TRAMWAY D’ORAN
« ES SENIA-GARE ROUTIERE SIDI MAAROUF » Marché N° 06/2008
HW Specification -
CLCXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXX
Maître d’Ouvrage Délégué: Maitre d’Oeuvre:
Le Titulaire:
2.1 Abreviations
2.2 Definitions
3 PRODUCT SPECIFICATION:
SUPPLIER DOCUMENT
Product release ID Code Rev File name Description
CLC V5 CONS-03 X302SXXSY041C Subsystem Application Conditions CLC This document, with reference to Central Logic Computer
(CLC), is issued to describe in detail the conditions and
constraints for the functional safety of the application as
envisaged in the subsystem Safety and V&V Plan. It
contains a functional description, application and
environmental conditions, SW and HW configuration,
description of the installation, uses and maintenance, a
diagnostic and decommissioning. Baseline BL_CLC-
10.2.5
SML400BS CONS-05 T-21 A406447 2A SUBSYSTEM APPLICATION The purpose of this document is to provide application
CONDITIONS SML400 BS conditions for the SML400BS Subsystem.
TRAMWAY D’ORAN
« ES SENIA-GARE ROUTIERE SIDI MAAROUF » Marché N°
There must be two separate power supply sections from the electrical cabinet,
one for the CLC N subsystem and one for the CLC R subsystem. Each power
supply section is connected to a specific multi-socket. The information displayed
is:
· The CLC internal switch does not require an overload switch if the power supply
is supplied by an electrical cabinet fitted with an overload switch. If this is not the
case then an overload switch must be installed.
· If the power supply available in the building where the CLC is installed does not
satisfy the requirements described above then a power supply cabinet satisfying
all the requirements and suitable to power the subsystem must be installed. In
GENERAL GE-001 this instance the cables coming from the electrical cabinet power supply panel Yes CONS-03
(ref. [13]). must be connected to the terminals located at the back of the CLC
cabinet.
· Installation and maintenance must be performed whilst the CLC N or R is
disconnected from the power supply to ensure the safety of the operator. It is not
enough to adjust the rear switch (front for V5 PBS) on each CLC N or R cabinet
or the cabinet multi-socket. Switch OFF the main switch, located on the power
supply panel, or disconnect the rack plugs from the multi-socket.
· External power supply source sizing must ensure a power supply of at least 500
VA for each individual rack.
The requirement must be guaranteed as part of system configuration design.
The Dallas chips (Ds2505) installed in the racks must have the following
characteristics:
- Fixed identification value to indicate whether the rack is for CLCN or CLCR.
- Local SID and constant values to enable calculation of the root for the Vital
Sequence Number Generator used by the FSFB/2 protocol (see Ref. [16]). This
configuration data is extracted from the HCF file generated by the SMARTCAA as
an input for the CLCCAA program which generates a Hex Intel file for the Dallas
GENERAL GE-010 Yes CONS-03
component which is loaded on the rack backplane using a special tool.
- Programmed in accordance with the procedures described in the document
entitled Configuration Boards Procedure (Ref. [15]). The procedures control
correct programming by comparing the program checksum with the one
envisaged for the system.
The requirement is guaranteed by internal ALSTOM procedures as well as
installation and maintenance procedures.
3.2.2 Installation:
DOCUMENT
Applicable
CATEGORY ID DESCRIPTION REFERENCE
to CIR
(ID baseline)
· You should ensure that the CLC sub-system earth is separate from the earth of
the other equipment outside the equipment-room and separate from the electrical
equipment earth.
INSTALLATION IN-001 Yes CONS-03
· The earth resistance MUST NOT be greater than 10 W. Preferably, the
resistance should not exceed 3 W.
This requirement must be ensured during installation.
The CLC cubicles must have earth bars. The equipment must be earthed by
connecting the rack structure to the earth bar. The earth bar must be connected
INSTALLATION IN-002 to the earth wire on the power supply cable and the power supply cable earth wire Yes CONS-03
cross-section must be at least 1 sq. mm.
This requirement must be ensured during installation.
· The internal CLC subsystem cable connections and system connections must
be correct.A description of the cable connections is shown in section 3 of the
installation manual [13] and in section 2.4.2 of the maintenance manual [19].·
INSTALLATION IN-003 Make sure that the connection between the CLC N and CLC R and the Yes CONS-03
connection for the device (plug) used to override alignment between N and R are
correct.
This requirement must be ensured during installation.
· The procedures described in section 3 of the installation manual [13] (first
connection) and section 2.4.2 of the maintenance manual [19] (corrective
INSTALLATION IN-004 intervention) must be followed. Amongst other things these procedures Yes CONS-03
unequivocally identify all the cables as well as the origin and destination
connectors.
As far as all the HDLC trunks in output from the CLC are concerned, the following
line terminations must be fitted for each serial channel:
§ ZNET trunk – (Ex: connection with ZLCs) Terminations – CLC side code
N687056860W, ZLC side code N687056863Z.
§ FNET trunk – (Ex: connection with MGRC chains)Terminations – CLC side code
N687056860W, MGRC side code N687056862Y.
INSTALLATION IN-010 Note:As far as the connections wiring diagram is concerned refer to the No CONS-03
maintenance manual [19]As far as the connection with the TFM-GW (ZNET
network) is concerned, an additional termination is not fitted on the TFM-GW side,
in that:
· Terminations are already fitted internally on the TFM-GW side.Only one TFM-
GW is fitted for the HDLC trunk.
This requirement must be ensured during the installation stage.
The FDB (N687056835U) and ZNET/FNET cables are shielded and the braiding
must only be connected to earth in a single point on the rack in the screw near
INSTALLATION IN-011 Yes CONS-03
the cable connection.
This requirement must be ensured during the installation stage.
3.2.3 Design:
The CLC subsystem must be powered by a 220Vac / 230Vac power supply with
the following characteristics to ensure correct functioning:
– Stationary variation less than -15% +10% .
– Dynamic variation less than +/- 10%.
– Frequency variation less than +/- 2%.
– Distortion less than 5%.
– Maximum interruption equal to 10 ms.
DESIGN DE-001 Yes CONS-03
– Variations to the peak value must be less than (Veff * Ö2) ±1.5%, where Veff is
the effective value measured on the 220V/230V power supply input suitable to
power Category II Overvoltage equipment (in accordance with IEC 60664�1 /
CEI 28-6) and class 3 installation equipment (in accordance with CEI EN 61000-
4-5; maximum overload 2 kVpk) or Category OV2 Overvoltage equipment (in
accordance with EN 50124-1; maximum overload 2.5 kVpk).
– Frequency equal to 50 Hz +/-2%.
The CLC uses the FSFB/2 protocol to ensure suitable countermeasures for the
transmission of data to other subsystems. Receiving subsystems must also use
the FSFB/2 protocol to ensure communication with the CVLC subsystem. The
DESIGN DE-003 Yes CONS-03
use of this communication protocol enables data transmission and prevents
unauthorised access.
The requirement must be guaranteed as part of system architecture configuration.
Refusal to use the input variables must be analysed carefully in that a false value
could mean that the input port which acquired the value is damaged (fault not
compromising safety). In this case a false state input variable could be used by
the logic to define a permissive action simply by combining, using an AND logic
DESIGN DE-007 Yes CONS-03
operation, the input variable with an enabling condition in the true state following
vital verification that the input port is functioning correctly .
This requirement must be guaranteed by the design process and system logic
validation (Interlocking Principles and Data Preparation).
The node SID allocated to each host must have unequivocal characteristics
based on the constraints described in “FSFB/2 PC SW Requirements
Specifications” Ref.[35] and is stored on the CLC Ss FLASH CARD.The
requirements that SMARTCAA must conform to for allocation of the numeric
values are described in the document “FSFB/2 PC SW Requirements
Specifications” Ref.[35]:
· FSFB/2- SWRS-Cnf 1 - CRC features
DESIGN DE-013 Yes CONS-03
· FSFB/2- SWRS-Cnf 2 - Number of nodes in a FSFB/2 network and related SID
· FSFB/2- SWRS-Cnf 3 – SID features
· FSFB/2- SWRS-Cnf 5 – Relation between values integrated in the transmission
CRCM
Conformity with the constraint is guaranteed by use of SMARTCAA. In systems
not using SMARTCAA, the constrains imposed by the application condition must
be respected.
The DATAVER is a configuration parameter for CLC for the FSFB/2 protocol with
specific characteristics and which is stored on the CLC Ss FLASH CARD.The
value of this parameter must be the same for the transmitting subsystem and the
receiving subsystem which dialogue using FSFB/2.As far as the value of
DATAVER for each node from which the CLC subsystem received vital data using
the FSFB/2 is concerned, SMARTCAA must define this 32-bit word which must
DESIGN DE-015 Yes CONS-03
be the same as the one set in the transmitting node. The details of this operation
are described in section 3.2.1 of the document entitled “FSFB/2 PC SW
Requirements Specifications” Ref.[35].
Conformity with the constraint is guaranteed by use of SMARTCAA. In systems
not using SMARTCAA, the constrains imposed by the application condition must
be respected.
The parameters defined in the HCF file host section have specific configuration
limits due to the current version of the CLC subsystem software. These limits
described in the document entitled “CLCCAA Configuration Files Specification”
DESIGN DE-016 (Ref. [28]) are shown in Table 2. Yes CONS-03
Conformity with the constraint is guaranteed by use of SMARTCAA. In systems
not using SMARTCAA, the constrains imposed by the application condition must
be respected.
The parameters defined in the [COM_MAIN] section of the CCF file have specific
configuration limits for the current version of the CLC subsystem software. The
values of the parameters are set automatically by the SMARTCAA system
configuration tool in accordance with the type of Specific Application under
consideration.These limits described in the document entitled “CLCCAA
Configuration Files Specification” (Ref. [28]) are shown in Table 4 below.Each
DESIGN DE-018 UDP channel which can be configured on CLC (in accordance with the Yes CONS-03
constraints described in Table 4) enables the following operating modes:
UNICAST, BROADCAST and MULTICAST.Each UDPRED channel which can be
configured on CLC (according to the values of Table 4) enables the following
operating modes: UNICAST and MULTICAST.The table below (Table 5) shows
the configurations permitted for the UDP and UDPRED protocol when the CLC Ss
communicates with other subsystems whether they are redundant or not.
There are some constraints on the maximum number of the CLC communication
channels. Precisely:
· 150 global communication channels
· 140 channels that use the UDP/IP protocol
DESIGN DE-031 Yes CONS-03
· 56 channels activated in multicast modality
· 5 channels that use the TCP protocol
· 10 HDLC starting up channels
Only constraints on the configuration of the CLC subsystem are identified.
There are some constraints on the BSD message length that it must make up of a
number of byte that is divisible by four.
DESIGN DE-032 Yes CONS-03
There are some constraints on the configuration of remote Ss that receive FSFB2
tristate stream
ZNET/FNET equipment with the same cycle time must be configured in the same
subnetwork. For example, it is not possible to configure, within an FNET sub-
DESIGN DE-033 network, MGRC subsystems with TC of 500 msecs and ZLC subsystems with the Yes CONS-03
same TC
The requirement must be guaranteed as part of system architecture configuration.
· The time between one polling operation and the next one towards the same
DESIGN DE-034 slave is equal to 220 ms if there are two or more slaves. If only one slave is No CONS-03
configured this time has a maximum value of 110 ms.
· At least two polling sessions towards the slaves are performed during the CLC
DESIGN DE-035 500 ms cycle. No CONS-03
Similarly for the FNET configuration:
· The time between one polling operation and the next one towards the same
DESIGN DE-036 slave is equal to 440 ms if there are two or more slaves. If only one slave is Yes CONS-03
configured this time has a maximum value of 440 ms.
The following must be taken into consideration to calculate the oversight cycles
for each individual receiving node.- time dynamics of communications (polling
cycles and sessions).- limit defined by worst case CLC transmission scenario
following failure of the subsystem in service and therefore the maximum distance
DESIGN DE-037 between 2 consecutive packages transmitted from CLC towards a node in any Yes CONS-03
network. This distance is equal to Twctx = 2 * TC = 1 s (worst case transmission
scenario following failure).The above condition must be suitable integrated with
the effects of the time required for transmission on the network and the cycle time
for the asynchronous receiving network.
The following must be taken into consideration to calculate the oversight cycles
for each individual receiving node.
· - time dynamics of communications (polling cycles and sessions).
· limit defined by worst case CLC transmission scenario following failure of the
subsystem in service and therefore the maximum distance between 2
DESIGN DE-060 consecutive packages transmitted from CLC towards a node in any network. This Yes CONS-05
distance is equal to Twctx = 2 * TC = 1 s (worst case transmission scenario
following failure).
· The above condition must be suitable integrated with the effects of the time
required for transmission on the network and the cycle time for the asynchronous
receiving network.
4 PROJECT SPECIFICATION:
4.1 Project requirements:
Req ID Text Allocation
ORAN_IXL_SyRSAD_0 Les normes CENELEC EN-50126 [DR5] 50128 [DR6] 50129 SIG, CLC,
007 [DR7] sont applicables à l'ensemble des équipements de SMIO, HWD,
signalisation ferroviaire. CAPS, AXLE,
BSEC, SIGN,
NS1,
ORAN_IXL_SyRSAD_0 La norme CEM de référence proposée est la EN50121 SIG, CLC,
008 [DR1], [DR2] et [DR3].SMIO, CAPS,
Les normes suivantes sont applicables à tous lesAXLE, BSEC,
équipements du système :SIGN, NS1,
· NF EN 50081-1 Compatibilité électromagnétique - Norme
générique émission-Partie 1 : résidentiel, commercial et
industrie légère.
· NF EN 50082-1 Compatibilité électromagnétique - Norme
générique immunité-
ORAN_IXL_SyRSAD_0 Equipements extérieurs : IP66SIG, HWD,
009 Equipements intérieurs : IP43CLC, SMIO,
Equipements embarqués : IP54 CAPS, AXLE,
BSEC, SIGN,
NS1,
ORAN_IXL_SyRSAD_0 L'enclenchement est conçu pour fonctionnerSIG, HWD,
021 correctement dans les conditions définies par la norme CLC, SMIO,
EN 50125-3 [DR4].CAPS, AXLE,
Toutes les parties de l'enclenchement doivent être BSEC, SIGN,
conformes à la catégorie Ax de la norme EN 50125-3 c'est NS1,
à dire:
· Altitude inférieure à 1400 mètres
· Equipements à la voie supportant une température
comprise entre -15°C et +40°C
· Equipements dans les locaux techniques supportant une
température comprise entre -5°C et +40°C. Les locaux
techniques où sont installées les armoires IXL doivent
être climatisées pour maintenir la température de
fonctionnement de celles-ci.
5 HARDWARE DESIGN:
5.1 Cabinet configuration
ELEMENT QUANTITY
CLC CUBICLE 1
Rack CLC N/R 2
CLCMAIN BOARD 2
CLCCOM BOARD 2
CLCMAIN T BOARD 2
CLCCOM T BOARD 2
CPCI POWER SUPPLY BOARD 2
CLC APNR Normal BOARD 1
CLC APNR Reserve BOARD 1
CLC MCV BOARD 2
DIAG BOARD 2
Alim VPC2 BOARD 2
IDE 1
FANS 6
SIDE PANEL 4TE 6U 42
Inside the cubicle, for power supply distribution there are two blocks with 6 terminals each, mounted on the
sides of the cubicle to the rear. The cables from the power supply panel (PA) and the sectioning panel (QSP)
are connected to these terminal blocks.
Each block is connected to a multi-socket on the same side of the cubicle. The multi-sockets have four sockets
each. The equipment inside the cubicle is connected to the multi-sockets. The multi-sockets have an ON/OFF
switch for switching the 220Vac o 230Vac power supply on and off.
5.4 Dimensions
The CLC cubicle has the following dimensions:
The cubicles containing the CLC sub-system racks are made from sheet steel and aluminium and have
removable panels to facilitate access to the components inside the cubicle. The removable panels also enable
assembly of a series of cubicles alongside each other