CONTRACT PRICE BREAKDOWN TENDER PRICE SUMMARY REALISATION EN EPC TRAIN 4 GPL ZCINA-HASSI MESSAOUD

REALISATION EN EPC D'UNE USINE DE DESSALEMENT DE L'EAU DE MER DE CAP-DJINET DE MIAH WAHRAN SPA
300 000 M3/J

ANNEXE III
DECOMPOSITION DU PRIX CONTRACTUEL
LEVEL - 1
MATRICE DE RESPONSABILITE
ITEMS DZD DWT DRO DEP DCM
I.0 MANAGEMENT DU PROJET 1,790,000,000 816,171,610 973,828,391 0 0

II.0 INGENIERIE 1,335,000,000 554,655,118 0 780,344,882 0

III.0 APPROVISIONNEMENT 31,900,000,000 31,900,000,000 0 0 0

IV.0 TRANSPORT 3,785,960,000 3,785,960,000 0 0 0

V.0 CONSTRUCTION 17,900,000,000 2,294,433,888 15,232,298,162 0 373,267,950

VI.0 ESSAIS ET MISE EN SERVICE 745,200,000 745,200,000 0 0 0

VII.0 DOCUMENTATION FINALE 19,440,000 9,720,000 0 9,720,000 0

VIII.0 ASSURANCE 291,590,000 291,590,000 0 0 0

PIECES DE RECHANGE, CONSOMMABLES ET PRODUITS


IX.0 CHIMIQUES 1,020,600,000 1,020,600,000 0 0 0

X.0 SPECIALISATION DU PERSONNEL DE MAITRE DE L'OUVRAGE 110,160,000 110,160,000 0 0 0

PRIX TOTAL EN HT 58,897,950,000 41,528,490,616 16,206,126,553 790,064,882 373,267,950

INVITATION TO TENDER PAGE 1 DE 14 Décomposition du Prix


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

I.0 MANAGEMENT DE PROJET

ITEMS DZD DWT DRO DEP DCM


1.1 MANAGEMENT DU PROJET DE L'ENTREPRENEUR (*) 1,720,062,285 761,963,938 958,098,348 0 0

Services de gestion du Projet à partir du siège 407,388,725 407,388,725

Contrôle du Projet 709,150,425 354,575,213 354,575,213

Prise en charge du personnel de Maitre de l'Ouvrage 603,523,135 603,523,135

1.2 SERVICES DE PROCUREMENT 38,477,629 38,477,629

1.3 SERVICES DE LA SOUS TRAITANCE 31,460,086 15,730,043 15,730,043

I.0 TOTAL MANAGEMENT DE PROJET 1,790,000,000 816,171,610 973,828,391 0 0

(*) Le management du Projet de l'Entrepreneur doit inclure ce qui suit :


Services de gestion du Projet à partir du siège
Contrôle du Projet
Toutes les inspections
Prise en charge du personnel de Maitre de l'Ouvrage
Autres ( à détailler par l'Entrepreneur s'il y a lieu)

INVITATION TO TENDER Page 2 de 14 I.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

II.0 INGENIERIE

ITEMS DZD DWT DRO DEP DCM


2.1 ETUDES 281,465,584 0 0 281,465,584 0
2.1.1 ETUDE TOPOGRAPHIQUE 31,800,000 31,800,000
2.1.2 ETUDE GEOTECHNIQUE 22,595,584 22,595,584
2.1.3 ETUDE BATHYMETRIQUE 227,070,000 227,070,000
2.2 INGENIERIE DE BASE 932,543,456 460,074,158 0 472,469,298 0
2.2.1 PROCESS 108,126,000 108,126,000
2.2.2 MECANIQUE 98,639,000 98,639,000
2.2.3 TUYAUTERIE 82,698,579 82,698,579
2.2.4 GENIE CIVIL 472,469,298 472,469,298
2.2.5 ELECTRICITE 82,698,579 82,698,579
2.2.6 INSTRUMENTATION & CONTRÔLE 55,312,000 55,312,000
2.2.7 TELECOMMUNICATION 18,100,000 18,100,000
2.2.8 HSE 14,500,000 14,500,000
2.3 DOCUMENTS COMME CONSTRUITS ( AS BUILT) 28,320,000 14,160,000 14,160,000
2.4 MANUELS/PROCEDURES DE GESTION DE PROJET/PLANS 92,670,960 80,420,960 0 12,250,000 0
2.4.1 Manuels 24,998,064 24,998,064
2.4.2 Procédures de gestion de projet 43,172,896 43,172,896
2.4.3 Plans 24,500,000 12,250,000 12,250,000
II.0 TOTAL INGENIERIE 1,335,000,000 554,655,118 0 780,344,882 0

N.B: La ventilation des prix doit se faire par discipline et par zone

INVITATION TO TENDER Page 3 de 14 II.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

III.0 APPROVISIONNEMENT

ITEMS DZD DWT DRO DEP DCM


3.1 ZONE 1 : CAPTAGE D'EAU DE MER 3,280,450,248 3,280,450,248 0 0 0
3.1.1 TOUR (S) DE CAPTAGE 19,575,000 19,575,000
3.1.2 CONDUITE (S) D'AMENEE 1,345,803,000 1,345,803,000
3.1.3 OUVRAGE DE RECEPTION 915,101,550 915,101,550
3.1.4 STATION DE POMPAGE D'EAU DE MER 845,092,878 845,092,878
3.1.5 SYSTÈME DE NETTOYAGE PIGGING SYSTEM 9,500,000 9,500,000
3.1.6 SERVICES AUXILIAIRES 145,377,820 145,377,820
3.2 ZONE 2 : PRE-TRAITEMENT 4,436,452,249 4,436,452,249 0 0 0
3.2.1 STATIONS DE DOSAGE DE REACTIFS CHIMIQUES 168,048,830 168,048,830
3.2.2 SYSTEME DE CLARIFICATION 1,328,326,525 1,328,326,525
3.2.3 FILTRES A SABLE (CAS DES FILTRES PRESSURISES) 1,584,551,102 1,584,551,102
3.2.4 STATION DE POMPAGE INTERMEDIAIRE (SI NECESSAIRE) 552,435,862 552,435,862
3.2.5 FILTRES A CARTOUCHES 319,277,963 319,277,963
3.2.6 SYSTÈME DE LAVAGE DES FILTRES A SABLE 159,231,392 159,231,392
3.2.7 SERVICES AUXILIAIRES 324,580,575 324,580,575
3.3 ZONE 3 : BATIMENT OSMOSE INVERSE 11,365,908,571 11,365,908,571 0 0 0
3.3.1 SYSTEME DE POMPAGE A HAUTE PRESSION 1,292,789,368 1,292,789,368
3.3.2 SYSTEME DE RECUPERATION D’ENERGIE 2,424,752,893 2,424,752,893
3.3.3 CHASSIS D’OSMOSE INVERSE 7,035,423,061 7,035,423,061
3.3.4 SYSTEME DE NETTOYAGE CHIMIQUE DES MEMBRANES (CIP) 115,026,143 115,026,143
3.3.5 SERVICES AUXILIAIRES 497,917,106 497,917,106
3.4 ZONE 4 : POSTE TRAITEMENT (REMENERALISATION) 1,109,296,990 1,109,296,990 0 0 0
3.4.1 SYSTÈME DE REMINÉRALISATION (LIT DE CALCITE / SYSTÈME DE DOSAGE DE CHAUX) 421,741,229 421,741,229
3.4.2 SYSTEME DE DOSAGE CHIMIQUE 15,600,000 15,600,000
3.4.3 SYSTEME DE STOCKAGE ET DE DOSAGE CO2 457,055,761 457,055,761
3.4.4 SERVICES AUXILIAIRES 214,900,000 214,900,000
3.5 ZONE 5 : LIVRAISON 1,061,387,206 1,061,387,206 0 0 0
3.5.1 RESERVOIR D’EAU POTABLE 9,787,500 9,787,500
3.5.2 POMPES DE LIVRAISON 745,861,918 745,861,918
3.5.3 DEBITMETRE COMMERCIAL 5,872,500 5,872,500
3.5.4 SYSTEME DE CHLORATION 19,575,000 19,575,000
3.5.5 SERVICES AUXILIAIRES 280,290,288 280,290,288
3.6 ZONE 6 : SOUS-STATION ELECTRIQUE (*) 7,595,534,195 7,595,534,195 0 0 0
1,648,727,473 1,648,727,473
662,723,761 662,723,761
1,258,905,834 1,258,905,834
172,954,716 172,954,716
2,236,019,168 2,236,019,168
468,755,673 468,755,673
96,983,971 96,983,971
942,703,812 942,703,812
107,759,787 107,759,787
3.7 ZONE 7 : BLOC ADMINISTRATIF & LABORATOIRE (*) 21,780,000 21,780,000
3.8 ZONE 8 : ATELIER ET MAGASIN (*) 19,800,000 19,800,000
3.9 AUTRES (*) 3,009,390,541 3,009,390,541 0 0 0
1,290,837,748 1,290,837,748
864,782,599 864,782,599
234,247,500 234,247,500
87,554,864 87,554,864
13,469,949 13,469,949
67,349,940 67,349,940
40,409,847 40,409,847
26,939,898 26,939,898

INVITATION TO TENDER Page 4 de 14 III.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

ITEMS DZD DWT DRO DEP DCM


241,900,000 241,900,000
141,898,196 141,898,196
III.0 TOTAL APPROVISIONNEMENT 31,900,000,000 31,900,000,000 0 0 0

(*) Le montant n'est pris en considération que si l'entrepreneur détaille cette rubrique
N.B: La ventilation des prix doit etre faite par équipement / matériel

INVITATION TO TENDER Page 5 de 14 III.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

IV.0 TRANSPORT (*)

ITEMS DZD DWT DRO DEP DCM


4.1 TRANSPORT INTERNATIONAL (EXWORK - PORT DE DÉCHARGEMENT) 785,160,000 785,160,000

4.2 DÉDOUANEMENT 2,090,000,000 2,090,000,000

4.3 TRANSPORT LOCAL ( PORT DE DÉCHARGEMENT - SITE) 910,800,000 910,800,000

IV.0 TOTAL TRANSPORT 3,785,960,000 3,785,960,000 0 0 0

INVITATION TO TENDER Page 6 de 14 IV.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

V.0 CONSTRUCTION

ITEMS DZD DWT DRO DEP DCM


5.1 ZONE 1 : CAPTAGE D'EAU DE MER 3,661,391,264 228,816,424 3,388,618,090 0 43,956,750
5.1.1 TRAVAUX DE GENIE CIVIL 3,294,136,340 0 3,294,136,340 0 0
5.1.1.1 TOUR (S) DE CAPTAGE 205,500,000 205,500,000
5.1.1.2 CONDUITE (S) D'AMENEE 2,161,470,861 2,161,470,861
5.1.1.3 OUVRAGE DE RECEPTION 656,510,886 656,510,886
5.1.1.4 STATION DE POMPAGE D'EAU DE MER 123,066,875 123,066,875
5.1.1.5 SYSTÈME DE NETTOYAGE PIGGING SYSTEM 147,587,718 147,587,718
5.1.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 72,484,174 72,484,174 0 0 0
5.1.2.1 TOUR (S) DE CAPTAGE 13,772,104 13,772,104
5.1.2.2 CONDUITE (S) D'AMENEE 21,008,295 21,008,295
5.1.2.3 OUVRAGE DE RECEPTION 10,870,959 10,870,959
5.1.2.4 STATION DE POMPAGE D'EAU DE MER 14,505,727 14,505,727
5.1.2.5 SYSTÈME DE NETTOYAGE PIGGING SYSTEM 12,327,089 12,327,089
5.1.3 ELECTRICITE 94,481,750 94,481,750
5.1.4 INSTRUMENTATION ET CONTRÔLE 20,210,000 20,210,000
5.1.5 CHARPENTE METALLIQUE 43,956,750 43,956,750
5.1.6 TUYAUTRIE / PIPELINE 131,575,000 131,575,000
5.1.7 TELECOMMUNICATION 4,547,250 4,547,250
5.2 ZONE 2 : PRE-TRAITEMENT 5,027,682,199 497,044,557 4,443,369,142 0 87,268,500
5.2.1 TRAVAUX DE GENIE CIVIL 4,285,062,142 0 4,285,062,142 0 0
5.2.1.1 STATIONS DE DOSAGE DE REACTIFS CHIMIQUES 34,437,427 34,437,427
5.2.1.2 SYSTEME DE CLARIFICATION 2,425,876,992 2,425,876,992
5.2.1.3 FILTRES A SABLE (CAS DES FILTRES PRESSURISES) 1,290,749,644 1,290,749,644
5.2.1.4 STATION DE POMPAGE INTERMEDIAIRE (SI NECESSAIRE) 170,443,468 170,443,468
5.2.1.5 FILTRES A CARTOUCHES 274,627,584 274,627,584
5.2.1.6 SYSTÈME DE LAVAGE DES FILTRES A SABLE 88,927,027 88,927,027
5.2.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 214,273,432 214,273,432 0 0 0
5.2.2.1 STATIONS DE DOSAGE DE REACTIFS CHIMIQUES 38,358,230 38,358,230
5.2.2.2 SYSTEME DE CLARIFICATION 29,330,730 29,330,730
5.2.2.3 FILTRES A SABLE (CAS DES FILTRES PRESSURISES) 78,930,101 78,930,101
5.2.2.4 STATION DE POMPAGE INTERMEDIAIRE (SI NECESSAIRE) 20,303,229 20,303,229
5.2.2.5 FILTRES A CARTOUCHES 24,799,685 24,799,685
5.2.2.6 SYSTÈME DE LAVAGE DES FILTRES A SABLE 22,551,457 22,551,457
5.2.3 ELECTRICITE 158,307,000 158,307,000
5.2.4 INSTRUMENTATION ET CONTRÔLE 34,588,125 34,588,125
5.2.5 CHARPENTE METALLIQUE 87,268,500 87,268,500
5.2.6 TUYAUTRIE / PIPELINE 239,669,000 239,669,000
5.2.7 TELECOMMUNICATION 8,514,000 8,514,000
5.3 ZONE 3 : BATIMENT OSMOSE INVERSE 2,246,755,502 727,789,104 1,396,158,398 0 122,808,000
5.3.1 TRAVAUX DE GENIE CIVIL 1,227,598,398 0 1,227,598,398 0 0
5.3.1.1 SYSTEME DE POMPAGE A HAUTE PRESSION 123,741,918 123,741,918
5.3.1.2 SYSTEME DE RECUPERATION D’ENERGIE 123,741,918 123,741,918
5.3.1.3 CHASSIS D’OSMOSE INVERSE 792,537,527 792,537,527

INVITATION TO TENDER Page 7 de 14 V.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

ITEMS DZD DWT DRO DEP DCM


5.3.1.4 SYSTEME DE NETTOYAGE CHIMIQUE DES MEMBRANES (CIP) 187,577,035 187,577,035
5.3.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 175,875,504 175,875,504 0 0 0
5.3.2.1 SYSTEME DE POMPAGE A HAUTE PRESSION 43,994,160 43,994,160
5.3.2.2 SYSTEME DE RECUPERATION D’ENERGIE 32,970,336 32,970,336
5.3.2.3 CHASSIS D’OSMOSE INVERSE 65,940,672 65,940,672
5.3.2.4 SYSTEME DE NETTOYAGE CHIMIQUE DES MEMBRANES (CIP) 32,970,336 32,970,336
5.3.3 ELECTRICITE 168,560,000 168,560,000
5.3.4 INSTRUMENTATION ET CONTRÔLE 48,641,600 48,641,600
5.3.5 CHARPENTE METALLIQUE 122,808,000 122,808,000
5.3.6 TUYAUTRIE / PIPELINE 491,232,000 491,232,000
5.3.7 TELECOMMUNICATION 12,040,000 12,040,000
5.4 ZONE 4 : POSTE TRAITEMENT (REMENERALISATION) 833,968,081 324,411,632 506,034,749 0 3,521,700
5.4.1 TRAVAUX DE GENIE CIVIL 498,572,099 0 498,572,099 0 0
5.4.1.1 SYSTÈME DE REMINÉRALISATION (LIT DE CALCITE / SYSTÈME DE DOSAGE DE CHAUX) 437,347,446 437,347,446
5.4.1.2 SYSTEME DE DOSAGE CHIMIQUE 25,975,606 25,975,606
5.4.1.3 SYSTEME DE STOCKAGE ET DE DOSAGE CO2 35,249,047 35,249,047
5.4.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 4,943,132 4,943,132 0 0 0
5.4.2.1 SYSTÈME DE REMINÉRALISATION (LIT DE CALCITE / SYSTÈME DE DOSAGE DE CHAUX) 2,472,040 2,472,040
5.4.2.2 SYSTEME DE DOSAGE CHIMIQUE 1,544,433 1,544,433
5.4.2.3 SYSTEME DE STOCKAGE ET DE DOSAGE CO2 926,659 926,659
5.4.3 ELECTRICITE 7,462,650 7,462,650
5.4.4 INSTRUMENTATION ET CONTRÔLE 2,850,900 2,850,900
5.4.5 CHARPENTE METALLIQUE 3,521,700 3,521,700
5.4.6 TUYAUTRIE / PIPELINE 315,862,950 315,862,950
5.4.7 TELECOMMUNICATION 754,650 754,650
5.5 ZONE 5 : LIVRAISON 1,229,027,671 181,031,671 1,026,453,000 0 21,543,000
5.5.1 TRAVAUX DE GENIE CIVIL 980,400,000 0 980,400,000 0 0
5.5.1.1 RESERVOIR D’EAU POTABLE 879,810,960 879,810,960
5.5.1.2 POMPES DE LIVRAISON 100,589,040 100,589,040
5.5.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 39,520,671 39,520,671 0 0 0
5.5.2.1 RESERVOIR D’EAU POTABLE 17,568,484 17,568,484
5.5.2.2 POMPES DE LIVRAISON 8,780,875 8,780,875
5.5.2.3 DEBITMETRE COMMERCIAL 4,390,437 4,390,437
5.5.2.4 SYSTEME DE CHLORATION 8,780,875 8,780,875
5.5.3 ELECTRICITE 46,053,000 46,053,000
5.5.4 INSTRUMENTATION ET CONTRÔLE 16,383,000 16,383,000
5.5.5 CHARPENTE METALLIQUE 21,543,000 21,543,000
5.5.6 TUYAUTRIE / PIPELINE 121,000,000 121,000,000
5.5.7 TELECOMMUNICATION 4,128,000 4,128,000
5.6 ZONE 6 : SOUS-STATION ELECTRIQUE 1,075,000,000 293,797,500 687,032,500 0 94,170,000
5.6.1 TRAVAUX DE GENIE CIVIL 414,735,000 414,735,000
5.6.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 247,250,000 247,250,000
5.6.3 ELECTRICITE 272,297,500 272,297,500
5.6.4 INSTRUMENTATION ET CONTRÔLE 37,195,000 37,195,000
5.6.5 CHARPENTE METALLIQUE 94,170,000 94,170,000
5.6.6 TELECOMMUNICATION 9,352,500 9,352,500

INVITATION TO TENDER Page 8 de 14 V.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

ITEMS DZD DWT DRO DEP DCM


5.7 ZONE 7 : BLOC ADMINISTRATIF & LABORATOIRE 215,000,000 13,373,000 201,627,000 0 0
5.7.1 TRAVAUX DE GENIE CIVIL 201,627,000 201,627,000
5.7.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 7,525,000 7,525,000
5.7.3 ELECTRICITE ET TELECOMMUNICATION 5,848,000 5,848,000
5.8 ZONE 8 : ATELIER ET MAGASIN (*) 107,500,000 8,170,000 99,330,000 0 0
5.8.1 TRAVAUX DE GENIE CIVIL 87,967,250 87,967,250
5.8.2 TRAVAUX DE MONTAGE ET INSTALLATION MECANIQUE 4,300,000 4,300,000
5.8.3 ELECTRICITE 11,362,750 11,362,750
5.8.4 CHARPENTE METALLIQUE 3,870,000 3,870,000
5.9 TERRASSEMENT,VRD,,,,,,,,, 2,085,277,900 2,085,277,900
5.10 INSTALATION DE CHANTIER 1,418,397,383 20,000,000 1,398,397,383 0 0
MOBILISATION 1,294,859,986 1,294,859,986
DEMOBILISATION 45,845,799 20,000,000 25,845,799
REMISE EN ETAT DES LIEUX 77,691,598 77,691,598
V.0 TOTAL CONSTRUCTION 17,900,000,000 2,294,433,888 15,232,298,162 0 373,267,950
(*) Le montant n'est pris en considération que si l'entrepreneur détaille cette rubrique

INVITATION TO TENDER Page 9 de 14 V.0


CONTRACT PRICE BREAKDOWN = REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

VI.0 ESSAIS & MISE EN SERVICE

ITEMS DZD DWT DRO DEP DCM


6.1 ESSAIS 447,120,000 447,120,000
6.2 MISE EN SERVICE 298,080,000 298,080,000

VI.0 TOTAL ESSAIS ET MISE EN SERVICE 745,200,000 745,200,000

INVITATION TO TENDER Page 10 de 14 VI.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

VII.0 DOCUMENTATION FINALE

ITEMS DZD DWT DRO DEP DCM


7.1 DOCUMENTATION FINALE 19,440,000 9,720,000.00 9,720,000.00

VII.0 TOTAL DOCUMENTATION FINALE 19,440,000 9,720,000 0 9,720,000 0

INVITATION TO TENDER Page 11 de 14 VII.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

VIII.0 ASSURANCES

ITEMS DZD DWT DRO DEP DCM


8.1 ASSURANCE TRC/TRM 0
8.2 ASSURANCE DECENALE 0

VIII.0 ###
TOTAL ASSURANCES 291,590,000 291,590,000

INVITATION TO TENDER Page 12 de 14 VIII.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

IX.0 PIECES DE RECHANGE, CONSOMMABLES ET PRODUITS CHIMIQUES

EQUIPMENT DESCRIPTION DZD

9.1 PIECES DE RECHANGE, CONSOMMABLES ET PRODUITS CHIMIQUES 0

9.1.1 [*] 0

9.1.2 [*] 0

9.1.3 [*] A RENSEIGNER PAR L'ENTREPRENEUR 0

9.1.4 [*] 0

9.1.5 [*] 0

9.1.6 [*] 0

9.1.7 [*] 0

9.1.8 [*] 0

9.1.9 [*] 0

IX.0 TOTAL PIECES DE RECHANGE, CONSOMMABLES ET PRODUITS CHIMIQUES 1,020,600,000

(*) COUT DE LA PIECE DE RECHANGES, CONSOMMABLES ET DES PRODUITS CHIMIQUES POUR L'EXPLOITATION
PENDANT 2 ANS RENDUS SITE

INVITATION TO TENDER Page 13 de 14 IX.0


CONTRACT PRICE BREAKDOWN REALISATION EN EPC TRAIN 4 GPL ZCINA HASSI MESSAOUD

X.0 SPECIALISATION DU PERSONNEL DE MAITRE DE L'OUVRAGE

ITEMS DZD
SPECIALISATION DU PERSONNEL DE MAITRE DE
10.1 L'OUVRAGE 0

10.1.1 [*] 0

10.1.2 [*] 0

10.1.3 [*] 0

10.1.4 [*] 0

10.1.5 [*] 0

10.1.6 [*] 0

10.1.7 [*] 0

[*] [*] 0

X.0
SPECIALISATION DU PERSONNEL DE MAITRE 110,160,000
DE L'OUVRAGE

INVITATION TO TENDER Page 14 de 14 X.0