (6), PANNE DANS LES VEHICULES MULTI SERVICES (TSP) AVEC DES PROBLEMES MECANIQUES ET ELECTRONIQUES. L
´UN DES VEHICULES FONCTIONNE AVEC DES DIFFICLTÉ
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20), MOLETTES (36), DOUBLES
MOLETTES (6), PANNE DANS LES VEHICULES MULTI SERVICES (TSP) AVEC DES PROBLEMES MECANIQUES ET ELECTRONIQUES. L
´UN DES VEHICULES FONCTIONNE AVEC DES DIFFICLTÉ

PANNE TEMPORAIRE DE L´ERECTEUR DE VOUSSOIRE (LA CHAINE)


EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20), MOLETTES (36), DOUBLES
MOLETTES (6), PANNE DANS LES VEHICULES MULTI SERVICES (TSP) AVEC DES PROBLEMES MECANIQUES ET ELECTRONIQUES. L
´UN DES VEHICULES FONCTIONNE AVEC DES DIFFICLTÉ

EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20), MOLETTES (36), DOUBLES
MOLETTES (6), PANNE DANS LES VEHICULES MULTI SERVICES (TSP) AVEC DES PROBLEMES MECANIQUES ET ELECTRONIQUES. L
´UN DES VEHICULES FONCTIONNE AVEC DES DIFFICLTÉ

TRAVAUX D´ENTRETIEN
TRAVAUX D´ENTRETIEN
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20), MOLETTES (36), DOUBLES
MOLETTES (6) ARRET TEMPORAIRE DE PRODUCTION EN RAISON DE
L´EXTENSION DU CABLE DE LA FIBRE OPTIQUE

EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
ARRET EN RAISON DE L´EXTENSION DE LA BANDE DU CONVOYEUR
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
ARRET DE L´ACTIVITÉ DANS LE TUNNEL SUITE A LA RUPTURE DE LA BANDE DU CONVOYEUR DU BACK UP
DANS LE TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL SUITE A LA RUPTURE DE LA BANDE DU CONVOYEUR DU BACK UP
DANS LE TBM
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
ARRET TEMPORAIRE EN RAISON D´UNE PANNE- OBSTRUCTION DU CONVOYEUR A OUED SMAR DUE A LA
PRESENCE D´ARGILE TRÉS ADHESIVE
DES ARRETS TEMPORAIRES EN RAISON D´OBSTRUCTION DES TREMIES DUE A L´ARGILE TRÉS
ADHESIVES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION AVEC UNE TETE DE COUPE MIXTE, RIPPERS (20),
MOLETTES (36), DOUBLES MOLETTES (6)
JONCTION DU TUNNEL PRINCIPAL AVEC LA SATION SMAIL YEFSAH
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
INCIDENT: DEPLACEMENT DES DEUX VOUSSOIRS D´APPUI PAR APPORT A L´AXE (VERS LE COTÉ
GAUCHE) PROVOQUANT UNE ASYMETRIE PARTIEL DES BOGIES DU BACK UP DU TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
TRAVAUX POUR LE PASSAGE A LA STATION SMAIL YEFSAH AVEC LE TUNNELIER
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
INCIDENT: DEFAILLANCE AU NIVEAU DU SUPPORT DU CONVOYEUR VERTICAL A LA SORTIE DU BACK UP
DU TBM, AVEC ARRET TEMPORAIRE DES TRAVAUX D´EXCAVATION
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
EXCAVATION AVEC UNE NOUVELLE CONFIGURATION DE LA TETE DE COUPE POUR LES SOLS: 6 RIPPERS
DOUBLES, 50 RIPPERS SIMPLES, 6 MOLETTES PERIPHERIQUES
TRES MAUVAISE QUALITÉ D´AERATION DANS LE TUNNEL EN RAISON DU MANQUE DE VENTILLATION.
ARRET DES TRAVAUX DE PRODUCTION
TRES MAUVAISE QUALITÉ D´AERATION. INSTALLATION DE VENTILLATION EXTERIEUR, EXTENSION DE
CABLE ELECTRIQUE DE MOYENNE TENSION. DEFAILLANCE DE 2 GENERATEURS ELECTRIQUES
ARRET DE L´ACTIVITÉ EN RAISON DE LA DEFAILLANCE DE 2 GENERATEURS ELECTRIQUES (RUPTURE DE
LA POMPE D´EAU)
ARRET DE L´ACTIVITÉ EN RAISON DE LA DEFAILLANCE DE 2 GENERATEURS ELECTRIQUES (RUPTURE DE
LA POMPE D´EAU)
ARRET DE L´ACTIVITÉ EN RAISON DE LA DEFAILLANCE DE 2 GENERATEURS ELECTRIQUES (RUPTURE DE
LA POMPE D´EAU)
LES TRAVAUX DANS LE TUNNELIER TBM SONT EFFECTUÉS AVEC DIFFICULTÉ ET DANS DES DELAIS
EXCESSIF, EN RAISON DE L´EQUIPE PEU EXPERIMENTÉ
LES TRAVAUX DANS LE TUNNELIER TBM SONT EFFECTUÉS AVEC DIFFICULTÉ ET DANS DES DELAIS
EXCESSIF, EN RAISON DE L´EQUIPE PEU EXPERIMENTÉ
LES TRAVAUX DANS LE TUNNELIER TBM SONT EFFECTUÉS AVEC DIFFICULTÉ ET DANS DES DELAIS
EXCESSIF, EN RAISON DE L´EQUIPE PEU EXPERIMENTÉ
TRAVAUX DE PRODUCTION A L´ARRET. EXCAVATION LIMITÉ AU MAINTIEN DE LA PRESSION DANS LE
TUNNELIER ET EVITER UN EVENTUEL BLOCAGE DU TBM
TRAVAUX DE PRODUCTION A L´ARRET. EXCAVATION LIMITÉ AU MAINTIEN DE LA PRESSION DANS LE
TUNNELIER ET EVITER UN EVENTUEL BLOCAGE DU TBM
TUNNELIER TBM NON OPERATIONNEL. 0 TECHNICIENS/ OPERATEURS DANS LE TUNNEL
TUNNELIER TBM NON OPERATIONNEL. 4 TECHNICIENS/ OPERATEURS DANS LE TUNNEL
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DE PRODUCTION DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DE PRODUCTION DANS LE TUNNEL TBM
ARRET DE L´ACTIVITÉ DE PRODUCTION DANS LE TUNNEL TBM
REPRISE DE L´EXCAVATION MAIS SIX JOURS SUR SEPT (6/7) À CAUSE DES CONGÉS DU PERSONNEL ET
DU COVID19. LE VENDREDI EST LE JOUR D´ARRÊT
EXCAVATION
VENDREDI
EXCAVATION
EXCAVATION
EXCAVATION
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR VERTICAL.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR VERTICAL.
REPRISE DE L´EXCAVATION
VENDREDI
EXCAVATION
EXCAVATION
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR À L´INTERIEUR DU
TUNNEL. 1,500 m DE BANDE TRANSPORTEUSE DÉCHIRÉE.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR À L´INTERIEUR DU
TUNNEL. 1,500 m DE BANDE TRANSPORTEUSE DÉCHIRÉE.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR À L´INTERIEUR DU
TUNNEL. 1,500 m DE BANDE TRANSPORTEUSE DÉCHIRÉE.
REPRISE DE L´EXCAVATION
VENDREDI
EXCAVATION
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR VERTICAL.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR VERTICAL.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR VERTICAL.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR VERTICAL
EXCAVATION
VENDREDI
EXCAVATION
EXCAVATION
EXCAVATION
EXCAVATION
EXCAVATION AVEC DIFFICULTÉ A CAUSE D´EVENTUELLE USURE DES OUTILS DE COUPE (MOLETTES ET RIPPERS). PANNE DES
GENERATEURS ELECTRIQUES ET LIMITATION DE L´ALIMETATION ELECTRIQUE
POUR LE FONCTIONNEMENT DU TUNNEL TBM
EXCAVATION AVEC DIFFICULTÉ A CAUSE D´EVENTUELLE USURE DES OUTILS DE COUPE (MOLETTES ET RIPPERS). PANNE DES
GENERATEURS ELECTRIQUES ET LIMITATION DE L´ALIMETATION ELECTRIQUE
POUR LE FONCTIONNEMENT DU TUNNEL TBM
EXCAVATION AVEC DIFFICULTÉ A CAUSE D´EVENTUELLE USURE DES OUTILS DE COUPE (MOLETTES ET
RIPPERS). PANNE DES GENERATEURS ELECTRIQUES ET LIMITATION DE L´ALIMETATION ELECTRIQUE POUR LE
FONCTIONNEMENT DU TUNNEL TBM
EXCAVATION AVEC DIFFICULTÉ A CAUSE D´EVENTUELLE USURE DES OUTILS DE COUPE (MOLETTES ET RIPPERS). PANNE DES
GENERATEURS ELECTRIQUES ET LIMITATION DE L´ALIMETATION ELECTRIQUE
POUR LE FONCTIONNEMENT DU TUNNEL TBM
EXCAVATION AVEC DIFFICULTÉ A CAUSE D´EVENTUELLE USURE DES OUTILS DE COUPE (MOLETTES ET
RIPPERS). PANNE DES GENERATEURS ELECTRIQUES ET LIMITATION DE L´ALIMETATION ELECTRIQUE POUR LE
FONCTIONNEMENT DU TUNNEL TBM
ARRET DE L´ACTIVITÉ EN RAISON DE LA RUPTURE DE LA BANDE DU CONVOYEUR DU BACK UP TBM
EXCAVATION AVEC DIFFICULTÉ A CAUSE D´EVENTUELLE USURE DES OUTILS DE COUPE (MOLETTES ET RIPPERS). PANNE DES
GENERATEURS ELECTRIQUES ET LIMITATION DE L´ALIMETATION ELECTRIQUE
POUR LE FONCTIONNEMENT DU TUNNEL TBM
EXCAVATION AVEC DIFFICULTÉ A CAUSE D´EVENTUELLE USURE DES OUTILS DE COUPE (MOLETTES ET
RIPPERS). PANNE DES GENERATEURS ELECTRIQUES ET LIMITATION DE L´ALIMETATION ELECTRIQUE POUR LE
FONCTIONNEMENT DU TUNNEL TBM
ARRET POUR EFFECTUER UNE INTERVENTION HYPERBARE. CHANGEMENT DE LA BOBINE DU
CONVOYEUR
ARRET POUR EFFECTUER UNE INTERVENTION HYPERBARE. CHANGEMENT DE LA BOBINE DU
CONVOYEUR
INTERVENTION HYPERBARE POUR VERIFIER L´ETAT DE LA TETE DE COUPE
INTERVENTION HYPERBARE POUR VERIFIER L´ETAT DE LA TETE DE COUPE
INTERVENTION HYPERBARE POUR VERIFIER L´ETAT DE LA TETE DE COUPE
INTERVENTION HYPERBARE. CHANGEMENT DES MOLETTES PERIPHERIQUE DE COUPE DE LA TETE DU TUNNELIER,
DESOBSTRUCTION DES BOUCHONS D´ARGILE DANS LES FENETRES DE LA TETE DE COUPE
ET RIPPERS
INTERVENTION HYPERBARE. CHANGEMENT DES MOLETTES PERIPHERIQUE DE COUPE DE LA TETE DU
TUNNELIER, DESOBSTRUCTION DES BOUCHONS D´ARGILE DANS LES FENETRES DE LA TETE DE COUPE ET RIPPERS

INTERVENTION HYPERBARE. CHANGEMENT DES MOLETTES PERIPHERIQUE DE COUPE DE LA TETE DU TUNNELIER,


DESOBSTRUCTION DES BOUCHONS D´ARGILE DANS LES FENETRES DE LA TETE DE COUPE
ET RIPPERS
OPERATION D´ENTRETIEN ET PREPARATOIN DU TUNNELIER POUR REPRENDRE L´EXCAVATION APRÉS
L´INTERVENTION HYPERBARE
EXCAVATION DU TUNNELIER, CHANGEMENT DE 6 MOLETTES PERIPHERIQUE DE COUPE ET NETTOYAGE DES BOUCHONS D
´ARGILE DANS LES FENETRES DE LA TETE DE COUPE ET RIPPERS. SABLE DENSE DE
COULEUR MARRON
EXCAVATION
EXCAVATION
EXCAVATION
EXCAVATION
EXCAVATION
ARRET DE L´ACTIVITÉ POUR UN REPOS
EXCAVATION
EXCAVATION. DEFAILLANCES DANS LES CONDUITES D´INJECTION DU BI-COMPOSANT
EXCAVATION
EXCAVATION
EXCAVATION. PANNE DANS LE CONVOYEUR PENDANT L´EXCAVATION DE L´ANNEAU 1728
EXCAVATION. PANNE TEMPORAIRE DANS LE CONVOYEUR AVEC UN ARRET DE 3 HEURES ET UNE PANNE
DU VEHICULE MULTISERVICE
ARRET DE L´ACTIVITÉ POUR UN REPOS
EXCAVATION
EXCAVATION
EXCAVATION DU MASSIF DE BETON AVEC DES DIFFICULTÉ CONSIDERABLE (PLUS DE 4 HEURES PAR ANNEAU), LA TEMPERATURE
DE LE TETE DE COUPE EST TRÉS ÉLEVÉ ET ENGENDRE DES BOUES FLUIDES DANS L´EXCAVATION AVEC DES DEVERSEMENTS
DU CONVOYEUR TRÉS NOTABLE, CE QUI OBLIGE DES INTERRUPTIONS DE L´EXCAVATION EN RAISON DES TRAVAUX DE
NETTOYAGE.

JONCTION DU TUNNEL PRINCIPAL A LA STATION DE CENTRE DES AFFAIRES


TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION. INSTALLATION DES
DÉRNIERS ANNEAUX DE VOUSSOIRS A L´INTERIEUR DU TUNNEL
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
INCIDENT: ENDOMMAGEMENT DES RAILS DE GLISSEMENT DU TBM, PROFIL METALLIQUE DOUBLÉ AU-
DESSOUS DU BOUCLIER
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES

PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES

PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES


PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
PASSAGE DU TBM A TRAVERS LA STATION CENTRE DES AFFAIRES
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY)
PERIPHERIQUES, 50 RIPPERS FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC
DETECTEUR D´USURE
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY)
PERIPHERIQUES, 50 RIPPERS FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC
DETECTEUR D´USURE

RÉALISATION DU JOINT D´ETANCHEITÉ EXTERIEUR


RÉALISATION DU JOINT D´ETANCHEITÉ EXTERIEUR
DÉFAILLANCE DU JOINT D´ETANCHEITÉ, ARRET TEMPORAIRE POUR RENFORCER LE JOINT
PANNE DANS LE CONVOYEUR HORIZONTAL (TAMBOUR OUED SMAR). PANNE DANS LE CONVOYEUR
VERTICAL EN RAISON DE LA RUPTURE DE LA SOUDURE DE LA BANDE EN CAOUTCHOUC
PANNE DANS LE CONVOYEUR HORIZONTAL (TAMBOUR OUED SMAR). PANNE DANS LE CONVOYEUR
VERTICAL EN RAISON DE LA RUPTURE DE LA SOUDURE DE LA BANDE EN CAOUTCHOUC . ENTAME DES TRAVAUX D´EXCAVATION.

DÉFAILLANCE DANS LA VENTOUSE DE L´ERECTEUR DE VOUSSOIR S. FONCTIONNEMENT IRREGULIER DANS LE CONVOYEUR


HORIZONTAL AVEC DES PROBLEMES DANS LE TAMBOUR D´ENTRAINEMENT DE LA
BANDE EN CAOUTCHOUC A LA STATION D´OUED SMAR
PANNE ELECTROMECANIQUE DANS LE BOOSTER DU CONVOYEUR DE LA STATION DE SMAIL YEFSAH. FONCTIONNEMENT
IRREGULIER DANS LE CONVOYEUR HORIZONTAL AVEC DES PROBLEMES DANS LE
TAMBOUR D´ENTRAINEMENT DE LA BANDE EN CAOUTCHOUC A LA STATION OUED SMAR
PANNE ELECTROMECANIQUE DANS LE BOOSTER DU CONVOYEUR DE LA STATION DE SMAIL YEFSAH. FONCTIONNEMENT
IRREGULIER DANS LE CONVOYEUR HORIZONTAL AVEC DES PROBLEMES DANS LE
TAMBOUR D´ENTRAINEMENT DE LA BANDE EN CAOUTCHOUC A LA STATION OUED SMAR
PANNE ELECTROMECANIQUE DANS LE BOOSTER DU CONVOYEUR DE LA STATION DE SMAIL YEFSAH. FONCTIONNEMENT
IRREGULIER DANS LE CONVOYEUR HORIZONTAL AVEC DES PROBLEMES DANS LE
TAMBOUR D´ENTRAINEMENT DE LA BANDE EN CAOUTCHOUC A LA STATION OUED SMAR
PANNE ELECTROMECANIQUE DANS LE BOOSTER DU CONVOYEUR DE LA STATION DE SMAIL YEFSAH. FONCTIONNEMENT
IRREGULIER DANS LE CONVOYEUR HORIZONTAL AVEC DES PROBLEMES DANS LE
TAMBOUR D´ENTRAINEMENT DE LA BANDE EN CAOUTCHOUC A LA STATION OUED SMAR
PANNE DU CONVOYEUR HORIZONTAL A LA STATION D´OUED SMAR EN RAISON DE PROBLEME D´USURE EXCESIVE DU
RECOUVREMENT DU TAMBOUR DU BOOSTER PRINCIPAL PC-1, SANS ADHERENCE. PROBLEMES DE SYNCHRONISATION DE
COMMUNICATION DANS LE SYSTEME DE CONVOYEUR HORIZONTAL ENTRE BOOSTER PC-1 (OUED SMAR), PC-5 (USTHB), PC-2
(SMAIL YEFSAH), PC-4 (BACK UP TBM).

PANNE DU CONVOYEUR HORIZONTAL A LA STATION D´OUED SMAR EN RAISON DE PROBLEME D´USURE EXCESIVE DU
RECOUVREMENT DU TAMBOUR DU BOOSTER PRINCIPAL PC-1, SANS ADHERENCE. PROBLEMES DE SYNCHRONISATION DE
COMMUNICATION DANS LE SYSTEME DE CONVOYEUR HORIZONTAL ENTRE BOOSTER PC-1 (OUED SMAR), PC-5 (USTHB), PC-2
(SMAIL YEFSAH), PC-4 (BACK UP TBM).

LE TAMBOUR PRINCIPAL D´ENTRAINEMENT DU CONVOYEUR VERTICAL AVEC DES ENDOMMAGEMENTS SEVERES DANS LE
REVETEMENT ET DES PROBLEMES D´ADHERENCE.PANNE DU CONVOYEUR HORIZONTAL A LA STATION D´OUED SMAR EN RAISON
DE PROBLEME D´USURE EXCESIVE DU RECOUVREMENT DU TAMBOUR DU BOOSTER PRINCIPAL PC-1, SANS ADHERENCE.
PROBLEMES DE SYNCHRONISATION DE COMMUNICATION DANS LE SYSTEME DE CONVOYEUR HORIZONTAL ENTRE BOOSTER PC-
1 (OUED SMAR), PC-5 (USTHB), PC-2 (SMAIL YEFSAH), PC-4 (BACK UP TBM).

LE TAMBOUR PRINCIPAL D´ENTRAINEMENT DU CONVOYEUR VERTICAL AVEC DES ENDOMMAGEMENTS SEVERES DANS LE
REVETEMENT ET DES PROBLEMES D´ADHERENCE.PANNE DU CONVOYEUR HORIZONTAL A LA STATION D´OUED SMAR EN RAISON
DE PROBLEME D´USURE EXCESIVE DU RECOUVREMENT DU TAMBOUR DU BOOSTER PRINCIPAL PC-1, SANS ADHERENCE.
PROBLEMES DE SYNCHRONISATION DE COMMUNICATION DANS LE SYSTEME DE CONVOYEUR HORIZONTAL ENTRE BOOSTER PC-
1 (OUED SMAR), PC-5 (USTHB), PC-2 (SMAIL YEFSAH), PC-4 (BACK UP TBM).

LE TAMBOUR D´ENTRAINEMENT PRINCIPAL DU CONVOYEUR VERTICAL AVEC DE SEVERES ENDOMMAGEMENTS DANS LE


REVETEMENT ET DES PROBLEMES D´ADHERENCE. AJUSTEMENT DU
SYSTEME DE CONVOYEUR

REGLAGE DU SYSTEME DE CONVOYEUR. PROBLEMES D´ADHERENCE D´ARGILE, FORMATION DE BLOCS


D´ARGILE COHESIVE, ARRETS IRREGULIER A CAUSE DES PROBLEMES DANS LES TREMIES
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

PANNE DANS LE CONVOYEUR VERTICAL. 3 GODETS CASSÉS.


TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

VENDREDI
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

TAMBOUR DE TRACTION DU CONVOYEUR HORIZONTAL NON 0PERATIONNEL À CAUSE DE L´USURE DE


SON REVETEMENT.
TAMBOUR DE TRACTION DU CONVOYEUR HORIZONTAL NON 0PERATIONNEL À CAUSE DE L´USURE DE
SON REVETEMENT.
TAMBOUR DE TRACTION DU CONVOYEUR HORIZONTAL NON 0PERATIONNEL À CAUSE DE L´USURE DE
SON REVETEMENT.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR À L´INTERIEUR DU
TUNNEL. 350 m DE BANDE TRANSPORTEUSE DÉCHIRÉE.
ARRET DE LA PRODUCTION DANS LE TUNNEL. PROBLÈME DANS LE CONVOYEUR À L´INTERIEUR DU
TUNNEL. 350 m DE BANDE TRANSPORTEUSE DÉCHIRÉE.
DÉFAILLANCE DU TAMBOUR DE TRACTION DU CONVOYEUR VERTICAL, AVEC UN ENDOMMAGEMENT SEVERES DANS LE
REVETEMENT. ARRET TOTAL DE L´ACTIVITÉ. UNE REPARATION PROVISOIRE EST
PREVU AVEC DES PLAQUES SOUDÉES EN CAOUTCHOUC

DÉFAILLANCE DU TAMBOUR DE TRACTION DU CONVOYEUR VERTICAL, AVEC UN ENDOMMAGEMENT


SEVERES DANS LE REVETEMENT. ARRET TOTAL DE L´ACTIVITÉ. UNE REPARATION PROVISOIRE EST PREVU AVEC DES
PLAQUES SOUDÉES EN CAOUTCHOUC

DÉFAILLANCE DU TAMBOUR DE TRACTION DU CONVOYEUR VERTICAL, AVEC UN ENDOMMAGEMENT SEVERES DANS LE


REVETEMENT. ARRET TOTAL DE L´ACTIVITÉ. UNE REPARATION PROVISOIRE EST
PREVU AVEC DES PLAQUES SOUDÉES EN CAOUTCHOUC
DEFAILLANCE DU TAMBOUR DE TRACTION DU CONVOYEUR HORIZONTAL SANS LE REVETEMENT EN
CERAMIQUE. ARRET TOTAL DE L´ACTIVITÉ. DEFAILLANCE A CAUSE DE L´USURE DES ROULEAUX METALLIQUES DU CONVOYEUR
VERTICAL

TRAVAUX D´EXCAVATION AU TBM. REPARATION DU TAMBOUR DU MOTEUR PRINCIPAL DU CONVOYEUR


HORIZONTAL A LA STATION D´OUED SMAR AVEC REVETEMENT EN CERAMIQUE
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY)
PERIPHERIQUES, 50 RIPPERS FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC
DETECTEUR D´USURE. CRUCE BAJO LA VIA DE FERROCARRIL S.N.T.F.
PASSAGE SOUS LES VOIES FERRÉES S.N.T.F ARRET TEMPORAIRE DE L´ACTIVITÉ A CAUSE DES PROBLEMES DE
COMMUNICATION ENTRE LES BOOSTERS DU CONVOYEUR 2,4,5. UN MANQUE DE NOMBRE SUFFISANT DE PACKERS POUR L
´INJECTION SECONDAIRE, RUPTURE ET CHUTE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL AVEC UN ARRET
TOTAL DE L´ACTIVITÉ.

ARRET DE L´ACTIVITÉ A CAUSE DE LA RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE.


TRAVAUX DE REPARATION DU CONVOYEUR VERTICAL. LE TAMBOUR DU MOTEUR DU CONVOYEUR HORIZONTAL AVEC DES
ENDOMMAGEMENTS DANS LE REVETEMENT EN CERAMIQUE

ARRET DE L´ACTIVITÉ A CAUSE DE LA RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE.


TRAVAUX DE REPARATION DU CONVOYEUR VERTICAL. LE TAMBOUR DU MOTEUR DU CONVOYEUR HORIZONTAL AVEC DES
ENDOMMAGEMENTS DANS LE REVETEMENT EN CERAMIQUE

ARRET DE L´ACTIVITÉ A CAUSE DE LA RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE.


TRAVAUX DE REPARATION DU CONVOYEUR VERTICAL. LE TAMBOUR DU MOTEUR DU CONVOYEUR HORIZONTAL AVEC DES
ENDOMMAGEMENTS DANS LE REVETEMENT EN CERAMIQUE

ARRET DE L´ACTIVITÉ A CAUSE DE LA RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE.


TRAVAUX DE REPARATION DU CONVOYEUR VERTICAL. LE TAMBOUR DU MOTEUR DU CONVOYEUR HORIZONTAL AVEC DES
ENDOMMAGEMENTS DANS LE REVETEMENT EN CERAMIQUE

ARRET D´ACTIVITÉ A CAUSE DE LA RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE. TRAVAUX
DE REPARATION DU CONVOYEUR VERTICAL. TRAVAUX DE REPARATION DU TAMBOUR DU MOTEUR DU CONVOYEUR HORIZONTAL
AVEC ENDOMMAGEMENTS DANS LE REVETEMENT EN CERAMIQUE. TRAVAUX DE REPARATION DU CONVOYEUR BY-PASS ENTRE L
´HORIZONTAL ET LE VERTICAL A OUED SMAR AVEC ENDOMMAGEMENTS DANS LES ROULEAUX DES TAMBOURS ET
ENDOMMAGEMENTS DANS LA BANDE EN CAOUTCHOUC.

ARRET D´ACTIVITÉ A CAUSE DE LA RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE. TRAVAUX
DE REPARATION DU CONVOYEUR VERTICAL. TRAVAUX DE REPARATION DU TAMBOUR DU MOTEUR DU CONVOYEUR HORIZONTAL
AVEC ENDOMMAGEMENTS DANS LE REVETEMENT EN CERAMIQUE. TRAVAUX DE REPARATION DU CONVOYEUR BY-PASS ENTRE L
´HORIZONTAL ET LE VERTICAL A OUED SMAR AVEC ENDOMMAGEMENTS DANS LES ROULEAUX DES TAMBOURS ET
ENDOMMAGEMENTS DANS LA BANDE EN CAOUTCHOUC.

ARRET D´ACTIVITÉ A CAUSE DE LA RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE. TRAVAUX
DE REPARATION DU CONVOYEUR VERTICAL. TRAVAUX DE REPARATION DU TAMBOUR DU MOTEUR DU CONVOYEUR HORIZONTAL
AVEC ENDOMMAGEMENTS DANS LE REVETEMENT EN CERAMIQUE. TRAVAUX DE REPARATION DU CONVOYEUR BY-PASS ENTRE L
´HORIZONTAL ET LE VERTICAL A OUED SMAR AVEC ENDOMMAGEMENTS DANS LES ROULEAUX DES TAMBOURS ET
ENDOMMAGEMENTS DANS LA BANDE EN CAOUTCHOUC.

REPARATION DU CONVOYEUR HORIZONTAL, CONVOYEUR BY-PASS ET TAMBOUR EN CERAMIQUE DU CONVOYEUR HORIZONTAL.


REALISATION D´UNE TREMIE AVEC UNE CAPACITÉ DE 3 ANNEAUX D´EXCAVATION, POUR POUVOIR TRAVAILER DANS DES
CONDITIONS D´EXCEPTION A CAUSE DES PROBLEMES DU CONVOYEUR

REPARATION DU CONVOYEUR HORIZONTAL, CONVOYEUR BY-PASS ET TAMBOUR EN CERAMIQUE DU CONVOYEUR HORIZONTAL.


REALISATION D´UNE TREMIE AVEC UNE CAPACITÉ DE 3 ANNEAUX D´EXCAVATION, POUR POUVOIR TRAVAILER DANS DES
CONDITIONS D´EXCEPTION A CAUSE DES PROBLEMES DU CONVOYEUR

REPARATION DU CONVOYEUR HORIZONTAL, CONVOYEUR BY-PASS ET TAMBOUR EN CERAMIQUE DU CONVOYEUR HORIZONTAL.


REALISATION D´UNE TREMIE AVEC UNE CAPACITÉ DE 3 ANNEAUX D´EXCAVATION, POUR POUVOIR TRAVAILER DANS DES
CONDITIONS D´EXCEPTION A CAUSE DES PROBLEMES DU CONVOYEUR

TRAVAUX DE REPARATION DU CONVOYEUR VERTICAL, DIFFICULTE DE MARINAGE DES DEBLAIS PAR MOYENS
MECANIQUES(TREMIE PLAIN), INSTALLATION DE NOUVELLE GRUE SUR CHENILLES
TELESCOPIQUES 200T.

RUPTURE DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR VERTICAL ET SA CHUTE. TRAVAUX DE


REPARATION DU CONVOYEUR VERTICAL. MANQUE D'INJECTION DE BENTONITE POUR LES TROIS ANNEAUX INSTALLES.
INSTALLATION DE NOUVELLE GRUE SUR CHENILLES TELESCOPIQUES 200T.

ARRET D´ACTIVITÉ A CAUSE DE LA DIFFICULTE DE MARINAGE DES DEBLAIS (TREMIE PLAIN) .TRAVAUX DE REPARATION DU
CONVOYEUR VERTICAL, INSTALLATION DE NOUVELLE GRUE SUR CHENILLES
TELESCOPIQUES 200T.
DIFFICULTE D´ACTIVITÉ A CAUSE DE LA DIFFICULTE DE MARINAGE DES DEBLAIS (TREMIE PLAIN)
.TRAVAUX DE REPARATION DU CONVOYEUR VERTICAL, INSTALLATION DE NOUVELLE GRUE SUR CHENILLES
TELESCOPIQUES 200T.PREPARATION DE MONTAGE DE CONVOYEUR VERTICAL.
ARRET D´ACTIVITÉ A CAUSE LA POSE DU TAPIS SUR LE CONVOYEUR VERTICAL
ARRET D´ACTIVITÉ A CAUSE DE LA POSE DU TAPIS SUR LE CONVOYEUR VERTICAL
ARRET D´ACTIVITÉ A CAUSE DE LA POSE DU TAPIS SUR LE CONVOYEUR VERTICAL
ARRET D´ACTIVITÉ A CAUSE DE LA POSE DU TAPIS SUR LE CONVOYEUR VERTICAL.LA NOVELLE GRUE
OPERATIONELLE ET MARINAGE EN COURS
REPRISE DE L´EXCAVATION (27/12/21) APRÈS LA REPARATION DU CONVOYEUR VERTICAL. PAS
D'INJECTION DE BENTONITE ET L'INJECTION SECONDAIRE DE COULIS EN RETARD
PAS D'INJECTION DE BENTONITE ET L'INJECTION SECONDAIRE DE COULIS EN RETARD
PAS D'INJECTION DE BENTONITE ET L'INJECTION SECONDAIRE DE COULIS EN RETARD + CHUTE DE
PRESSION JUSQU’À 0 BAR
ARRET D´ACTIVITÉ A CAUSE DE LA PANNE DE CONVOYEUR LATERALE (TAMBOUR) ET CONVOYEUR BY-
PASS
PAS D'ACTIVITE AU NIVEAU DE TBM (1ERE JANVIER)
ARRET D´ACTIVITÉ A CAUSE DE LA PANNE DE CONVOYEUR LATERALE (TOMBEUR) ET CONVOYEUR BY-
PASS
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY)
PERIPHERIQUES, 50 RIPPERS FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC
DETECTEUR D´USURE

INCIDENT: RUPTURE TRANSVERSAL D´UN JOINT DU TAPIS HORIZONTAL (ENTRE OS ET USTHB).


RÉPARATION AU FROID SUR SITE. ARRÊT 03/01/2021; 23 H À 04/01/2021; 24 H
INCIDENT: DEVIATION DU TAPIS À NIVEAU DU VIRAGE ENTRE RT ET SY ET DEVERSEMENT DES DÉBLAIS.
ARRÊT 05/01/2021;12 H À 05/01/2021;17 H
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY)
PERIPHERIQUES, 50 RIPPERS FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC
DETECTEUR D´USURE

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

VENDREDI
INCIDENT: RUPTURE DU STOCK DE SILICATE. ARRÊT 09/01/2022;9,00 H À 09/01/2022;23,00 H.
INCIDENT: RUPTURE TRANSVERSAL DU TAPIS HORIZONTAL. RÉPARATION AU CHAUD À OUED SMAR.
ARRÊT 10/01/2022;1,00 H À 10/01/2022;24,00 H.
MAINTENANCE DU CONVOYEUR VERTICAL: CHANGEMENT DES QUELQUES ROULEAUX. ARRÊT 11/01/2022;
8,00 H À 11/01/2022; 15,00 H.
INCIDENT: RUPTURE TRANSVERSAL DU TAPIS HORIZONTAL (ENTRE USTHB ET RT). RÉPARATION AU
CHAUD À OUED SMAR. ARRÊT 12/01/2022; 4,00 H À 12/01/2022; 23,00 H.
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

VENDREDI
INCIDENT: RUPTURE TRANSVERSAL DU TAPIS HORIZONTAL (OUED SMAR). RÉPARATION AU CHAUD À
OUED SMAR.
RUPTURE DE LA BANDE HORIZONTAL DU CONVOYEUR ET REPARATION DES JOINTS TRANSVERSAUX. PROBLEMES
ELECTRONIQUES ET D´ACCUMULATION DE DEBLAIS DANS LE CONVOYEUR BY-PASS DE OUED SMAR, AVEC INTERRUPTIONS DE L
´ACTIVITÉ

RUPTURE DU REVETEMENT EN CERAMIQUE DU TAMBOUR D´ENTRAINEMENT PRINCIPAL DU CONVOYEUR HORIZONTAL A OUED


SMAR. ARRET DU TUNNELIER TBM SOUS LA VOIE MENANT A L´AEROPORT

RUPTURE DU REVETEMENT EN CERAMIQUE DU TAMBOUR D´ENTRAINEMENT PRINCIPAL DU CONVOYEUR HORIZONTAL A OUED


SMAR. ARRET DU TUNNELIER TBM SOUS LA VOIE MENANT A L´AEROPORT

RUPTURE DU REVETEMENT EN CERAMIQUE DU TAMBOUR D´ENTRAINEMENT PRINCIPAL DU CONVOYEUR HORIZONTAL A OUED


SMAR. ARRET DU TUNNELIER TBM SOUS LA VOIE MENANT A L´AEROPORT

VENDREDI
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

ARRETS TEMPORAIRES DE L´ACTIVITÉ EN RAISON DE L´ACCUMULATION DE BOUES ET L´OBSTRUCTION DANS LES TREMIES DE
SMAIL YEFSAH ET LES TREMIES DE SORTIE DU CONVOYEUR VERTICAL DE OUED SMAR. PROBLEME DE MANQUE DE STOCK DE
COULIS DE GROUTING DANS LA CENTRAL DE GROUTING DE OUED SMAR

COUPURE ET RUPTURE EN DEUX ZONES DE LA BANDE DE CAOUTCHOUC DU CONVOYEUR HORIZONTAL. LONGUEUR


ENDOMMAGÉE : PLUS DE 1.500 MÈTRES. ARRÊT COMPLET DE L'ACTIVITÉ D'EXCAVATION.

COUPURE ET RUPTURE EN DEUX ZONES DE LA BANDE DE CAOUTCHOUC DU CONVOYEUR HORIZONTAL. LONGUEUR


ENDOMMAGÉE : PLUS DE 1.500 MÈTRES. ARRÊT COMPLET DE L'ACTIVITÉ D'EXCAVATION.

COUPURE ET RUPTURE EN DEUX ZONES DE LA BANDE DE CAOUTCHOUC DU CONVOYEUR HORIZONTAL. LONGUEUR


ENDOMMAGÉE : PLUS DE 1.500 MÈTRES. ARRÊT COMPLET DE L'ACTIVITÉ D'EXCAVATION.

COUPURE ET RUPTURE EN DEUX ZONES DE LA BANDE DE CAOUTCHOUC DU CONVOYEUR HORIZONTAL. LONGUEUR


ENDOMMAGÉE : PLUS DE 1.500 MÈTRES. ARRÊT COMPLET DE L'ACTIVITÉ D'EXCAVATION.

TRAVAUX DE RÉPARATION DE LA BANDE DE CAOUTCHOUC ENDOMMAGÉE DU CONVOYEUR > 1.500 MÈTRES. RÉPARATION DES
JOINTS TRANSVERSAUX ENDOMMAGÉS PAR UNE SURTENSION. RÉPARATION DE LA STRUCTURE MÉTALLIQUE ET DES PLAQUES
DE SUPPORT ENDOMMAGÉES DU CONVOYEUR HORIZONTAL DANS LA ZONE DE LA COURBE DU TRONÇON 7, OÙ LA BANDE DE
CAOUTCHOUC A ÉTÉ DÉCHIRÉE EN RAISON DE PROBLÈMES DE CONCEPTION, D'UN MANQUE D'ENTRETIEN ET D'UN MANQUE
DE VIGILANCE,
TRAVAUX DE RÉPARATION DE LA BANDE DE CAOUTCHOUC ENDOMMAGÉE DU CONVOYEUR > 1.500 MÈTRES. RÉPARATION DES
JOINTS TRANSVERSAUX ENDOMMAGÉS PAR UNE SURTENSION. RÉPARATION DE LA STRUCTURE MÉTALLIQUE ET DES PLAQUES
DE SUPPORT ENDOMMAGÉES DU CONVOYEUR HORIZONTAL DANS LA ZONE DE LA COURBE DU TRONÇON 7, OÙ LA BANDE DE
CAOUTCHOUC A ÉTÉ DÉCHIRÉE EN RAISON DE PROBLÈMES DE CONCEPTION, D'UN MANQUE D'ENTRETIEN ET D'UN MANQUE
DE VIGILANCE,

TRAVAUX DE RÉPARATION DE LA BANDE DE CAOUTCHOUC ENDOMMAGÉE DU CONVOYEUR > 1.500 MÈTRES. RÉPARATION DES
JOINTS TRANSVERSAUX ENDOMMAGÉS PAR UNE SURTENSION. RÉPARATION DE LA STRUCTURE MÉTALLIQUE ET DES PLAQUES
DE SUPPORT ENDOMMAGÉES DU CONVOYEUR HORIZONTAL DANS LA ZONE DE LA COURBE DU TRONÇON 7, OÙ LA BANDE DE
CAOUTCHOUC A ÉTÉ DÉCHIRÉE EN RAISON DE PROBLÈMES DE CONCEPTION, D'UN MANQUE D'ENTRETIEN ET D'UN MANQUE
DE VIGILANCE,

RUPTURE DUE À UNE SURTENSION DU JOINT TRANSVERSAL DE LA BANDE DU CONVOYEUR SITUÉ À LA


HAUTEUR DU TRONÇON 8, ANNEAU 1467. LES TRAVAUX DE RÉPARATION PAR SOUDAGE À CHAUD AVEC UNE PRESSE
VULCANISÉE.

RUPTURE DUE À UNE SURTENSION DU JOINT TRANSVERSAL DE LA BANDE DU CONVOYEUR SITUÉ À LA


HAUTEUR DU TRONÇON 8, ANNEAU 1467. LES TRAVAUX DE RÉPARATION PAR SOUDAGE À CHAUD AVEC UNE PRESSE
VULCANISÉE.

RÉVISION DES JOINTS TRANSVERSAUX DE LA BANDE EN CAOUTCHOUC DU CONVOYEUR HORIZONTAL ET RÉPARATION DE 13


JOINTS PAR SOUDURE À CHAUD AVEC UNE PRESSE À VULCANISER.

REVISION DU SYSTEME DU CONVOYEUR HORIZONTAL ET SYNCHRONISATION DU SYSTEME


REVISION DE LA STRUCTURE DU CONVOYEUR ET DEBUT DES TRAVAUX D´EXCAVATION
ARRET D´ACTIVITÉ POUR REPOS
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. PROBLEMES D
´ACCUMULATION DE BOUES TRES ADHERENTS DANS LES TREMIES DU CONVOYEUR, AVEC DES TRAVAUX DE DESOBSTRUCTION
ET ARRETS TEMPORAIRES DE L´EXCAVATION.

INCIDENT: PANNE DANS LA VENTOUSE DE L´ERECTEUR DE VOUSSOIRS CE QUI ENTRAVE PENDANT PLUSIEURS HEURES L
´INSTALLATION DES ANNEAUX DE VOUSSOIRS. RUPTURE D´UN NOUVEAU JOINT TRANSVERSAL DANS LA BANDE EN
CAOUTCHOUC DU CONVOYEUR HORIZONTAL SITUÉ DANS LE TRONÇON 5, ANNEAU 209; REPARATION SUR PLACE AVEC
SOUDURE À CHAUD AVEC UNE PRESSE À VULCANISER.

RUPTURE D´UN NOUVEAU JOINT TRANSVERSAL DANS LA BANDE EN CAOUTCHOUC DU CONVOYEUR HORIZONTAL SITUÉ DANS LE
TRONÇON 5, ANNEAU 209; REPARATION SUR PLACE AVEC SOUDURE À
CHAUD AVEC UNE PRESSE À VULCANISER.
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS
FRONTAUX AVEC DETECTEUR D´USURE

ARRET D´ACTIVITÉ POUR REPOS


TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL.LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

PANNE DANS LE TAMBOUR DU CONVOYEUR BY-PASS A OUED SMAR 17/02/2022 ( RUPTURE DE L´AXE
METALLIQUE)
ARRET D´ACTIVITÉ POUR REPOS
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

INTERRUPTION TEMPORAIRE DE L´EXCAVATION A CAUSE DU MANQUE DE SILICATE.PANNE DES 2 VEHICULES MULTISERVICES


AVEC INTERRUPTION TEMPORAIRE DE L´EXCAVATION DANS LE TUNNELIER
EN RAISON DU MANQUE D´APPROVISIONNEMENT DES VOUSSOIRES
INTERRUPTION TEMPORAIRE DE L´EXCAVATION A CAUSE DU MANQUE DE SILICATE
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

ARRET D´ACTIVITÉ POUR REPOS


TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.
ARRÊT TECHNIQUE À PARTIR DU 04/03/22 (PRÉVU JUSQU´AU 07/03/22).TRAVAUX À FAIRE:
*DOUBLE BOOSTER À CdA
*RÉVISION ET ENTRETIEN: BROSSES DE LA JUPE, CONVOYEUR VERTICAL, VSM, CÂBLE ELECTRIQUE, PLATEFORMES DE
CROISEMENT À USTHB ET SY.

ARRÊT TECHNIQUE À PARTIR DU 04/03/22 (PRÉVU JUSQU´AU 07/03/22).TRAVAUX À FAIRE:


*DOUBLE BOOSTER À CdA
*RÉVISION ET ENTRETIEN: BROSSES DE LA JUPE, CONVOYEUR VERTICAL, VSM, CÂBLE ELECTRIQUE, PLATEFORMES DE
CROISEMENT À USTHB ET SY.

ARRÊT TECHNIQUE À PARTIR DU 04/03/22 (PRÉVU JUSQU´AU 07/03/22).TRAVAUX À FAIRE:


*DOUBLE BOOSTER À CdA
*RÉVISION ET ENTRETIEN: BROSSES DE LA JUPE, CONVOYEUR VERTICAL, VSM, CÂBLE ELECTRIQUE, PLATEFORMES DE
CROISEMENT À USTHB ET SY.

ARRÊT TECHNIQUE À PARTIR DU 04/03/22 (PRÉVU JUSQU´AU 07/03/22).TRAVAUX À FAIRE:


*DOUBLE BOOSTER À CdA
*RÉVISION ET ENTRETIEN: BROSSES DE LA JUPE, CONVOYEUR VERTICAL, VSM, CÂBLE ELECTRIQUE, PLATEFORMES DE
CROISEMENT À USTHB ET SY.

ARRÊT TECHNIQUE À PARTIR DU 04/03/22 (PRÉVU JUSQU´AU 07/03/22).TRAVAUX À FAIRE:


*DOUBLE BOOSTER À CdA
*RÉVISION ET ENTRETIEN: BROSSES DE LA JUPE, CONVOYEUR VERTICAL, VSM, CÂBLE ELECTRIQUE, PLATEFORMES DE
CROISEMENT À USTHB ET SY.

ARRÊT TECHNIQUE À PARTIR DU 04/03/22 (PRÉVU JUSQU´AU 07/03/22).TRAVAUX À FAIRE:


*DOUBLE BOOSTER À CdA
*RÉVISION ET ENTRETIEN: BROSSES DE LA JUPE, CONVOYEUR VERTICAL, VSM, CÂBLE ELECTRIQUE, PLATEFORMES DE
CROISEMENT À USTHB ET SY.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES,IL INTERROMPT DANS CERTAINES OCCASIONS L´INSTALLATION
DES ANNEAUX DANS LE TUNNEL A CAUSE DU RETARD D´APPROVISIONNEENT DE VOUSSOIRS.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

ARRET DE L´ACTIVITÉ A CAUSE DU MANQUE DE SILICATE POUR L´INJECTION DU BI-COMPOSNT DU GAP


ENTRE LE TERRAIN ET L´ANNEAU DE REVETEMENT
ARRET DE L´ACTIVITÉ A CAUSE DU MANQUE DE SILICATE POUR L´INJECTION DU BI-COMPOSNT DU GAP
ENTRE LE TERRAIN ET L´ANNEAU DE REVETEMENT
ARRET DE L´ACTIVITÉ A CAUSE DU MANQUE DE SILICATE POUR L´INJECTION DU BI-COMPOSNT DU GAP
ENTRE LE TERRAIN ET L´ANNEAU DE REVETEMENT
ARRET DE L´ACTIVITÉ A CAUSE DU MANQUE DE SILICATE POUR L´INJECTION DU BI-COMPOSNT DU GAP
ENTRE LE TERRAIN ET L´ANNEAU DE REVETEMENT
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. LIMITATIONS DE L´EFFICACITÉ DU CYCLE DE TRAVAIL A CAUSE DE PANNES PRONLONGÉES DE
PLUSIEURS SEMAINES DE L´UN DES VEHICULE MULTISERVICES.DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE
DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

ARRET D´ACTIVITÉ POUR REPOS


TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT
D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER. PREMIER ANNEAU DE 1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. DEFAILLANCE DU JOINT D´ETANCHEITÉ DU BOUCLIER DE LA JUPE DU TUNNELIER.

ARRÊT TECHNIQUE À PARTIR DU 07/04/22 (PRÉVU JUSQU´AU 12/04/22).TRAVAUX À FAIRE:


*PRINCIPAL: RÉVISION + EVENTUELLE SUBSTITUTION DES 3 LIGNES INTERIEURES DE BROSSES DU BOUCLIER
*AUTRES: MAINTENANCE SYSTEME CONVOYEUR, NETTOYAGE DU TUNNEL.

ARRÊT TECHNIQUE À PARTIR DU 07/04/22 (PRÉVU JUSQU´AU 12/04/22).TRAVAUX À FAIRE:


*PRINCIPAL: RÉVISION + EVENTUELLE SUBSTITUTION DES 3 LIGNES INTERIEURES DE BROSSES DU BOUCLIER
*AUTRES: MAINTENANCE SYSTEME CONVOYEUR, NETTOYAGE DU TUNNEL.

ARRÊT TECHNIQUE À PARTIR DU 07/04/22 (PRÉVU JUSQU´AU 12/04/22).TRAVAUX À FAIRE:


*PRINCIPAL: RÉVISION + EVENTUELLE SUBSTITUTION DES 3 LIGNES INTERIEURES DE BROSSES DU BOUCLIER
*AUTRES: MAINTENANCE SYSTEME CONVOYEUR, NETTOYAGE DU TUNNEL.
ARRÊT TECHNIQUE À PARTIR DU 07/04/22 (PRÉVU JUSQU´AU 12/04/22).TRAVAUX À FAIRE:
*PRINCIPAL: RÉVISION + EVENTUELLE SUBSTITUTION DES 3 LIGNES INTERIEURES DE BROSSES DU BOUCLIER
*AUTRES: MAINTENANCE SYSTEME CONVOYEUR, NETTOYAGE DU TUNNEL.

ARRÊT TECHNIQUE À PARTIR DU 07/04/22 (PRÉVU JUSQU´AU 12/04/22).TRAVAUX À FAIRE:


*PRINCIPAL: RÉVISION + EVENTUELLE SUBSTITUTION DES 3 LIGNES INTERIEURES DE BROSSES DU BOUCLIER
*AUTRES: MAINTENANCE SYSTEME CONVOYEUR, NETTOYAGE DU TUNNEL.

ARRÊT TECHNIQUE À PARTIR DU 07/04/22 (PRÉVU JUSQU´AU 12/04/22).TRAVAUX À FAIRE:


*PRINCIPAL: RÉVISION + EVENTUELLE SUBSTITUTION DES 3 LIGNES INTERIEURES DE BROSSES DU BOUCLIER
*AUTRES: MAINTENANCE SYSTEME CONVOYEUR, NETTOYAGE DU TUNNEL.

ARRÊT TECHNIQUE À PARTIR DU 07/04/22 (PRÉVU JUSQU´AU 12/04/22).TRAVAUX À FAIRE:


*PRINCIPAL: RÉVISION + EVENTUELLE SUBSTITUTION DES 3 LIGNES INTERIEURES DE BROSSES DU BOUCLIER
*AUTRES: MAINTENANCE SYSTEME CONVOYEUR, NETTOYAGE DU TUNNEL.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

PANNE DANS LA VENTOUSE DE L´ERECTEUR DE VOUSSOIRS, CE QUI LIMITE LA PRODUCTION.


TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

ARRET POUR EXTENSION DE LA BANDE DU CONVOYEUR


TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE 1,40 m = 2345. PRODUCTION FAIBLE À CAUSE DE LA DÉVIATION DE LA BANDE DU
CONVOYEUR PLACÉ
DANS LE BACK-UP DU TBM

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE 1,40 m = 2345. PRODUCTION FAIBLE POUR LE BLOCAGE DES VMS À CAUSE DU
NIVEAU D´EAU DANS LE
TUNNEL

JOUR FERIÉ. AID EL FITR 2022


JOUR FERIÉ. AID EL FITR 2022
JOUR FERIÉ. AID EL FITR 2022
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE 1,40 m = 2345. PRODUCTION FAIBLE POUR LA DETERIORATION DU CONVOYEUR
BY-PASS (OUED SMAR)

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345.

TBM À L´ARRÊT Á CAUSE DU CONVOYEUR BY-PASS (OUED SMAR)


ARRET A CAUSE D´UNE PANNE DANS LE CONVOYEUR VERTICAL ,TRÉS DEGRADÉ
ARRET A CAUSE D´UNE PANNE DANS LE CONVOYEUR VERTICAL ,TRÉS DEGRADÉ
PANNE DANS LE CONVOYEUR DU BACK UP DU TUNNELIER, AVEC DES PROBLÉMES DE SURTENSION ET
DE NIVELLEMENT
TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,40 m = 2345.

TRAVAUX D´EXCAVATION AVEC DES ARRETS TEMPORAIRES A CAUSE DES PROBLEMES DANS LE CONVOYEUR VERTICAL OU
DES PROBLÉMES DANS LA BANDE EN CAOUTCHOUC DU BACK UP DU TBM

TRAVAUX D´EXCAVATION AVEC DES ARRETS TEMPORAIRES A CAUSE DES PROBLEMES DANS LE CONVOYEUR VERTICAL OU
DES PROBLÉMES DANS LA BANDE EN CAOUTCHOUC DU BACK UP DU TBM

TRAVAUX D´EXCAVATION AVEC DES ARRETS TEMPORAIRES A CAUSE DES PROBLEMES DANS LE CONVOYEUR VERTICAL OU
DES PROBLÉMES DANS LA BANDE EN CAOUTCHOUC DU BACK UP DU TBM

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,80 m = 2542.

TRAVAUX D´EXCAVATION AVEC UNE NOUVELLE TETE DE COUPE: 6 MOLETTES HD (HIGH DENSITY) PERIPHERIQUES, 50 RIPPERS
FRONTAUX SIMPLES, 6 MOLETTES CENTRALES DOUBLES, 12 SCRAPERS FRONTAUX AVEC DETECTEUR D´USURE. REPARACION
CONVOYEUR VERTICAL. PREMIER ANNEAU DE
1,80 m = 2542.

PANNE SERIEUSE DANS LE CONVOYEUR VERTICAL , AVEC ENDOMMAGEMENT TRÉS SIGNIFICATIF DANS LE BANDE EN
CAOUTCHOUC ET LA STRUCTURE METALLIQUE. NON OPERATIONNEL. HORS SERVICE.

PANNE SERIEUSE DANS LE CONVOYEUR VERTICAL , AVEC ENDOMMAGEMENT TRÉS SIGNIFICATIF DANS LE BANDE EN
CAOUTCHOUC ET LA STRUCTURE METALLIQUE. NON OPERATIONNEL. HORS SERVICE.

ON ET RETOURNEMENT DE LA BANDE DU CONVOYEUR HORIZONTAL A LA SORTIE DU TBM. PANNE DU CON


PANNE DANS LE CONVOYEUR BY-PASS DE OUED SMAR
EXCAVATION DANS LE BLOC EN BÉTON A L´ENTRÉE DE LA STATION AÉROPORT
JONCTION DU TUNNEL PRINCIPAL A LA STATION AÉROPORT
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DU MASSIF DE BÉTON DE L´ENTRÉE DE LA STATION.
TRAVAUX DE DEMOLITION DES ANNEAUX EXTERIEURS (USTHB, RABIA TAHAR, SMAIL YEFSAH). LA DEMOLITION DES ANNEAUX
EXTERIEURS DES STATIONS OBLIGE LA COUPURE DES INSTALLATIONS ELECTRIQUES ET LES SYSTEMES AUXILIAIRES DU TBM ET
EMPECHE LA PROGRESSION DU TUNNELIER A TRAVERS DE LA STATION AEROPORT

TRAVAUX DE DEMOLITION DES ANNEAUX EXTERIEURS (USTHB, RABIA TAHAR, SMAIL YEFSAH). LA DEMOLITION DES ANNEAUX
EXTERIEURS DES STATIONS OBLIGE LA COUPURE DES INSTALLATIONS ELECTRIQUES ET LES SYSTEMES AUXILIAIRES DU TBM ET
EMPECHE LA PROGRESSION DU TUNNELIER A TRAVERS DE LA STATION AEROPORT

TRAVAUX DE DEMOLITION DES ANNEAUX EXTERIEURS (USTHB, RABIA TAHAR, SMAIL YEFSAH). LA DEMOLITION DES ANNEAUX
EXTERIEURS DES STATIONS OBLIGE LA COUPURE DES INSTALLATIONS ELECTRIQUES ET LES SYSTEMES AUXILIAIRES DU TBM ET
EMPECHE LA PROGRESSION DU TUNNELIER A TRAVERS DE LA STATION AEROPORT

TRAVAUX DE DEMOLITION DES ANNEAUX EXTERIEURS (USTHB, RABIA TAHAR, SMAIL YEFSAH). LA DEMOLITION DES ANNEAUX
EXTERIEURS DES STATIONS OBLIGE LA COUPURE DES INSTALLATIONS ELECTRIQUES ET LES SYSTEMES AUXILIAIRES DU TBM ET
EMPECHE LA PROGRESSION DU TUNNELIER A TRAVERS DE LA STATION AEROPORT

TRAVAUX DE DEMOLITION DES ANNEAUX EXTERIEURS (USTHB, RABIA TAHAR, SMAIL YEFSAH). LA DEMOLITION DES ANNEAUX
EXTERIEURS DES STATIONS OBLIGE LA COUPURE DES INSTALLATIONS ELECTRIQUES ET LES SYSTEMES AUXILIAIRES DU TBM ET
EMPECHE LA PROGRESSION DU TUNNELIER A TRAVERS DE LA STATION AEROPORT

TRAVAUX DE DEMOLITION DES ANNEAUX EXTERIEURS (USTHB, RABIA TAHAR, SMAIL YEFSAH). LA DEMOLITION DES ANNEAUX
EXTERIEURS DES STATIONS OBLIGE LA COUPURE DES INSTALLATIONS ELECTRIQUES ET LES SYSTEMES AUXILIAIRES DU TBM ET
EMPECHE LA PROGRESSION DU TUNNELIER A TRAVERS DE LA STATION AEROPORT
TRAVAUX DE DEMOLITION DES ANNEAUX EXTERIEURS (USTHB, RABIA TAHAR, SMAIL YEFSAH). LA DEMOLITION DES ANNEAUX
EXTERIEURS DES STATIONS OBLIGE LA COUPURE DES INSTALLATIONS ELECTRIQUES ET LES SYSTEMES AUXILIAIRES DU TBM ET
EMPECHE LA PROGRESSION DU TUNNELIER A TRAVERS DE LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT. L´AVANCEMENT DU TBM EST PARALISÉ A LA STATION A CAUSE DU
MANQUE DE SILICATE POUR LE REMPLISSAGE DE LA BASE DES VOUSSOIRS DE
POUSSÉE
PASSAGE DU TBM A TRAVERS LA STATION AEROPORT. L´AVANCEMENT DU TBM EST PARALISÉ A LA STATION A CAUSE DU
MANQUE DE SILICATE POUR LE REMPLISSAGE DE LA BASE DES VOUSSOIRS DE
POUSSÉE
PASSAGE DU TBM A TRAVERS LA STATION AEROPORT. L´AVANCEMENT DU TBM EST PARALISÉ A LA STATION A CAUSE DU
MANQUE DE SILICATE POUR LE REMPLISSAGE DE LA BASE DES VOUSSOIRS DE
POUSSÉE
T38
15-Jun-2022

T38
16-Jun-2022

17-Jun-2022 T39, T40, T41, T42, T43, T44, T45, T46, T47, T48
18-Jun-2022 T49, T50, T51, T52, T53, T54, T55, T56, T57, T58
19-Jun-2022 T59, T60, T61, T62, T63, T64, T65, T66, T67
20-Jun-2022 T67
21-Jun-2022 T67
22-Jun-2022 T67
23-Jun-2022 T68
24-Jun-2022 T68
25-Jun-2022 T68 9,003.500 3

26-Jun-2022 1 EXT, 2 EXT 9,003.589 3


27-Jun-2022 3 EXT, 4 EXT, 5 EXT 9,008.389 3
28-Jun-2022 6 EXT, 7 EXT, 8 EXT 9,012.654 3
29-Jun-2022 8 EXT 9,012.654 3
30-Jun-2022 2573 9,015.266 3

01-Jul-2022 2573 9,015.266 3

02-Jul-2022 2574, 2575, 2576, 2577, 2578, 2579 9,026.066 3


03-Jul-2022 2580, 2581, 2582, 2583, 2584, 2585, 2586 9,038.280 3
04-Jul-2022 2587, 2588, 2589, 2590, 2591, 2592, 2593 9,050.155 4

05-Jul-2022 2594, 2595, 2596, 2597, 2598, 2599, 2600 9,062.753 4

06-Jul-2022 2601, 2602 9,066.340 4

07-Jul-2022 2603, 2604, 2605, 2606, 2607, 2608 9,077.160 4


08-Jul-2022 2609 9,079.561 4

09-Jul-2022 2609 9,079.561 3

10-Jul-2022 2609 9,079.561 3

11-Jul-2022 2609 9,079.561 3

12-Jul-2022 2610, 2611, 2612 9,084.460 4

13-Jul-2022 2613 9,086.260 4

14-Jul-2022 2613 9,087.810 4

15-Jul-2022 2614, 2615, 2616, 2617, 2617, 2618, 2619, 2620, 2621 9,104.010 4
16-Jul-2022 2622, 2623, 2624, 2625, 2626, 2627, 2628, 2629 9,115.454 4
17-Jul-2022 2630, 2631, 2632, 2633, 2634, 2635, 2636 9,127.704 4
18-Jul-2022 2637, 2638, 2639, 2640, 2641, 2642, 2643 9,142.061 4
19-Jul-2022 2644, 2645, 2646, 2647, 2648, 2649, 2650, 2651, 2652 9,156.533 4
20-Jul-2022 2653 9,160.107 4

21-Jul-2022 2654, 2655, 2656, 2657, 2658, 2659, 2660, 2661, 2662, 2663 9,178.165 4
22-Jul-2022 2664, 2665, 2666, 2667, 2668, 2669 9,188.965 4

23-Jul-2022 2670, 2671, 2672, 2673, 2674, 2675, 2676 9,201.625 4


24-Jul-2022 2677, 2678, 2679 9,205.201 4
25-Jul-2022 2680, 2681, 2682, 2683, 2684, 2685, 2686, 2687, 2688 9,221.418 4
26-Jul-2022 2688, 2690 9,225.012 4
27-Jul-2022 2691, 2692, 2693, 2694, 2695, 2696 9,235.805 4
28-Jul-2022 2697, 2698, 2699, 2700, 2701 , 2702, 2703 9,248.453 4
29-Jul-2022 2704, 2705, 2706, 2707, 2708, 2709, 2710 9,261.053 4
30-Jul-2022 2711, 2712, 2713, 2714, 2715, 2716, 2717 9,274.110 4
31-Jul-2022 2717 9,274.110 4

01-Aug-2022 2717 9,274.110 4

02-Aug-2022 2718, 2719 9,277.290 4

03-Aug-2022 2720 9,279.117 4


04-Aug-2022 2720 9,279.117 4
05-Aug-2022 2720 9,279.117 4
06-Aug-2022 2720 9,279.117 4
07-Aug-2022 2720 9,279.117 4

08-Aug-2022 2720 9,279.117 4

09-Aug-2022 2720 9,280.873 4

10-Aug-2022 2721, 2722 9,282.750 4

11-Aug-2022 2723, 2724, 2725, 2726, 2727 9,291.721 4


12-Aug-2022 2728, 2729, 2730, 2731, 2732, 2733 9,302.521 4
13-Aug-2022 2734, 2735, 2736, 2737, 2738, 2739, 2740, 2741 9,316.921 4
14-Aug-2022 2742, 2743, 2744, 2745 9,324.175 4
15-Aug-2022 2746, 2747, 2748, 2749 9,332.568 4
16-Aug-2022 2750, 2751, 2752, 2753 9,338.639 4

17-Aug-2022 2753 9,338.639 4

18-Aug-2022 2753 9,340.491 4

19-Aug-2022 2754, 2755, 2756 9,344.500 4


20-Aug-2022 2757, 2758, 2759, 2760, 2761 9,353.020 4
21-Aug-2022 2762, 2763, 2764, 2765, 2766, 2767 9,363.860 4
22-Aug-2022 2768, 2769, 2770, 2771, 2772, 2773, 2774, 2775, 2776 9,380.093 4
23-Aug-2022 2777, 2778, 2779 9,387.054 4
24-Aug-2022 2780, 2781 9,389.090 4

25-Aug-2022 2782, 2783, 2784, 2785, 2786 9,398.107 4


26-Aug-2022 2787, 2788, 2789, 2790, 2791, 2792, 2793 9,410.707 4
27-Aug-2022 2794, 2795, 2796, 2797, 2798, 2799, 2800 9,423.800 4
28-Aug-2022 2801, 2802, 2803, 2804, 2805, 2806, 2807, 2808 9,437.796 4
29-Aug-2022 2808 9,438.442 4

30-Aug-2022 2809, 2810, 2811 9,444.287 4

31-Aug-2022 2812, 2813, 2814, 2815, 2816, 2817, 2818 9,457.560 4


01-Sep-2022 2819, 2820, 2821, 2822, 2823, 2824, 2825, 2826, 2827, 2828 9,475.699 4
02-Sep-2022 2829, 2830, 2831, 2832, 2833, 2834, 2835 9,486.599 4
03-Sep-2022 2836, 2837, 2838, 2839, 2840, 2841, 2842, 2843, 2844 9,502.769 4
04-Sep-2022 2845, 2846, 2847, 2848, 2849, 2850, 2851, 2852 9,517.195 4
05-Sep-2022 2853, 2854, 2855, 2856, 2857, 2858, 2859, 2860, 2861 9,533.450 4

06-Sep-2022 2862, 2863, 2864 9,538.842 4

07-Sep-2022 2865, 2866 9,544.072 4

08-Sep-2022 2867, 2868, 2869 9,548.033 4

09-Sep-2022 2869 9,548.033 4


10-Sep-2022 2869 9,548.033 4
11-Sep-2022 2869 9,548.033 4

12-Sep-2022 2870, 2871, 2872 9,553.433 4

13-Sep-2022 2872 9,553.433 4

14-Sep-2022 2872 9,553.433 4

15-Sep-2022 2872 9,553.433 4

16-Sep-2022 2872 9,553.433 4

17-Sep-2022 2872 9,553.433 4

18-Sep-2022 2872 9,553.433 4

19-Sep-2022 2872 9,553.433 4

20-Sep-2022 2872 9,553.433 4

21-Sep-2022 2872 9,553.433 4

22-Sep-2022 2872 9,553.433 4

23-Sep-2022 2873, 2874 9,557.033 4

24-Sep-2022 T1, T2, T3

25-Sep-2022 T3

26-Sep-2022 T3

27-Sep-2022 T3

28-Sep-2022 T4, T5

29-Sep-2022 T4, T5

30-Sep-2022 T4, T5

01-Oct-2022 T4, T5

02-Oct-2022 T4, T5
03-Oct-2022 T4, T5

04-Oct-2022 T4, T5
0.000 0

0.089 0.089 8,995.089 0


4.800 4.889 8,999.889 0
4.265 9.154 9,004.154 0
0.000 9.154 9,004.154 0
2.612 11.766 9,006.766 0

0.000 11.766 9,006.766 0

10.800 22.566 9,017.566 6


12.214 34.780 9,029.780 7
11.875 46.655 9,041.655 7

12.598 59.253 9,054.253 7

3.587 62.840 9,057.840 2

10.820 73.660 9,068.660 6


2.401 76.061 9,071.061 1

0.000 76.061 9,071.061 0

0.000 76.061 9,071.061 0

0.000 76.061 9,071.061 0

4.899 80.960 9,075.960 3

1.800 82.760 9,077.760 1

1.550 84.310 9,079.310 0

16.200 100.510 9,095.510 9


11.444 111.954 9,106.954 8
12.250 124.204 9,119.204 7
14.357 138.561 9,133.561 7
14.472 153.033 9,148.033 9
3.574 156.607 9,151.607 1

18.058 174.665 9,169.665 10


10.800 185.465 9,180.465 6

12.660 198.125 9,193.125 7


3.576 201.701 9,196.701 3
16.217 217.918 9,212.918 9
3.594 221.512 9,216.512 2
10.793 232.305 9,227.305 6
12.648 244.953 9,239.953 7
12.600 257.553 9,252.553 7
13.057 270.610 9,265.610 7
0.000 270.610 9,265.610 0

0.000 270.610 9,265.610 0

3.180 273.790 9,268.790 2

1.827 275.617 9,270.617 1


0.000 275.617 9,270.617 0
0.000 275.617 9,270.617 0
0.000 275.617 9,270.617 0
0.000 275.617 9,270.617 0

0.000 275.617 9,270.617 0

1.756 277.373 9,272.373 0

1.877 279.250 9,274.250 2

8.971 288.221 9,283.221 5


10.800 299.021 9,294.021 6
14.400 313.421 9,308.421 8
7.254 320.675 9,315.675 4
8.393 329.068 9,324.068 4
6.071 335.139 9,330.139 4

0.000 335.139 9,330.139 0

1.852 336.991 9,331.991 1

4.009 341.000 9,336.000 3


8.520 349.520 9,344.520 5
10.840 360.360 9,355.360 6
16.233 376.593 9,371.593 9
6.961 383.554 9,378.554 3
2.036 385.590 9,380.590 2

9.017 394.607 9,389.607 5


12.600 407.207 9,402.207 7
13.093 420.300 9,415.300 7
13.996 434.296 9,429.296 8
0.646 434.942 9,429.942 0

5.845 440.787 9,435.787 3

13.273 454.060 9,449.060 7


18.139 472.199 9,467.199 10
10.900 483.099 9,478.099 6
16.170 499.269 9,494.269 9
14.426 513.695 9,508.695 8
16.255 529.950 9,524.950 9

5.392 535.342 9,530.342 3

5.230 540.572 9,535.572 2

3.961 544.533 9,539.533 3

0.000 544.533 9,539.533 0


0.000 544.533 9,539.533 0
0.000 544.533 9,539.533 0

5.400 549.933 9,544.933 3

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

0.000 549.933 9,544.933 0

3.600 553.533 9,548.533 2


PASSAGE DU TBM A TRAVERS LA STATION AEROPORT. L´AVANCEMENT DU TBM EST PARALISÉ A LA STATION A CAUSE DU
MANQUE DE SILICATE POUR LE REMPLISSAGE DE LA BASE DES VOUSSOIRS DE
POUSSÉE
PASSAGE DU TBM A TRAVERS LA STATION AEROPORT. L´AVANCEMENT DU TBM EST PARALISÉ A LA
STATION A CAUSE DU MANQUE DE SILICATE POUR LE REMPLISSAGE DE LA BASE DES VOUSSOIRS DE POUSSÉE

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

PASSAGE DU TBM A TRAVERS LA STATION AEROPORT

TRAVAUX D´EXCAVATION DANS LE TUNNEL

TRAVAUX D´EXCAVATION DANS LE TUNNEL


TRAVAUX D´EXCAVATION DANS LE TUNNEL
TRAVAUX D´EXCAVATION DANS LE TUNNEL
TRAVAUX D´EXCAVATION DANS LE TUNNEL
INCIDENT: RUPTURE DE L´UN DES BOGIES DU TUNNELIER, A CAUSE DES PROBLÉMES D´APPUI DANS LES
VOUSSOIRS EN BÉTON (DESAJUSTEMENT GEOMETRIQUE, MANQUE D´ALLIGNEMENT)
INCIDENT: RUPTURE DE L´UN DES BOGIES DU TUNNELIER, A CAUSE DES PROBLÉMES D´APPUI DANS LES
VOUSSOIRS EN BÉTON (DESAJUSTEMENT GEOMETRIQUE, MANQUE D´ALLIGNEMENT)
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
INTÉRFERANCE DES TRAVAUX: ARRET D´EXCAVATION DU TBM POUR EXTRAIRE ET DEMONTER LA
STRUCTURE METALLIQUE DU CONVOYEUR VERTICAL AVEC DES GRUES LOURDES A LA STATION DE OUED SMAR

INTÉRFERANCE DES TRAVAUX: ARRET D´EXCAVATION DU TBM POUR EXTRAIRE ET DEMONTER LA STRUCTURE METALLIQUE DU
CONVOYEUR VERTICAL AVEC DES GRUES LOURDES A LA STATION DE OUED SMAR. ENDOMMGEMENTS DE 6 ROULEAUX DU
CONVOYEUR HORIZONTAL A LA STATION DU CENTRE DES AFFAIRES AVEC UN ARRET TEMPORAIRE DE L´EXCAVATION.

TRAVAUX D´EXCAVATION
UN MANQUE D´EQUIPE COMPLETS POUR LES TRAVAUX AFIN DE METTRE EN SERVICE LE TUNNELIER. PRESENCE DANS LE
TUNNEL DE L´OPERATEUR DU TBM, L´OPERATEUR DE L´ERECTEUR DE VOUSSOIRS, OPERATEURS GROUTING, 1 SPECIALISTE
ELECTRONIQUE, 1 SPECIALISTE MECANIQUE-HYDRAULIQUE

UN MANQUE D´EQUIPE COMPLETS POUR LES TRAVAUX AFIN DE METTRE EN SERVICE LE TUNNELIER. PRESENCE DANS LE
TUNNEL DE L´OPERATEUR DU TBM, L´OPERATEUR DE L´ERECTEUR DE VOUSSOIRS, OPERATEURS GROUTING, 1 SPECIALISTE
ELECTRONIQUE, 1 SPECIALISTE MECANIQUE-HYDRAULIQUE

UN MANQUE D´EQUIPE COMPLETS POUR LES TRAVAUX AFIN DE METTRE EN SERVICE LE TUNNELIER. PRESENCE DANS LE
TUNNEL DE L´OPERATEUR DU TBM, L´OPERATEUR DE L´ERECTEUR DE VOUSSOIRS, OPERATEURS GROUTING, 1 SPECIALISTE
ELECTRONIQUE, 1 SPECIALISTE MECANIQUE-HYDRAULIQUE

DES DIFFICULTÉS AVEC UNE PARTIE DU STAF DES OUVRIERS, QUI NE PERMET PAS DE REALISER LES
TRAVAUX DE PRODUCTION DNS LE TUNNELIER
PANNE DANS LA GRUE D´EXTRACATION DES DEBLAIS A OUED SMAR, AVEC UN ARRET TEMPORAIRE DE L´EXCAVATION DU TBM,
SUITE AU REMPLISSAGE DU BASSIN DE BOUE A LA STATION D´OUED SMAR

PANNE DANS LA GRUE D´EXTRACATION DES DEBLAIS A OUED SMAR. TRAVAUX A L´ARRETS
COLISION DE LA BENNE PRENEUSE CONTRE LE CONVOYEUR BY-PASS A L´INTERIEUR DE OUED SMAR; ENDOMMAGEMENT DE LA
STRUCTURE METALLIQUE DU CONVOYEUR. EXCAVATION A L´ARRET AU TBM.
TRAVAUX DE REPARATION DU BY-PASS
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
ARRET A CAUSE DU MANQUE DE SILICATE. ENDOMMAGEMENTS DANS LE TAMBOUR D´ENTRAINEMENT DU CONVOYEUR BY-PASS
A OUED SMAR A CAUSE DE LA COLISION CONTRE LA BENNE PRENEUSE (ENDOMMGEMENT DE L´AXE). INTERFÉRENCE DES
TRAVAUX A RABIA TAHAR, AVEC UN CHANGEMENT DE 100 m DE TUBE DE VENTILLATION SEVEREMENT ENDOMMAGÉ.

TRAVAUX D´EXCAVATION
CHUTE DE BLOC DE DEBLAIS DE LA GRUE ET UN IMPACT SE PRODUIT CONTRE LE CONVOYEUR
HORIZONTAL. ENDOMMAGEMENT DANS LA STRUCTURE METALLIQUE ET DES ROULEAUX.
TRAVAUX D´EXCAVATION
EXTENSION DU TAPIS DU CONVOYEUR
TRAVAUX D´EXCAVATION
ARRET A CAUSE DU MANQUE DE FOURNISSEMENT DU SILICATE
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXTENSION DU TAPIS DE CONVOYEUR HORIZONTAL A OUED SMAR, REMPLACEMENT DE
TRONÇON DU TAPIS DETERIORÉ
TRAVAUX A L´ARRET DANS LE TBM EN RAISON DE PANNE DANS LA LIGNE ELECTRIQUE DE MOYENNE TENSION ET DU MANQUE
D´ALIMENTATION EN ELECTRICITÉ
TRAVAUX A L´ARRET DANS LE TBM EN RAISON DE PANNE DANS LA LIGNE ELECTRIQUE DE MOYENNE
TENSION ET DU MANQUE D´ALIMENTATION EN ELECTRICITÉ
TRAVAUX A L´ARRET DANS LE TBM À CAUSE DE LA PANNE DE LA GRUE DE MARINAGE (200 t)
TRAVAUX A L´ARRET DANS LE TBM À CAUSE DE LA PANNE DE LA GRUE DE MARINAGE (200 t)
TRAVAUX A L´ARRET DANS LE TBM À CAUSE DE LA PANNE DE LA GRUE DE MARINAGE (200 t)
TRAVAUX A L´ARRET DANS LE TBM À CAUSE DE LA PANNE DE LA GRUE DE MARINAGE (200 t)
TRAVAUX A L´ARRET DANS LE TBM À CAUSE DE LA PANNE DE LA GRUE DE MARINAGE (200 t)
TRAVAUX A L´ARRET DANS LE TBM À CAUSE DE LA PANNE DE LA GRUE DE MARINAGE (200 t). MISE EN
OEUVRE D´UNE GRUE DE 160 t POUR LA REMPLACER EN ATTEINTE DE L´ARRIVAGE D´UNE NOUVELLE POMPE DE GAS OIL.

MISE EN OEUVRE D´UNE GRUE DE 160 t POUR REMPLACER DE MANIERE PROVISOIRE LA GRUE DE 200 t. EN ATTEINTE DE L
´ARRIVAGE D´UNE NOUVELLE POMPE DE GAS OIL. RÉVISION DE LA GRUE DE 160 T EN
COURS. RENDEMENT FAIBLE
MISE EN OEUVRE D´UNE GRUE DE 160 t POUR REMPLACER DE MANIERE PROVISOIRE LA GRUE DE 200 t. EN ATTEINTE DE L
´ARRIVAGE D´UNE NOUVELLE POMPE DE GAS OIL. RÉVISION DE LA GRUE DE 160 T EN COURS. RENDEMENT FAIBLE

TRAVAUX D´EXCAVATION. EXTRACTION DES DÉBLAIS AVEC LA GRUE 160 t


TRAVAUX D´EXCAVATION. EXTRACTION DES DÉBLAIS AVEC LA GRUE 160 t
TRAVAUX D´EXCAVATION. EXTRACTION DES DÉBLAIS AVEC LA GRUE 160 t
TRAVAUX D´EXCAVATION. EXTRACTION DES DÉBLAIS AVEC LA GRUE 160 t
TRAVAUX D´EXCAVATION. EXTRACTION DES DÉBLAIS AVEC LA GRUE 160 t
TRAVAUX D´EXCAVATION. EXTRACTION DES DÉBLAIS AVEC LA GRUE 160 t
TRAVAUX A L´ARRET. DECHIRURE LONGITUDINALE DE 150 m DE TAPIS. SUBSTITUTION DU TRONÇON
ENDOMMAGÉ. 2 JOINTS À CHAUD, 1 JOINT EN MAUVAIS ETAT REPARÉE. REPARATION DU TAPIS BY-PASS DU BACK-UP

TRAVAUX A L´ARRET. DECHIRURE LONGITUDINALE DE 150 m DE TAPIS. SUBSTITUTION DU TRONÇON ENDOMMAGÉ. 2 JOINTS À
CHAUD, 1 JOINT EN MAUVAIS ETAT REPARÉE. REPARATION DU TAPIS BY-PASS
DU BACK-UP. GRUE 200 t REPARÉE.
EXTRACTION DES DÉBLAIS AVEC LA GRUE 200 t
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
CHANGEMENT DU MOTEUR (BOOSTER) DE TAPIS DU TUNNEL DANS LE TBM
RUPTURE TRANSVERSAL DU TAPIS à CÔTÉ DU OUED SMAR (PAR LA BANDE, NON PAR LA JONCTION
(23/08/22; ARRÊT 21 H)
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
RUPTURE TRANSVERSAL DU TAPIS à CÔTÉ DU OUED SMAR. DERNIER MORCEAU DE TAPIS AJOUTÉ.
NOUVELLE RUPTURE TRANSVERSAL DU TAPIS À CÔTÉ DU RABIA TAHAR
RUPTURE TRANSVERSAL DU TAPIS à CÔTÉ DU OUED SMAR. DERNIER MORCEAU DE TAPIS AJOUTÉ.
NOUVELLE RUPTURE TRANSVERSAL DU TAPIS À CÔTÉ DU RABIA TAHAR
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
TRAVAUX D´EXCAVATION
RETOUR DE MATERIEL EXCAVÉ VERS LE TBM À CAUSE DE SA CHUTE SUR LA BANDE DE RETOUR DÛ À LA PENTE EXCESSIVE DU
TAPIS SUPERIEUR DANS LE VIRAGE DU T9 (TENSION EXCESSIVE, SYSTÈME
CONVOYEUR DECOMPENSÉ)
RETOUR DE MATERIEL EXCAVÉ VERS LE TBM À CAUSE DE SA CHUTE SUR LA BANDE DE RETOUR DÛ À LA PENTE EXCESSIVE DU
TAPIS SUPERIEUR DANS LE VIRAGE DU T9 (TENSION EXCESSIVE, SYSTÈME
CONVOYEUR DECOMPENSÉ). ARRIVÉE 07/09/2022.
RETOUR DE MATERIEL EXCAVÉ VERS LE TBM À CAUSE DE SA CHUTE SUR LA BANDE DE RETOUR DÛ À LA PENTE EXCESSIVE DU
TAPIS SUPERIEUR DANS LE VIRAGE DU T9 (TENSION EXCESSIVE, SYSTÈME
CONVOYEUR DECOMPENSÉ). ARRIVÉE 07/09/2022.
TBM DANS LE PV10. NETTOYAGE DE LA TÊTE DE COUPE ET DU PUITS
TBM DANS LE PV10. NETTOYAGE DE LA TÊTE DE COUPE ET DU PUITS
/PV10/ NETTOYAGE DE LA TÊTE DE COUPE ET DU PUITS. MONTAGE GRUE 400 t /TUNNEL/ NETTOYAGE
/TBM/ NETTOYAGE /OUED SMAR/ DEMOLITION ET NETTOYAGE
/PV10/ MONTAGE GRUE 400 t. AVANCEMENT DU TBM POUR SE PLACER DANS LA POSITION PRÉVUE POUR LE LEVAGE DE LA TÊTE
DE COUPE. 3 ANNEAUX MONTÉS. ECHAFAUDAGE POUR LA TÊTE DE COUPE. DÉMONTAGE DES OUTILS DE COUPE /TUNNEL/
NETTOYAGE /TBM/ NETTOYAGE /OUED SMAR/
DEMOLITION ET NETTOYAGE

/PV10/ MONTAGE GRUE 400 t. ECHAFAUDAGE POUR LA TÊTE DE COUPE. FIN DÉMONTAGE DES OUTILS DE COUPE /TUNNEL/
NETTOYAGE /TBM/ NETTOYAGE /OUED SMAR/ DEMOLITION ET NETTOYAGE

/PV10/ MONTAGE GRUE 400 t. ECHAFAUDAGE POUR LA TÊTE DE COUPE. RETRAIT DES BOULONS DE CONNEXION TÊTE DE COUPE
- BOUCLIER. RETRAIT CONDUITES DE LA MOUSSE /TUNNEL/ NETTOYAGE. REPARATION T5. 500 m DE BANDE COLLECTÉS /TBM/
NETTOYAGE /OUED SMAR/ DEMOLITION ET
NETTOYAGE

/PV10/ MONTAGE GRUE 400 t. SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA LEVER/TUNNEL/ NETTOYAGE. RETRAIT
DE LA STRUCTURE DE REACTION DE LA STATION AEROPORT. REPARATION T5. 500 m DE BANDE COLLECTÉS /TBM/
NETTOYAGE /OUED SMAR/ DEMOLITION ET NETTOYAGE

/PV10/ MONTAGE GRUE 400 t. SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA LEVER/TUNNEL/ NETTOYAGE.
REPARATION T5. 500 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/
DEMOLITION ET NETTOYAGE

/PV10/ MONTAGE GRUE 400 t. SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA LEVER/TUNNEL/ NETTOYAGE.
REPARATION T5. 500 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/
DEMOLITION ET NETTOYAGE

/PV10/ MONTAGE GRUE 400 t TERMINÉ, IL MANQUE LA CERTIFICATION. SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA
LEVER /TUNNEL/ NETTOYAGE. REPARATION T5. 900 m DE BANDE COLLECTÉS
/TBM/ NETTOYAGE /OUED SMAR/ DEMOLITION ET NETTOYAGE

/PV10/ SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA LEVER /TUNNEL/ NETTOYAGE.
REPARATION T5. 900 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/ DEMOLITION ET NETTOYAGE

/PV10/ SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA LEVER /TUNNEL/ NETTOYAGE.
REPARATION T5. 900 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/ NETTOYAGE
/PV10/ SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA LEVER. ESSAIS DE CONTRÔLE DE LA SOUDURE /TUNNEL/
NETTOYAGE. REPARATION T5. 900 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE
/OUED SMAR/ PREPARATION DE LA FRAGILISATION DE LA PAROI MOULÉE POUR SA DÉMOLITION
/PV10/ SOUDURE DES OREILLES DE LA TÊTE DE COUPE POUR LA LEVER. ESSAIS DE CONTRÔLE DE LA SOUDURE /TUNNEL/
NETTOYAGE. REPARATION T5. 1.000 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE
/OUED SMAR/ PREPARATION DE LA FRAGILISATION DE LA PAROI MOULÉE POUR SA DÉMOLITION

/PV10/ RÉPARATION DE LA TETE DE COUPE - SOUDURE/TUNNEL/ NETTOYAGE. REPARATION T5. 1.000 m


DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/ PREPARATION DE LA FRAGILISATION DE LA PAROI MOULÉE POUR SA
DÉMOLITION
/PV10/ RÉPARATION DE LA TETE DE COUPE - SOUDURE/TUNNEL/ NETTOYAGE. REPARATION T5. 1.000 m
DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/ PREPARATION DE LA FRAGILISATION DE LA PAROI MOULÉE POUR SA
DÉMOLITION
/PV10/ RÉPARATION DE LA TETE DE COUPE - SOUDURE/TUNNEL/ NETTOYAGE. REPARATION T5. 3.000 m
DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/ PREPARATION DE LA FRAGILISATION DE LA PAROI MOULÉE POUR SA
DÉMOLITION
/PV10/ RÉPARATION DE LA TETE DE COUPE - SOUDURE. TRAVAUX DE DIVISION DU BOUCLIER TBM/TUNNEL/ NETTOYAGE.
REPARATION T5. 5.000 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED
SMAR/ FRAGILISATION DE LA PAROI MOULÉE POUR SA DÉMOLITION
/PV10/ RÉPARATION DE LA TETE DE COUPE - SOUDURE. TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE PARTIEL DU
SYSTEME DE VÉRINS HYDRAULIQUE /TUNNEL/ NETTOYAGE. REPARATION T5.
5.100 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/ DEMOLITION DE LA PAROI MOULÉE.

/PV10/ RÉPARATION DE LA TETE DE COUPE - SOUDURE. TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE DU SYSTEME DE
TUYAUX ET DE CABLES/TUNNEL/ NETTOYAGE. REPARATION T5. 5.200 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/
PROTECTION DU MUR DEMOLI AVEC DU BÉTON
PROJETÉ

/PV10/ RÉPARATION DE LA TETE DE COUPE - SOUDURE. TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE DU SYSTEME DE
TUYAUX ET DE CABLES/TUNNEL/ NETTOYAGE. REPARATION T5. 6.000 m DE BANDE COLLECTÉS /TBM/ NETTOYAGE /OUED SMAR/
PROTECTION DU MUR DEMOLI AVEC DU BÉTON
PROJETÉ

/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE DU SYSTEME DE TUYAUX ET DE
CABLES. TRAVAUX DE DECONNEXION DE LA VIS SANS FIN/TUNNEL/ NETTOYAGE. DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. 7.000 m DE BANDE COLLECTÉS
/TBM/ NETTOYAGE /OUED SMAR/ RETRAIT DES DEBLAIS PROVENANT DE LA DEMOLITION DU MUR EN
BÉTON.

/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE DU SYSTEME DE TUYAUX ET DE
CABLES. TRAVAUX DE DECONNEXION DE LA VIS SANS FIN/TUNNEL/ NETTOYAGE. DEMONTAGE DES TUYAUX AUXILIAIRES..
REPARATION T5. 8.000 m DE BANDE COLLECTÉS
/TBM/ NETTOYAGE /OUED SMAR/ RETRAIT DES DEBLAIS PROVENANT DE LA DEMOLITION DU MUR EN
BÉTON.

/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE DU SYSTEME DE TUYAUX ET DE
CABLES. TRAVAUX DE DECONNEXION DE LA VIS SANS FIN/TUNNEL/ NETTOYAGE. DEMONTAGE DES TUYAUX AUXILIAIRES..
REPARATION T5. BANDA COLECTADA EN SU TOTALIDAD /TBM/ NETTOYAGE /OUED SMAR/ RETRAIT DES DEBLAIS PROVENANT
DE LA DEMOLITION DU
MUR EN BÉTON.
/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE DU SYSTEME DE TUYAUX ET DE
CABLES. TRAVAUX DE DECONNEXION DE LA VIS SANS FIN/TUNNEL/ NETTOYAGE. DEMONTAGE DES TUYAUX AUXILIAIRES..
REPARATION T5. LA BANDE COLLECTÉS DANS SON TOTALITÉ /TBM/ NETTOYAGE. DEBRONCHEMENT DES CLABLES/OUED SMAR/
DEMONTAGE DES
TOURS DU CONVOYEUR HORIZONTAL.

/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM. DÉMONTAGE DU JOINT D´ETANCHEITÉ /
BROSSES METALLIQUES. TRAVAUX DE DECONNEXION DE LA VIS SANS FIN/TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. LA BANDE COLLECTÉS DANS SON TOTALITÉ
/TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP/OUED SMAR/
DEMONTAGE DE LA CABINE DE CONTROLE ELECTRONIQUE DU CONVOYEUR, TRAVAUX DE NETTOYAGE DE LA STATION.
05-Oct-2022 T4, T5

06-Oct-2022

07-Oct-2022

08-Oct-2022

09-Oct-2022

10-Oct-2022

11-Oct-2022

12-Oct-2022

13-Oct-2022

14-Oct-2022

15-Oct-2022

16-Oct-2022

17-Oct-2022
18-Oct-2022

19-Oct-2022

20-Oct-2022

21-Oct-2022

22-Oct-2022

23-Oct-2022

24-Oct-2022

25-Oct-2022

RAPPORT DE PRODUCTION DU TUNNEL PRINCIPAL.


3. SUIVI DE PLANNING
AL.
/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM. DÉMONTAGE DU JOINT D´ETANCHEITÉ /
BROSSES METALLIQUES TRAVAUX DE DECONNEXION DE LA VIS SANS FIN. DEMONTAGE PARTIEL DU WAGON 1 DU BACK UP AVEC
LES ARTICULATIONS OU TOWING/TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/DEMONTAGE DES
CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES/OUED
SMAR/ ADAPTATION DES VEHICULES MULTISERVICES POUR LE TRANSPORT DES MATERIELS AUXILAIRES DES
TUNNELS.

/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM. DEMONTAGE PARTIEL DU WAGON 1 DU BACK UP
AVEC LES ARTICULATIONS OU TOWING/TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/DEMONTAGE
DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES/OUED
SMAR/ ADAPTATION DES VEHICULES MULTISERVICES POUR LE TRANSPORT DES MATERIELS AUXILAIRES DES TUNNELS.

/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM./TUNNEL/ DEMONTAGE DES TUYAUX
AUXILIAIRES. REPARATION T5. /TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP.
DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/
DÉMONTAGE DES TOURS VERTICAUX DU CONVOYEUR
HORIZONTAL AVEC LES TAMBOURS D´ENTRAINEMENT.

/PV10/ SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM./TUNNEL/ DEMONTAGE DES TUYAUX
AUXILIAIRES. REPARATION T5. /TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP.
DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/
DÉMONTAGE DES TOURS VERTICAUX DU CONVOYEUR
HORIZONTAL AVEC LES TAMBOURS D´ENTRAINEMENT.

/PV10/ TRASOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU BOUCLIER TBM./TUNNEL/ DEMONTAGE DES TUYAUX
AUXILIAIRES. REPARATION T5.DEMOLITION DES ANNEAUX EXTERIEURS PROVISOIRES DE L´AEROPORT. /TBM/DEMONTAGE DES
CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES.
DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/ DÉMONTAGE DES TOURS VERTICAUX DU CONVOYEUR
HORIZONTAL AVEC
LES TAMBOURS D´ENTRAINEMENT.

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION DU
BOUCLIER TBM. DÉMONTAGE DE LA VIS SANS FIN DE L’ENTRAÎNEMENT PRINCIPAL OU MAIN DRIVE/TUNNEL/ DEMONTAGE DES
TUYAUX AUXILIAIRES. REPARATION T5.
/TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES COMPOSANTS
ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/ DÉMONTAGE DES TOURS VERTICAUX DU
CONVOYEUR HORIZONTAL AVEC LES TAMBOURS D´ENTRAINEMENT.DÉMONTAGE DE LA STRUCTURE METALLIQUE DU
CONVOYEUR VERTICAL.

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE.DEPLACEMENT AVEC GRUE DU BOUCLIER ARRIÉRE DU
TUNNELIER (PHASE1), DÉMONTAGE DE 14 VÉRINS DE PROPULSION DU TBM, SOUDAGE DES ANCRAGES ET TRAVAUX DE DIVISION
DU BOUCLIER TBM. DÉMONTAGE DE LA VIS SANS FIN DE L’ENTRAÎNEMENT PRINCIPAL OU MAIN DRIVE/TUNNEL/ DEMONTAGE
DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP.
DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/
DÉMONTAGE DES TOURS VERTICAUX DU CONVOYEUR HORIZONTAL AVEC LES
TAMBOURS D´ENTRAINEMENT

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. DÉMONTAGE DE 14 VÉRINS DE PROPULSION DU TBM,
DIVISION DU BOUCLIER TBM. /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/DEMONTAGE DES
CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES.
DÉMONTAGE DU PLC CABINE DE CONTRÖLE
TBM/OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION,

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. SOULEVEMENT DU BOUCLIER ARRIÉRE DU TUNNELIER
/TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5.
/TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT
DES COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/TRAVAUX DE NETTOYAGE A
LA STATION.

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. /TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES
COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/TRAVAUX DE NETTOYAGE A LA
STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET TRAVAUX POUR L´INSTALLATION DES RAILS DE
GLISSEMENT.

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. /TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES
COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/TRAVAUX DE NETTOYAGE A LA
STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET TRAVAUX POUR L´INSTALLATION DES RAILS DE
GLISSEMENT.

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. /TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES
COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/TRAVAUX DE NETTOYAGE A LA
STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET TRAVAUX POUR L´INSTALLATION DES RAILS DE
GLISSEMENT.

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. PREPARATION DE L´OPERATION DE SOULEVEMENT DE LA VIS
SANS FIN /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5.
/TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES WAGONS DU BACK UP. DÉBRONCHEMENT DES COMPOSANTS
ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE TBM/OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION.
PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET TRAVAUX POUR L´INSTALLATION DES RAILS DE .DEBUT DES
TRAVAUX DE DEMONTAGE DU
WINCH, 400 METRES DE CABLE COLLECTÉ.
/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. SOULEVEMENT DE LA VIS SANS FIN
/TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/DEMONTAGE DES CABLES ET DES TUYAUX ENTRE LES
WAGONS DU BACK UP. DÉBRONCHEMENT DES COMPOSANTS ELECTRONIQUES. DÉMONTAGE DU PLC CABINE DE CONTRÖLE
TBM/OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET
TRAVAUX POUR L´INSTALLATION DES RAILS DE .DEBUT DES TRAVAUX DE DEMONTAGE DU WINCH, 400 METRES DE CABLE
COLLECTÉ.

/PV10/ TRAVAUX DE DIVISION EN 3 PARTIES DE LA TETE DE COUPE. TRAVAUX PRÉVUE POUR LE PROCHAIN SOULEVEMENT DE L
´ERECTEUR DE VOUSSOIRS ET DE 2 POUTRES /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/
NETTOYAGE DE LA CABINE DE CONTRÖLE DE LA TBM, NETTOYAGE DES CADRES ELECTRIQUES /OUED SMAR/TRAVAUX DE
NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET TRAVAUX POUR L´INSTALLATION
DES
RAILS DE GLISSEMENT.

/PV10/ LEVAGE DE L´ERECTEUR À SURFACE /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/ SIN
ACTIVIDAD /OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM
ET TRAVAUX POUR L´INSTALLATION DES
RAILS DE GLISSEMENT.

/PV10/ TRAVAUX POUR LA DIVISION DU BOUCLIER INTERMEDIAIRE /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. /TBM/ SANS ACTIVITÉ /OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI
POUR LE MONTAGE DU TBM ET TRAVAUX POUR
L´INSTALLATION DES RAILS DE GLISSEMENT.

/PV10/ TRAVAUX POUR LA DIVISION DU BOUCLIER INTERMEDIAIRE /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. /TBM/ SANS ACTIVITÉ /OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI
POUR LE MONTAGE DU TBM ET TRAVAUX POUR
L´INSTALLATION DES RAILS DE GLISSEMENT.

/PV10/ TRAVAUX POUR LA DIVISION DU BOUCLIER INTERMEDIAIRE /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES.
REPARATION T5. /TBM/ SANS ACTIVITÉ /OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI
POUR LE MONTAGE DU TBM ET TRAVAUX POUR
L´INSTALLATION DES RAILS DE GLISSEMENT.

/PV10/ LEVAGE DU BOUCLIER INTERMEDIAIRE /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/ SANS
ACTIVITÉ /OUED SMAR/TRAVAUX DE NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET
TRAVAUX POUR L´INSTALLATION DES
RAILS DE GLISSEMENT.

/PV10/ TRAVAUX POUR LA DIVISION DU BOUCLIER FRONTAL EN QUATRE PARTIES ET POUR L´EXTRACTION DE L´ENTRAINEMENT
PRINCIPAL OU MAIN DRIVE /TUNNEL/ DEMONTAGE DES TUYAUX AUXILIAIRES. REPARATION T5. /TBM/ SANS ACTIVITÉ /OUED
SMAR/TRAVAUX DE NETTOYAGE A LA STATION. PREPARATION DE BLOC D´APPUI POUR LE MONTAGE DU TBM ET TRAVAUX POUR
L´INSTALLATION DES RAILS DE GLISSEMENT.
Nº ACTIVITÉ DURÉE (j) DÉBUT
1 ACTIVITÉS DE CHANGEMENT DE LA PHASE I À LA PHASE II 124 15-Sep-2022
132 07-Sep-2022
2 ENTRÉE DU TBM VERS PV10 (PERCÉE) 1 15-Sep-2022
1 07-Sep-2022
3 DÉMONTAGE TBM À PV10 41 15-Sep-2022
07-Sep-2022
4 LAVAGE COMPLET DE LA TÊTE ET NETTOYAGE DU BERCEAU 4 15-Sep-2022
4 07-Sep-2022
5 1º TRANSLATION DE LA TBM JUSQU´A LA POSITION DE LEVAGE DE LA TÊTE 3 19-Sep-2022
1 13-Sep-2022
6 SOUDAGE DES POINTS DE LEVAGE ET ENLEVEMENT DES VIEUX OUTILS 5 22-Sep-2022
8 14-Sep-2022
7 LEVAGE DE LA TÊTE DE COUPE 1 27-Sep-2022
1 22-Sep-2022
8 2º TRANSLATION DE LA TBM JUSQU´A LA POSITION DE LEVAGE DES AUTRES ELEMENTS 2 28-Sep-2022
2 23-Sep-2022
9 DÉCONNEXION DES TUYAUX ET DE CÂBLES ENTRE LE TUNNELIER ET LES TRAIN SUIVEUR 5 30-Sep-2022
5 28-Sep-2022
10 DÉCONNEXION ET LEVAGE DU CONVOYEUR À VIS 2 05-Oct-2022
1 18-Oct-2022
11 COUPE SOUDURE BOUCLIERS ARRIERE - CENTRAL. DÉMONTAGE DU BOUCLIER ARRIERE 4 07-Oct-2022
15 27-Sep-2022
12 LEVAGE DU BOUCLIER ARRIERE 1 11-Oct-2022
1 13-Oct-2022
13 DÉMONTAGE ET LEVAGE DE L´ESCALIER DE L´ERECTEUR 1 12-Oct-2022
1 11-Oct-2022
14 DECONNEXION ET LEVAGE DE L´ERECTEUR COMPLET AVEC POUTRE PORTEUSE 2 13-Oct-2022
1 19-Oct-2022
15 DÉMONTAGE ET LEVAGE DU BOUCLIER INTERMEDIARE AVEC LES VERINS DE POUSSÉE 3 15-Oct-2022
27 27-Sep-2022
16 DÉMONTAGE ET DÉCOUPE DU BOUCLIER INTERMEDIARE EN SURFACE 3 18-Oct-2022

17 DÉCOUPE , DÉMONTAGE ET LEVAGE DU BOUCLIER FRONTAL - PARTIE SUPERIEURE 2 18-Oct-2022


14-Oct-2022
18 DÉCOUPE , DÉMONTAGE ET LEVAGE DU BOUCLIER FRONTAL - PARTIE DROITE 2 20-Oct-2022
27-Sep-2022
19 DÉCOUPE , DÉMONTAGE ET LEVAGE DU BOUCLIER FRONTAL - PARTIE GAUCHE 2 22-Oct-2022
27-Sep-2022
20 LEVAGE DU MAIN DRIVE (MOTEURS INCLUS) 1 24-Oct-2022

21 LEVAGE DU BOUCLIER FRONTAL - PARTIE INFERIEURE 1 25-Oct-2022

22 FIN DE DÉMONTAGE DU TBM - PV10 LIBERÉ DU TBM 1 26-Oct-2022

23 DÉMONTAGE DE WAGON PV10 40 27-Oct-2022

24 CREATION DU RADIER PV10 AVEC DES VOUSSOIRS À ARCS INVERSÉES POUR PERMETTRE AUX 3 27-Oct-2022

25 AVANCEMANT DU WAGON N°1 JUSQU’À LA FENETRE ET DEMONTAGE DES ROUES. SOUDAGE DE 3 30-Oct-2022

26 LEVAGE DU WAGON Nº1 ET POSITIONNEMENT SUR LA SURFACE 3 02-Nov-2022

27 DÉMANTELEMENT DU WAGON Nº1 EN ELEMENTS TRANSPORTABLES 3 04-Nov-2022


S2 O22 N22 D22 J23 F23
FIN 21 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4

17-Jan-2023
17-Jan-2023
16-Sep-2022
08-Sep-2022
26-Oct-2022

19-Sep-2022
11-Sep-2022
22-Sep-2022
14-Sep-2022
27-Sep-2022
22-Sep-2022
28-Sep-2022
23-Sep-2022
30-Sep-2022
25-Sep-2022
05-Oct-2022
03-Oct-2022
07-Oct-2022
19-Oct-2022
11-Oct-2022
12-Oct-2022
12-Oct-2022
14-Oct-2022
13-Oct-2022
12-Oct-2022
15-Oct-2022
20-Oct-2022
18-Oct-2022
24-Oct-2022
21-Oct-2022

20-Oct-2022

22-Oct-2022

24-Oct-2022

25-Oct-2022

26-Oct-2022

27-Oct-2022

06-Dec-2022

30-Oct-2022

02-Nov-2022

05-Nov-2022

07-Nov-2022
Nº ACTIVITÉ DURÉE (j) DÉBUT
28 PREPARATION DE SOUTENEMENTS SUR ROUES TEMPORAIRES POUR LE PONT (les roues du wagon 2 07-Nov-2022

29 AVANCEMENT DU PONT ET LEVAGE ET POSITIONNEMENT A LA SURFACE 2 09-Nov-2022

30 DEMANTELEMENT DU PONT EN ELEMENTS TRANSPORTABLES 3 11-Nov-2022

31 AVANCEMENT DU WAGON 2 SOUS LA FENETRE 2 14-Nov-2022

32 LEVAGE DU WAGON 2 ET POSITIONNEMENT SUR LA SURFACE 1 16-Nov-2022

33 DEMONTAGE DU WAGON 2 3 17-Nov-2022

34 AVANCEMENT DU WAGON 3 SOUS LA FENETRE 2 20-Nov-2022

35 LEVAGE DU WAGON 3 ET POSITIONNEMENT SUR LA SURFACE 2 22-Nov-2022

36 DEMONTAGE DU WAGON 3 3 24-Nov-2022

37 AVANCEMENT DU WAGON 4 SOUS LA FENETRE 1 27-Nov-2022

38 LEVAGE DU WAGON 4 ET POSITIONNEMENT SUR LA SURFACE 1 28-Nov-2022

39 DEMONTAGE DU WAGON 4 3 29-Nov-2022

40 AVANCEMENT DU WAGON 5 SOUS LA FENETRE 1 02-Dec-2022

41 LEVAGE DU WAGON 5 ET POSITIONNEMENT SUR LA SURFACE 1 03-Dec-2022

42 DEMONTAGE DU WAGON 5 2 04-Dec-2022

43 TOUS LE WAGONS SONT DÉMONTÉS 1 06-Dec-2022

44 TRANSFERT TBM ET BU DE PV10 À OUED SMAR 64 07-Oct-2022

45 TRANSFERT DE CONVOYEUR A VIS DE PV 10 À OUED SMAR 1 07-Oct-2022

46 TRANSFERT DE L´ERECTEUR ET L´ESCALIER DE L´ERECTEUR DU PV 10 À OUED SMAR 1 13-Oct-2022

47 TRANSFERT DU BOUCLIER INTERMÉDIAIRE DE PV 10 À OUED SMAR 2 18-Oct-2022

48 TRANSFERT DES SECTEURS SUPÉRIEUR DU BOUCLIER AVANT DE PV10 À OUED SMAR 1 20-Oct-2022

49 TRANSFERT DES SECTEURS DROIT DU BOUCLIER AVANT DE PV10 À OUED SMAR 1 22-Oct-2022

50 TRANSFERT DES SECTEURS GAUCHE DU BOUCLIER AVANT DE PV10 À OUED SMAR 1 24-Oct-2022

51 TRANSFERT DU MAIN DRIVE (INCL. MOTEURS) DU PV10 À OUED SMAR 1 25-Oct-2022

52 TRANSFERT DES SECTEURS INFÉRIEUR DU BOUCLIER AVANT DE PV10 À OUED SMAR 1 26-Oct-2022

53 TRANSFERT DE LA TÊTE DE PV10 À OUED SMAR 1 28-Oct-2022

54 TRANSFERT DU BOUCLIER ARRIERE DE PV 10 À OUED SMAR 2 29-Oct-2022


S22 O22 N22 D22 J23 F23
FIN 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4

09-Nov-2022

11-Nov-2022

14-Nov-2022

16-Nov-2022

17-Nov-2022

20-Nov-2022

22-Nov-2022

24-Nov-2022

27-Nov-2022

28-Nov-2022

29-Nov-2022

02-Dec-2022

03-Dec-2022

04-Dec-2022

06-Dec-2022

07-Dec-2022

10-Dec-2022

08-Oct-2022

14-Oct-2022

20-Oct-2022

21-Oct-2022

23-Oct-2022

25-Oct-2022

26-Oct-2022

27-Oct-2022

29-Oct-2022

31-Oct-2022
Nº ACTIVITÉ DURÉE (j) DÉBUT
55 TRANSFERT DU WAGON 1 À OUED SMAR PAR ROUTE 2 07-Nov-2022

56 TRANSPORT D´ÉQUIPEMENTS AUXILIAIRES 3 07-Nov-2022

57 TRANSFERT DU PONT À OUED SMAR PAR ROUTE 2 14-Nov-2022

58 TRANSPORT D´ÉQUIPEMENTS AUXILIAIRES 3 14-Nov-2022

59 TRANSFERT DU WAGON 2 À OUED SMAR PAR ROUTE 2 20-Nov-2022

60 TRANSPORT D´ÉQUIPEMENTS AUXILIAIRES 3 20-Nov-2022

61 TRANSFERT DU WAGON 3 À OUED SMAR PAR ROUTE 2 27-Nov-2022

62 TRANSPORT D´ÉQUIPEMENTS AUXILIAIRES 3 27-Nov-2022

63 TRANSFERT DU WAGON 4 À OUED SMAR PAR ROUTE 2 02-Dec-2022

64 TRANSPORT D´ÉQUIPEMENTS AUXILIAIRES 3 02-Dec-2022

65 TRANSFERT DU WAGON 5 À OUED SMAR PAR ROUTE 2 06-Dec-2022

66 TRANSPORT D´ÉQUIPEMENTS AUXILIAIRES 4 06-Dec-2022

67 TOUS LES WAGONS SONT À OUED SMAR 1 10-Dec-2022

68 PREPARATION DE LA STATION OUED SMAR 26 15-Sep-2022


11-Sep-2022
69 NETTOYAGE DE LA STATION 8 15-Sep-2022
11-Sep-2022
70 DÉMOLITION DES MURS INUTILS ET DE TOUTES LES STRUCTURE TEMPORAIRES 6 23-Sep-2022
6 12-Sep-2022
71 RESTAURATION / CREATION DU RADIER POUR LE LOGEMENT DU TUNNELIER 8 29-Sep-2022
8 12-Sep-2022
72 RESTAURATION DES ZONES ENVIRONNANTES POUR L´INSTALLATION DES EQUIPMENTS 4 07-Oct-2022
2 11-Sep-2022
73 RÉMONTAGE DU TBM À OUED SMAR 65 20-Oct-2022

74 DESCENTE ET POSITIONNEMENT DU SECTEUR INFERIEUR DU BOUCLIER AVANT (90 t) 1 27-Oct-2022

75 DESCENTE DE MAIN DRIVE (155 t) 1 27-Oct-2022

76 DESCENTE DU SECTEUR GAUCHE DU BOUCLIER FRONTAL 1 28-Oct-2022

77 DESCENTE DU SECTEUR DROIT DU BOUCLIER FRONTAL 1 29-Oct-2022

78 DESCENTE DU SECTEUR SUPERIEUR DU BOUCLIER FRONTAL 1 29-Oct-2022

79 SOUDAGE ET FERMETURE DU BOUCLIER FRONTAL 6 30-Oct-2022

80 MONTAGE ET SOUDAGE DU BOUCLIER INTERMEDIAIRE EN SURFACE 4 20-Oct-2022

81 MONTAGE DU JOINT D´ETANCHEITE 3 24-Oct-2022


S22 O22 N22 D22 J23 F23
FIN 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4

09-Nov-2022

10-Nov-2022

16-Nov-2022

17-Nov-2022

22-Nov-2022

23-Nov-2022

29-Nov-2022

30-Nov-2022

04-Dec-2022

05-Dec-2022

08-Dec-2022

10-Dec-2022

11-Dec-2022

11-Oct-2022

23-Sep-2022

29-Sep-2022
18-Sep-2022
07-Oct-2022
20-Sep-2022
11-Oct-2022
13-Sep-2022
24-Dec-2022

28-Oct-2022

28-Oct-2022

29-Oct-2022

30-Oct-2022

30-Oct-2022

05-Nov-2022

24-Oct-2022

27-Oct-2022
Nº ACTIVITÉ DURÉE (j) DÉBUT
82 DESCENTE DE L´ANNEAU POSTERIEUR DU BOUCLIER INTER ET DE LA CROIX CENTRALE 2 27-Oct-2022

83 DESCENTE ET CONNEXION DE LA TÊTE (Installation del nouveaux outils) 5 29-Oct-2022

84 DESCENTE ET CONNEXION DE L´ESCALIER DE L´ERECTEUR 2 29-Oct-2022

85 DEPLACEMENT VERS L´AVANT DU TBM (8,8 m) 4 03-Nov-2022

86 DESCENTE ET ASSEMBLAGE DE L´ERECTEUR COMPLET AVEC LA POUTRE PORTEUSE 2 07-Nov-2022

87 DEPLACEMENT VERS L´AVANT DU TBM (2,6 m). POSITION RTB 3 09-Nov-2022

88 POSITIONNEMENT DE LA GRUE A VOUSSOIR SUR LE RADIER 1 12-Nov-2022

89 DESCENTE DU CONVOYEUR A VIS 1 13-Nov-2022

90 DESCENTE ET SOUDAGE DU BOUCLIER ARRIERE 5 14-Nov-2022

91 INSTALLATION DU BATI D´APPUI 4 19-Nov-2022

92 MONTAGE COMPLET DU WAGON 1 ET RACCORDEMENT AU TUNNELIER 4 23-Nov-2022

93 MONTAGE COMPLET DU PONT 3 27-Nov-2022

94 MONTAGE COMPLET DU WAGON 2 3 30-Nov-2022

95 MONTAGE COMPLET DU WAGON 3 3 03-Dec-2022

96 MONTAGE COMPLET DU WAGON 4 3 06-Dec-2022

97 MONTAGE COMPLET DU WAGON 5 3 09-Dec-2022

98 CONNEXION ÉLECTRIQUES/ÉLECTRONIQUES ET HYDRAULIQUES BOUCLIER-TBM 9 12-Dec-2022

99 ESSAIS FINAUX DE FONCTIONNEMENT 3 21-Dec-2022

100 ASSEMBLAGE DU TBM TERMINÉ 1 24-Dec-2022

101 DÉMONTAGE ET REMONTAGE DU CONVOYEUR À OUED SMAR 124 15-Sep-2022

102 COLLECTION DU TAPIS DE MAGASIN DE BANDE AVEC SYSTÉME MOTORISÉ A OUED SMAR 20 15-Sep-2022
17 14-Sep-2022
103 DÉMONTAGE DU CONVOYEUR BY-PASS 2 15-Sep-2022
1 14-Sep-2022
104 DÉMONTAGE BORFLEX 5 17-Sep-2022
5 07-Sep-2022
105 DÉMATELEMENT DES TOURS DE DÉRIVATION 7 05-Oct-2022
8 02-Oct-2022
106 DÉMATELEMENT DE LA TOUR TC01 5 12-Oct-2022
8 02-Oct-2022
107 DÉMONTAGE DU RUBAN SUSPENDU AUX POUTRES DE LA STATION 7 17-Oct-2022
3 29-Sep-2022
108 DÉMONTAGE DU MAGASIN DE BANDE 10 24-Oct-2022
17-Oct-2022
S22 O22 N22 D22 J23 F23
FIN 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4

29-Oct-2022

03-Nov-2022

31-Oct-2022

07-Nov-2022

09-Nov-2022

12-Nov-2022

13-Nov-2022

14-Nov-2022

19-Nov-2022

23-Nov-2022

27-Nov-2022

30-Nov-2022

03-Dec-2022

06-Dec-2022

09-Dec-2022

12-Dec-2022

21-Dec-2022

24-Dec-2022

25-Dec-2022

17-Jan-2023

05-Oct-2022
01-Oct-2022
17-Sep-2022
15-Sep-2022
22-Sep-2022
12-Sep-2022
12-Oct-2022
10-Oct-2022
17-Oct-2022
10-Oct-2022
24-Oct-2022
02-Oct-2022
03-Nov-2022
Nº ACTIVITÉ DURÉE (j) DÉBUT
109 DÉMONTAGE TC03 10 03-Nov-2022
8 02-Oct-2022
110 BORFLEX- PRÉ-ASSEMBLAGE AU SOL 15 13-Nov-2022

111 BORFLEX- ASSEMBLAGE DE SUPPORT EN POSITION 6 28-Nov-2022

112 BORFLEX- POSITIONNEMENT 2 04-Dec-2022

113 MAGASIN DE BANDE - MONTAGE EN PLACE 15 03-Nov-2022

114 CONVOYEUR DE REMONTÉ - ASSEMBLAGE DES SUPPORTS EN PLACE 4 06-Dec-2022

115 CONVOYEUR DE REMONTÉ - PRÉ-ASSEMBLAGE DE GABARIT AU SOL 4 06-Dec-2022

116 CONVOYEUR DE REMONTÉ - ASSEMBLAGE DE GABARIT EN PLACE 5 14-Dec-2022

117 CONVOYEUR DE REMONTÉ - POSITIONNEMENT DU TAPIS 3 19-Dec-2022

118 CONVOYEUR DE REMONTÉ - MONTAGE DE LA TRÉMIES ET LA PROTECTIONS 4 22-Dec-2022

119 CONVOYEUR BY-PASS - MONTAGE DE SUPPORTS 3 19-Dec-2022

120 CONVOYEUR BY-PASS - POSITIONNEMENT DU CONVOYEUR 1 22-Dec-2022

121 CONVOYEUR TUNNEL- TÊTE DE TRACTION 5 23-Dec-2022

122 CONVOYEUR TUNNEL- CONNEXION A L´ENTREPÖT 3 28-Dec-2022

123 CONVOYEUR TUNNEL- GABARIT SUSPENDUS AUX POUTRES 10 28-Dec-2022

124 CONVOYEUR TUNNEL- POSITIONNEMENT DU TAPIS 5 10-Jan-2023

125 SYSTÉME ÉLECTRIQUES - POSITIONNEMENT DES CABLES 5 28-Dec-2022

126 SYSTÉME ÉLECTRIQUES - CÄBLAGE 5 02-Jan-2023

127 SYSTÉME ÉLECTRIQUES - CONNEXION AU RÉSEAU ÉLECTRIQUE 3 07-Jan-2023

128 TESTS ET RÉGLAGES DU FONCTIONNEMENT DE LA BANDE 2 15-Jan-2023

129 SYSTEME DE CONVOYEUR PRÊT 1 17-Jan-2022

130 TBM PRÊT POUR LE FORAGE 1 17-Jan-2022

131 DÉMONTAGE DE LIGNES DE TUNNEL ET DÉMOLITION DE CALIFORNIENS 124 15-Sep-2022

132 DÉMONTAGE DE 10 M DE STRUCTURE DE CONVOYEUR DU TUNNEL À L´ARRIERE DU TBM 2 05-Oct-2022


1 27-Sep-2022
133 DÉMONTAGE DE STRUCTURE DU CONVOYEUR TUNNEL À PARTIR DU PV10 30 07-Oct-2022
02-Oct-2022
134 DÉMONTAGE DE LA CONDUITE DE VENTILATION 25 15-Sep-2022
07-Oct-2022
135 DÉMONTAGE DES CONDUITES ET DE LA PASSARELLE 75 30-Sep-2022
27-Sep-2022
S22 O22 N22 D22 J23 F23
FIN 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4

13-Nov-2022
10-Oct-2022
28-Nov-2022

04-Dec-2022

06-Dec-2022

18-Nov-2022

10-Dec-2022

10-Dec-2022

19-Dec-2022

22-Dec-2022

26-Dec-2022

22-Dec-2022

23-Dec-2022

28-Dec-2022

31-Dec-2022

07-Jan-2023

15-Jan-2023

02-Jan-2023

07-Jan-2023

10-Jan-2023

17-Jan-2023

18-Jan-2022

18-Jan-2022

17-Jan-2023

07-Oct-2022
28-Sep-2022
06-Nov-2022

10-Oct-2022

14-Dec-2022
Nº ACTIVITÉ DURÉE (j) DÉBUT
136 REPARATION DES VOUSSOIRS 124 15/09/2022
15/09/2022
NOTES:
1. Concernant le démontage au PV10, le programme a été modifié; le bouclier arrière a été extrait avant que le vis sans fin.
2. L´activité "démontage du TBM au PV10" devrait finir le 27/10/2022.
3. Concernant les levages des parties du bouclier, à ce jour (27/10/2022) il était prévu 11/11 mais 6/11 ont été exécutés. Le retard est de 7 jours (la fin de la proc
4. Concernant les transferts des parties lourdes (transport special) du bouclier entre le PV10 et la station Oued Smar, à ce jour (27/10/2022) il était prévu 8/22 m
19 jours (la fin du premier transport était prévue le 8/10/22; date d´actualisation 27/10/22).
5. Le début de l´activité "remontage du TBM à Oued Smar" était prévu le 20/10/2022. Le retard est de 7 jours (20/10/2022 à 27/10/2022).
S22 O22 N22 D22 J23 F23
FIN 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4

17-Jan-2023

e retard est de 7 jours (la fin de la prochaine operation était prévue le 20/10/22; date d´actualisation 27/10/22).
our (27/10/2022) il était prévu 8/22 mais 0/22 ont été exécutés. Le retard est de

2 à 27/10/2022).
Travaux de Tunnelier
Récapitulatifs au des
de l’avancement 27/10/2022
travaux du Tunnelier au 27/10/2022 nouvelle
référence
250,00
Tunnelier
Prévue % 83.17
Réel % 59.95
Ecart en jours 201
Tunnelier
Prévue % 83.17
Réel % 59.95
Ecart en jours 201

200,00
150,00
100,00
50,00

0,00
L1B1-GCG-COSM28-3000-M4-80-901-8 PLANNING DETAILLE DES TRAVAUX DE TUNNELIER
ID tâche Nom de la tâche % d'avancement % prévu à Début de
performance date référence1

Métro d'alger : Ligne 1-Lot 2 Extension B1 : El HARR 59.95% 83.17% 01-Jul-2015

TUNNEL 59.95% 83.17% 01-Jul-2015

FABRICATION ET INSTALLATION DU TUNNELIER 0% 0% 01-Jul-2015


TUNNELIER (CREUSEMENT ET MISE EN PLACE VOUSSOIRS) 59.95% 83.17% 21-Dec-2019
TUNNEL Oued Smar - El Harrach 0% 57.99% 04-May-2022
D.0.1- Tunnel sur 750 ml ( HASSAN BADI - PV0 ) 0% 0% 25-Jan-2023
Entrée 0% 0% 25-Jan-2023
Tunnel 0% 0% 06-fév-23
Sortie 0% 0% 29-Mar-2023
D.2.1- Tunnel sur 529 ml ( POLE UNIV - HASSAN BADI ) 0% 0% 23-Nov-2022
Entrée 0% 0% 23-Nov-2022
Tunnel 0% 0% 27-Nov-2022
Sortie 0% 0% 06-Jan-2023
D.2.1- Tunnel sur 1137 ml ( BEAU LIEU - POLE UNIV ) 0% 89.78% 07-aoû-22
Entrée 0% 100% 07-aoû-22
Tunnel 0% 90.81% 13-aoû-22
Sortie 0% 0% 03-Nov-2022
D.6.1- Tunnel sur 905ml ( OUED SEMAR -BEAU LIEU ) 0% 100% 04-May-2022
Entrée 0% 100% 04-May-2022
Tunnel 0% 100% 07-May-2022
Sortie 0% 100% 18-Jul-2022
TUNNEL Oued Smar - l'Aéroport 100% 100% 21-Dec-2019
D.8.1- Tunnel sur 868 ml ( OUED SEMAR- U.S.T.H.B ) 100% 100% 21-Dec-2019
D.10.1- Tunnel sur 656 ml ( U.S.T.H.B - RABIA TAHAR ) 100% 100% 25-Oct-2020
D.12.1- Tunnel sur 965 ml ( RABIA TAHAR - SMAIL YEFSAH ) 100% 100% 02-fév-21
D.14.1- Tunnel sur 586 ml ( SMAIL YEFSAH - CENTRE DES AFFAI 100% 100% 20-May-2021
Entrée 100% 100% 20-May-2021
Tunnel 100% 100% 25-May-2021
Sortie 100% 100% 11-Jul-2021
D.16.1- Tunnel sur 1368 ml ( CENTRE DES AFFAIRES -AEROPOR 100% 100% 31-Jul-2021
Entrée 100% 100% 31-Jul-2021
Tunnel 100% 100% 12-aoû-21
Sortie 100% 100% 18-Nov-2021
D.18.1- Tunnel sur 543 ml ( AEROPORT - PV10 ) 100% 100% 07-Dec-2021
Entrée 100% 100% 07-Dec-2021
Tunnel 100% 100% 19-Dec-2021
Sortie 100% 100% 13-fév-22
DEMONTAGE INTTERMEDIAIRE 0% 0% 18-fév-22
A1860 Demontage intermediaire de la TBM 46.74% 100% 18-fév-22
A1870 Montage intermediaire de la TBM 0% 100% 04-Apr-2022
DEMONTAGE DEFINITIF 0% 0% 04-Apr-2023
17255 Démontage defenitif de la TBM 0% 0% 04-Apr-2023

RAPPORT DE PRODUCTION DU TUNNEL PRINCIPAL.


4. RAPPORT GRAPHIQUE DE SUIVI

RAPPORT DE SUIVI TBM – EPB
23 OCTOBRE 2022
PUITS 10: TRAVAUX POUR LA SEPARATION DU BOUCLIER INTERMEDIAIRE DU
BOUCLIER FRONTAL ET LE SOULEVEMENT DU BOUCLIER INTERMEDIAIRE
PHASE 1: SEPARATION DE L´UNION ENTRE LE BOUCLIER INTERMEDIAIRE
ET FRONTAL ET LE JOINT EN CAOUTCHOUC, AU MOYEN DE L'INSTALLATION DE
PLUSIEURS VÉRINS HYDRAULIQUES. RETRAIT DES GOUJONS MÉTALLIQUES DES VERINS
D'ARTICULATION DU TBM.
PHASE 2: SOULEVEMENT DU BOUCLIER INTERMEDIAIRE

PUITS 10: TRAVAUX POUR LA SEPARATION DU BOUCLIER INTERMEDIAIRE DU BOUCLIER FRONTAL


ET LE SOULEVEMENT DU BOUCLIER INTERMEDIAIRE. PHASE 1: SEPARATION DE L´UNION ENTRE LE
BOUCLIER INTERMEDIAIRE ET FRONTAL ET LE JOINT EN CAOUTCHOUC, AU MOYEN DE
L'INSTALLATION DE PLUSIEURS VÉRINS HYDRAULIQUES. RETRAIT DES GOUJONS MÉTALLIQUES
DES VERINS
D'ARTICULATION DU TBM.
PUITS 10: TRAVAUX DE LA DIVISION DE LA TÊTE DE COUPE DU TUNNELIER TBM EN 2 POUR SON
TRANSPORT, AJUSTEMENT DES POIDS. LE RETRAIT DES SCRAPERS POUR RÉDUIRE LE POIDS DE
LA TETE DE COUPE PENDANT LES
OPÉRATIONS DE TRANSPORT
PUITS 10: TRAVAUX DE LA DIVISION DE LA TÊTE DE COUPE DU TUNNELIER TBM EN 2 POUR SON
TRANSPORT, AJUSTEMENT DES POIDS. LE RETRAIT DES SCRAPERS POUR RÉDUIRE LE POIDS DE
LA TETE DE COUPE PENDANT LES
OPÉRATIONS DE TRANSPORT.
STATION OUED SMAR: TRAVAUX DE PREPARATION DE LA ZONE DE MONTAGE DU TBM (FOSSE,
POUTRES DE DÉPLACEMENT, BASE D'APPUI EN BÉTON PROJETÉ, ETC.), DÉMOLITION DE LA
CALIFORNIENNE EN BÉTON DE LA
STATION.
STATION OUED SMAR: TRAVAUX DE DÉMONTAGE DU WINCH DU CONVOYEUR
DU TBM.
STATION OUED SMAR: TRAVAUX DE DÉMONTAGE DES ANNEAUX EXTERIEURS
DU TUNNEL.
25 OCTOBRE 2022
PUITS  10: TRAVAUX POUR LA DIVISION DU BOUCLIER FRONTAL DU TBM EN PLUSIEURS
PARTIES.
PHASE 1: SÉPARATION DES DIFFÉRENTES PARTIES DU BOUCLIER, AVEC LE RETRAIT DES
GOUJONS, DES VIS ET DES COUPURES DANS LE BOUCLIER MÉTALLIQUE. RETRAIT DU
JOINT PÉRIMÉTRAL EN CAOUTCHOUC QUI GARANTIT L'ÉTANCHÉITÉ DU TBM.
PHASE 2: SEPARATION DANS LE LEVAGE DU VOUSSOIRS SUPERIEUR DU BOUCLIER ET LA
CHAMBRE HYPERBARE.
PHASE 3:.SEPARATION DANS LE LEVAGE DU VOUSSOIRS LATERAL DROIT.
PHASE 4: SEPARATION DANS LE LEVAGE DU VOUSSOIRS LATERAL GAUCHE.
PHASE 5: SEPARATION DANS LE LEVAGE DE L’ENTRAINEMENT PRINCIPAL OU MAIN
DRIVE, AVEC LES MOTOREDUCTEURS DU TUNNELIER.
PHASE 6: SEPARATION DANS LE LEVAGE DU VOUSSOIRS INFERIEUR.
PUITS 10: TRAVAUX POUR LA DIVISION DU BOUCLIER FRONTAL DU TBM EN PLUSIEURS
PARTIES. PHASE 1: SÉPARATION DES DIFFÉRENTES PARTIES DU BOUCLIER, AVEC LE
RETRAIT DES GOUJONS, DES VIS ET DES COUPURES DANS LE BOUCLIER MÉTALLIQUE.
RETRAIT DU JOINT
PÉRIMÉTRAL EN CAOUTCHOUC QUI GARANTIT L'ÉTANCHÉITÉ DU TBM.
TUNNEL TRONÇON 10: DEMONTAGE DE LA BANDE DU CONVOYEUR. DEMONTAGE PARTIEL DE LA
STRUCTURE METALLIQUE DU CONVOYEUR HORIZONTAL. DEMONTAGE PARTIEL DE LA PASSERELLE
PIETONNE. DEMONTAGE DES TUYAUTERIES AUXILIAIRES DE PETIT DIAMETRE. DEMONTAGE
PARTIEL DE LA CONDUITE DE VENTILATION. ACCUMULATION DE
GRANDE QUANTITE DE BOUES DANS LE TUNNEL.
TUNNEL TRONÇON 8: DEMONTAGE DE LA BANDE DU CONVOYEUR. DEMONTAGE PARTIEL DES
TUYAUTERIES DE PETIT DIAMETRE. DEMONTAGE PARTIEL DE LA PLATEFORME D’ACCES POUR LES
PIETONS. DEMONTAGE
PARTIEL DE LA CONDUITE DE VENTILATION.

STATION SMAIL YEFSAH: DÉMONTAGE DE LA BANDE DU CONVOYEUR. DÉMONTAGE DE CONDUITE


DE VENTILATION. TRAVAUX DE NETTOYAGE ET LE RETRAIT DES CÂBLES ÉLECTRIQUES DU
BOOSTER. PERSISTANCE DES
ZONES D´INFILTRATIONS D’EAU A TRAVERS LES JOINTS DE VOUSSOIRS.
TUNNEL TRONÇON 7 : DÉMONTAGE DE LA BANDE DU CONVOYEUR. DÉMONTAGE PARTIEL DE
CONDUITE DE VENTILATION. DÉBUT DU DÉMONTAGE DES INSTALLATIONS ÉLECTRIQUES.
ACCUMULATION D'EAU À L'INTÉRIEUR DU TUNNEL.FORTE ACCUMULATION DE DÉBLAIS DANS LA
COURBE EN RAISON DU DÉVERSEMENT DU CONVOYEUR HORIZONTAL.
TUNNEL TRONÇON 7: DÉMONTAGE DE LA BANDE DU CONVOYEUR. DÉMONTAGE PARTIEL DE
CONDUITE DE VENTILATION. DÉBUT DU DÉMONTAGE DES INSTALLATIONS ÉLECTRIQUES.
ACCUMULATION D'EAU À L'INTÉRIEUR DU TUNNEL.FORTE ACCUMULATION DE DÉBLAIS DANS LA
COURBE EN RAISON DU DÉVERSEMENT DU CONVOYEUR HORIZONTAL.
STATION RABIA TAHAR: DÉMONTAGE DE LA BANDE DU CONVOYEUR.
DÉMONTAGE DE LA CONDUITE DE VENTILATION. BLOCAGE DES ACCÈS AU TUNNEL EN RAISON DES
TRAVAUX SUR LA DALLE DE LA STATION.
TUNNEL TRONÇON 6: DÉMONTAGE DE LA BANDE DU CONVOYEUR. DÉMONTAGE PARTIEL DE LA
PASSERELLE PIETONNE. ACCUMULATION D’EAU
A L’INTERIEUR.
STATION USTHB: DÉMONTAGE DE LA BANDE DU CONVOYEUR. DÉMONTAGE DE LA CONDUITE DE
VENTILATION. BLOCAGE DE L’ACCÈS AU TUNNEL EN
RAISON DES TRAVAUX SUR LA DALLE DE LA STATION.
STATION USTHB: DÉMONTAGE DE LA BANDE DU CONVOYEUR. DÉMONTAGE DE LA CONDUITE DE
VENTILATION. BLOCAGE DE L’ACCÈS AU TUNNEL EN RAISON DES TRAVAUX SUR LA DALLE DE LA
STATION. RETRAIT DU BOOSTER
DE LA STATION.
TUNNEL TRONÇON 5: DÉMONTAGE DE LA BANDE DE CAOUTCHOUC DU CONVOYEUR, DÉMONTAGE
DE LA STRUCTURE MÉTALLIQUE DU CONVOYEUR, DÉMONTAGE DE LA CONDUITE DE VENTILATION.
DÉMONTAGE DES TUYAUTRIES AUXILIAIRES DE PETIT DIAMETRE TRÈS AVANCÉES, DÉMONTAGE
PARTIEL DES TUYAUTRIES AUXILIAIRES DE PLUS GRAND DIAMÈTRE. LES TRAVAUX DE RÉPARATION
DE LA PATHOLOGIE SONT A
L’ARRET.
STATION OUED SMAR: AUCUNE ACTIVITÉ.
26 OCTOBRE 2022
PUITS 10 : TRAVAUX POUR LA DIVISION DU BOUCLIER FRONTAL DU TBM EN PLUSIEURS PARTIES.
PHASE 1 : SÉPARATION DES DIFFÉRENTES PARTIES DU BOUCLIER, AVEC LE RETRAIT DES
GOUJONS, DES VIS ET DES COUPURES DANS LE BOUCLIER MÉTALLIQUE. RETRAIT DU
JOINT PÉRIMÉTRAL EN CAOUTCHOUC QUI GARANTIT L'ÉTANCHÉITÉ DU TBM.
DEPLACEMENT VERS LE CENTRE DU PUITS DU BOUCLIER AFIN DE FACILITER LES TRAVAUX
DE DIVISION ET DE LEVAGE AVEC L’AIDE DE 2 VERINS HYDRAULIQUE.
PHASE 2: SEPARATION DANS LE LEVAGE DU VOUSSOIRS SUPERIEUR DU BOUCLIER ET LA
CHAMBRE HYPERBARE.
PHASE 3:.SEPARATION DANS LE LEVAGE DU VOUSSOIRS LATERAL DROIT.
PHASE 4: SEPARATION DANS LE LEVAGE DU VOUSSOIRS LATERAL GAUCHE.
PHASE 5: SEPARATION DANS LE LEVAGE DE L’ENTRAINEMENT PRINCIPAL OU MAIN
DRIVE, AVEC LES MOTOREDUCTEURS DU TUNNELIER.
PHASE 6: SEPARATION DANS LE LEVAGE DU VOUSSOIRS INFERIEUR.

PUITS 10 : TRAVAUX POUR LA DIVISION DU BOUCLIER FRONTAL DU TBM EN PLUSIEURS PARTIES.


PHASE 1 : TRAVAUX POUR LE DEPLACEMENT VERS LE CENTRE DU PUITS DU BOUCLIER ET
FACILITER LES TRAVAUX DE DIVISION ET DE LEVAGE AVEC L’AIDE DE 2 VERINS HYDRAULIQUE ET
UNE CENTRALE
HYDRAULIQUE.
PUITS 10 : TRAVAUX POUR LA DIVISION DU BOUCLIER FRONTAL DU TBM EN PLUSIEURS PARTIES.
PHASE 1 : TRAVAUX POUR LE DEPLACEMENT VERS LE CENTRE DU PUITS DU BOUCLIER ET
FACILITER LES TRAVAUX DE DIVISION ET DE LEVAGE AVEC L’AIDE DE 2 VERINS HYDRAULIQUE ET
UNE CENTRALE
HYDRAULIQUE.
STATION OUED SMAR: AUCUNE ACTIVITÉ.
RAPPORT DE PRODUCTION DU TUNNEL PRINCIPAL.
5. FICHES DE CONTRÔLE
VAUX DE TUNNELIER REF/ Fin Février 2021 Mise à jour : 27-10-2022
Fin de référence1 Durée de Début Fin Durée prévisionnelle de Ecart - Date de fin de
référence1 fin référence1

16-May-2023 2054 01-jul-15 A 12-Jan-2024 2227 -172

16-May-2023 2054 01-jul-15 A 12-Jan-2024 2227 -172

11-Jul-2019 1226 01-jul-15 A 11-jul-19 A 1226 0


04-Apr-2023 858 21-déc-19 A 01-Dec-2023 1030 -172
04-Apr-2023 280 20-Dec-2022 01-Dec-2023 289 -201
04-Apr-2023 58 23-Sep-2023 01-Dec-2023 58 -201
06-fév-23 10 23-Sep-2023 03-Oct-2023 9 -200
29-Mar-2023 43 03-Oct-2023 24-Nov-2023 43 -200
04-Apr-2023 5 24-Nov-2023 01-Dec-2023 6 -201
10-Jan-2023 40 20-Jul-2023 05-Sep-2023 39 -198
27-Nov-2022 3 20-Jul-2023 23-Jul-2023 3 -198
06-Jan-2023 33 23-Jul-2023 01-Sep-2023 33 -198
10-Jan-2023 3 01-Sep-2023 05-Sep-2023 3 -198
08-Nov-2022 78 29-Mar-2023 02-Jul-2023 79 -196
13-aoû-22 5 29-Mar-2023 04-Apr-2023 5 -196
03-Nov-2022 69 04-Apr-2023 26-jui-23 69 -196
08-Nov-2022 5 26-jui-23 02-Jul-2023 5 -196
23-Jul-2022 67 20-Dec-2022 11-Mar-2023 68 -193
07-May-2022 3 20-Dec-2022 23-Dec-2022 3 -192
18-Jul-2022 60 23-Dec-2022 05-Mar-2023 60 -192
23-Jul-2022 5 05-Mar-2023 11-Mar-2023 5 -193
18-fév-22 565 21-déc-19 A 07-sep-22 A 708 -143
30-Sep-2020 203 21-déc-19 A 30-sep-20 A 203 0
19-Jan-2021 74 25-oct-20 A 19-jan-21 A 74 0
03-May-2021 78 13-fév-21 A 05-jui-21 A 96 -27
17-Jul-2021 40 30-jui-21 A 05-oct-21 A 69 -57
25-May-2021 4 30-jui-21 A 03-jul-21 A 3 -33
11-Jul-2021 39 04-jul-21 A 01-oct-21 A 77 -71
17-Jul-2021 5 02-sep-21 A 05-oct-21 A 28 -67
23-Nov-2021 96 28-oct-21 A 23-Mai-22 A 173 -150
12-aoû-21 10 28-oct-21 A 08-nov-21 A 9 -73
18-Nov-2021 82 07-nov-21 A 17-Mai-22 A 159 -149
23-Nov-2021 4 17-Mai-22 A 23-Mai-22 A 4 -150
18-fév-22 60 02-mar-22 A 07-sep-22 A 158 -167
19-Dec-2021 10 02-mar-22 A 29-jui-22 A 99 -160
13-fév-22 47 29-jui-22 A 05-sep-22 A 57 -170
18-fév-22 4 05-sep-22 A 07-sep-22 A 2 -167
04-May-2022 63 08-sep-22 A 20-Dec-2022 86 -192
04-Apr-2022 38 08-sep-22 A 20-Nov-2022 61 -192
04-May-2022 25 20-Nov-2022 20-Dec-2022 25 -192
16-May-2023 35 01-Dec-2023 12-Jan-2024 35 -201
16-May-2023 35 01-Dec-2023 12-Jan-2024 35 -201

RINCIPAL.
R INTERMEDIAIRE
NSTALLATION DE
LIQUES DES VERINS

BOUCLIER FRONTAL
E L´UNION ENTRE LE
AU MOYEN DE
ONS MÉTALLIQUES
BM EN 2 POUR SON
ÉDUIRE LE POIDS DE
BM EN 2 POUR SON
ÉDUIRE LE POIDS DE
GE DU TBM (FOSSE,
ÉMOLITION DE LA
NVOYEUR
TERIEURS
EN PLUSIEURS

LE RETRAIT DES
RETRAIT DU
BM.
BOUCLIER ET LA

.
HE.
IPAL OU MAIN
EN PLUSIEURS
UCLIER, AVEC LE
IER MÉTALLIQUE.
AGE PARTIEL DE LA
L DE LA PASSERELLE
TRE. DEMONTAGE
DE
TAGE PARTIEL DES
E D’ACCES POUR LES

NTAGE DE CONDUITE
LECTRIQUES DU

SSOIRS.
TAGE PARTIEL DE
S ÉLECTRIQUES.
E DÉBLAIS DANS LA
ONTAL.
TAGE PARTIEL DE
S ÉLECTRIQUES.
E DÉBLAIS DANS LA
ONTAL.
YEUR.
NNEL EN RAISON DES
AGE PARTIEL DE LA
DE LA CONDUITE DE
DE LA CONDUITE DE
UR LA DALLE DE LA
OYEUR, DÉMONTAGE
ITE DE VENTILATION.
CÉES, DÉMONTAGE
AUX DE RÉPARATION
LUSIEURS PARTIES.
LE RETRAIT DES
RETRAIT DU
TBM.
ITER LES TRAVAUX

BOUCLIER ET LA

.
HE.
IPAL OU MAIN

LUSIEURS PARTIES.
DU BOUCLIER ET
NS HYDRAULIQUE ET
LUSIEURS PARTIES.
DU BOUCLIER ET
NS HYDRAULIQUE ET
RINCIPAL.

Vous aimerez peut-être aussi