Vous êtes sur la page 1sur 7

PUBLISHED PAPER AWARD WINNER

Design and construction of


Nemiscau-1 Dam, the first
Asphalt Core Rockfill Dam
in North-America
Vlad Alicescu, P.Eng., M.Eng., MBA, Hydro-Québec, Canada
Jean Pierre Tournier, P.Eng., PhD, Hydro-Québec, Canada
Pierre Vannobel, P.Eng., M. Eng., SEBJ, Québec, Canada

ABSTRACT: RÉSUMÉ:
The concept of asphalt as a waterproofing Le concept de barrage avec un noyau en béton bitumineux
medium inside embankment dams was first comme élément d’étanchéité a été développé en Allemagne au
developed in Germany in the 1960s. Since the début des années soixante. Par la suite, plus de 100 barrages de ce
first Asphalt Core Rockfill Dam (ACRD) was built, type ont été construits ou sont actuellement en construction. Tous
more than 100 dams have been completed or are les barrages en enrochement avec noyau en béton bitumineux ont
under construction. All these dams have an excel- une excellente et unique feuille de route, aucun problème de com-
lent record with no seepage problems or required portement ou besoin d’entretien n’étant signalés jusqu’à présent.
maintenance. Après avoir utilisé pour plus de 50 ans la moraine comme maté-
After using for more than 50 years the glacial riau d’étanchéité pour ses barrages en remblai, Hydro-Québec veut
till as waterproofing material for its embank- maintenant faire appel à de nouveaux concepts de barrage, pour
ment dams, Hydro-Québec is now looking for- les appliquer dans les régions où les matériaux naturels imper-
ward to develop new dam concepts, mainly for méables sont déficitaires. Pour ce faire, Hydro-Québec a pris la
the zones where natural waterproofing materials décision de construire un barrage prototype en enrochement avec
do not exist. In order to do so, Hydro-Québec has noyau en béton bitumineux et c’est le barrage de la Nemiscau-1,
decided to design and construct the Nemiscau-1 un des ouvrages de retenue de l’Aménagement hydroélectrique
Dam as a prototype Asphalt Concrete Core Rockfi ll Eastmain-1-A-Sarcelle-Rupert qui a été choisi à cet effet. Les cri-
Dam. Being one of the retaining structures of the tères de conception de ce barrage de 15 m de haut reflètent bien
Eastmain-1-A-Sarcelle-Rupert Diversion project, les pratiques et l’expérience acquises par Hydro-Québec suite à la
situated in the North of Quebec, the design of this construction de nombreux ouvrages de retenue, qui ont enregistré
15 m high dam follows the experiences and stan- un comportement très satisfaisant en exploitation. Les conditions
dards of many constructed Hydro-Quebec dams géologiques du site, ainsi que les matériaux de construction dis-
that have a very good record. The given dam site, ponibles sur place sont favorables pour la réalisation d’un barrage
geology and materials are well suited for a dam de ce type. En tenant compte que la charge hydraulique effective
with an asphalt core. The chosen core thickness of est de 7,6 m, le choix d’une épaisseur du noyau de seulement 400
minimum 400 mm is appropriate, given the small mm est justifiée. L’article présente les critères détaillés de concep-
net water head of 7.6 metres. The paper will present tion adoptés, les clauses techniques particulières pour la construc-
the detailed design criteria, technical specifications tion du noyau en béton bitumineux et des zones de transition
and finally, some information concerning the con- et finalement, certaines informations concernant la construction
struction of the dam. du barrage.

6 Winter 2010
1. Introduction 3. Design and construction of
Through the design and construc- Nemiscau-1 Dam, the first
tion of the Nemiscau-1 Dam, Hydro- ACRD in North-America 3.3 Design criteria
Québec wanted to gain experience Given the small net water head of
with asphalt concrete core con- 3.1 General design 7.6 m, a core thickness of 400 mm
struction, before proceeding with considerations is considered to be very appropriate
the final design and construction of The dam is located in a tail bay for the dam. Internationally, several
the much larger dams or dykes for with many rock outcrops in the vicin- dams have been constructed using
the La Romaine Complex. Hydro- ity of the axis. The geology of the dam 400 mm as width of the asphalt con-
Quebec has extensive and success- site consists of Precambrian rocks, crete core and the experience with
ful experience with the design and generally massive, with high strength. these dams is excellent.
construction of earth core rockfill Lower RQD’s were estimated in the The requirements to founda-
dams (ECRD) and wanted to use as upper 2 m mainly due to the stress tion preparation and plinth design
much as possible of that practice, relief joints and at some places, to are, in general, similar to those
with respect to types of materials, the weathering and infilling of those for a Concrete Faced Rockfill Dam
dam zoning, compaction proced- joints. Several shear zones were iden- (CFRD), but the plinth and the con-
ures, upstream slopes related to the tified and treated after the excavation nection to the impervious element is
riprap design, yet adapt the design of the overburden. The water pressure much simpler. The main purpose of
to the special features and require- tests showed, in general, low perme- the plinth is to serve as a grouting
ments of the Asphalt Core Rockfill abilities and the grout consumption cap to ensure high quality grouting
Dam (ACRD) concept. was low to moderate, with some local to the base and as a horizontal sur-
exceptions. face for placing the first layer of the
2. The Asphalt Core On the abutments, the loose to asphalt core and transitions zones,
Rockfill Dam (ACRD), dense overburden of glacial till (silty 2B. The concrete reinforcement is
a safe and cost effective sand and gravel, cobbles and boul- primarily used to reduce shrinkage
choice ders) is 0 to 2 m, locally exceeding cracking. The steel reinforcement
Since the first Asphalt Core 5 m. On the bottom of the river, the and the bolts of the plinth were
Rockfill Dam was built more than overburden consists of sandy silt, silty structurally designed for a max-
45 years ago, some 100 dams have sand and locally of sand and gravel, imum grout pressure of 160 kPa.
been completed or are under con- with a density varying from very loose Minimum average calculated plinth
struction. All these dams have an to compact, a similar situation being thickness is 0.5 m and absolute min-
excellent record with no seepage noticed between the two branches of imum thickness is 0.4 m.
problems or required maintenance. the river. In this particular case, the longi-
Asphalt core embankment dams The main reservoir levels con- tudinal profile of the rock excavation
have proved to be an economical sidered for the design of the under the concrete plinth is designed
and very safe alternative to other Nemiscau-1 Dam are presented in to keep the inclination of the plinth
traditional designs. The dams have Table 1. in all locations less than 45º and the
been constructed under various angle change between adjacent plinth
climatic and foundation condi- 3.2 Characteristics of sections less than 30º.
tions. The flexible properties of the the dam On Figure 4 is presented the
asphalt make Asphalt Concrete Core The cross section of the dam is longitudinal profile of the plinth
dams especially suitable in earth- presented on Figure 1; the present with its cross sections.
quake areas. Furthermore, asphalt design has an upstream slope of 1.8H Asphalt mastic is applied at the
core construction is to some extent, : 1.0V (imposed by the design cri- interface between the concrete
independent of weather conditions. teria of the riprap) and a downstream plinth and the fi rst layer of asphalt
This concept has been proved to be slope of 1.45H : 1.0V, a crest width of core, into waterstop box outlets
cost efficient in both wet and cold 7.5 m and a free board of 3.0 m above and as a sealant into joints in the
areas. the Maximum Operating Level. plinth. The mastic must be liquid
The main characteristics of the enough to stick to any unevenness
dam as originally designed with on the concrete plinth, as well as
a theoretical rock profile and being stable enough to build the
respectively, with a modified axis specified thickness on steep sur-
adapted to the real rock longitud- faces. Mastic consists of bitumen,
inal profile, plotted according to aggregates and fi ller, and an appro-
the field collected data after the priate adhesion agent that secure
excavation of the overburden, are necessary bonding to the concrete
presented in Table 2.

Canadian Dam Association 7


plinth, previously sandblasted or Table 1: Main reservoir levels
green cut. Definition Level (m)
Minimum Operating Level 292.7
3.4 Asphalt mix design Minimum Inferior Protection Level (riprap) 293.0
The preliminary asphalt mix was
made and tested with a bitumen con- Maximum Operating Level 297.5
tent of 7.3%. Voids content (less than 2 Maximum Extreme Level 297.5
%) was calculated on laboratory sam- Minimum Downstream Level (Q=10 m3/s) 289.9
ples with the above mentioned bitu- Downstream Level (Q= 100 m3/s) ±291.4
men content after compaction with
2x30 blows as defi ned by the Marshall
method (ASTM D6926-04).
As a part of the asphalt mix design
process, the stress-strain strength
properties of the AC (asphalt concrete)
where documented through Triaxial
Tests, performed at an established
consultant laboratory, the Norwegian Figure 1: The Nemiscau-1 Dam, cross section
Geotechnical Institute. The tests were
Table 2: Characteristics of the Nemiscau-1 Dam
Original design with a Reviewed design and axis with the real
Nemiscau-1 Dam: Characteristics
theoretical rock profile longitudinal profile of the bedrock

Maximum Height (m) 15 15

Top of the dam (elevation - m) 300.5 300.5

Crest length (m) 316 336

Crest width (m) 7.5 7.5

Upstream slope (1.8 riprap); 1.6 H : 1.0 V (1.8 riprap); 1.6 H : 1.0 V

Downstream slope 1.45 H : 1.0 V 1.45 H : 1.0 V

Total rockfill volume (m3) – without cofferdams 50,000 49,350

Total concrete volume – slab (m3) 410 504

Total asphalt concrete volume (m3) 750 650


Rock excavations (m3) 1,750 535
Overburden excavations (m3) 17,500 19,000

The zoning of the Nemiscau-1 Dam and the compaction pattern are described in Table 3.

Table 3: Nemiscau-1 Dam: zoning and compaction


Zone Material Compaction

Asphalt concrete
3-4 passes, 0.5 to 1 tons vibratory roller (until void content <3%); layer
9-Core
thickness = 22.5 cm after compaction
(bitumen type PG52-34)
2B – Transition 3-4 passes, 1.5 to 2.5 tons vibratory roller; layer thickness = 22.5 cm
Well graded crushed gravel, max. 80 mm
zone after compaction

3B-Shoulder Well graded crushed rock max. 150 mm 4 passes, 10 to 15 tons vibratory roller; layer thickness= 45 cm

3C-Shoulder Well graded quarried max. 450 mm 4 passes, 10 to 15 tons vibratory roller; layer thickness = 90 cm

4B – Slope
protection Selected rockfill max. 900 mm, with max. 20%
4 passes, 10 to 15 tons vibratory roller; layer thickness = 90 cm
< 200 mm
(downstream)
4 – Riprap Selected rockfill min. 400 mm - max. 600 mm Placed with a backhoe

8 Winter 2010
performed at a temperature of Contractor must also build the dam the responsibility of the General
5ºC which corresponds to the embankment (zones 3B, 3C, 4, 4A, Contractor. The core and transi-
main temperature estimated in 4B and 5), with the exception of tion zones 2B shall never be more
the core; the confi ning stress was zones 9 (Asphalt Core, AC) and 2B than two layers above or lower than
equal to 0.5 MPa. The maximum (transition zones). the adjacent zones 3B. With a com-
deviator stress for the Nemiscau-1 He must furnish and deliver pacted layer thickness of the core
Dam tests was about 2.3 MPa. The material for transition zones 2B and transition zones of 225 mm,
ductility (horizontal plateau) of and natural sand and gravel 10 this means a maximum level dif-
the Nemiscau-1 Dam specimens mm to 100 mm as a half – fabri- ference of 450 mm between the
shows almost no strain softening cate for the production of aggre- core and transition zones 2B and
and loss of resistance after the gates for the asphaltic core to the respectively, the zone 3B.
maximum level was reached, and asphalt plant of the Specialized The machines and supplementary
excellent visco-elastic behaviour. Sub-Contractor. equipment for placing of the asphalt
The AC (asphalt concrete) mix His tasks consist also in pro- core (zone 9) and transition zones
must be in accordance with the viding the geodetic survey of the 2B were specially designed and con-
following requirements: center line of each layer of asphalt structed to meet the design specifica-
o Density (kg/m 3) : >2.3 (ASTM concrete and securing sufficient tions for this part of the dam. The
D2041-03a) access to and on the dam for the paving machine is capable of placing
o Voids content on laboratory Specialized Sub-Contractor. simultaneously the core and transi-
made Marshall specimens, The General Contractor is tion zones 2B in 225 mm high lay-
compacted with 30 blows on required to install the instru- ers (after compaction). The width of
each side (%) : < 2.0 (ASTM mentation in the dam and in the placed core material shall be 400 mm
D3203-05) foundation of the dam includ- and the width of transition zones 2B
o Permeability factor (cm/s) : < 1.0 ing, vibrating wire piezometers, shall be 1550 mm each.
x10 -8 (must be documented on thermistors in the core, surface Prior to starting any works on
2 samples with a void content monuments, metallic rod on top of the dam, the Specialized Sub-
< 3.0 % as a part of initial mix the asphaltic core and all associ- Contractor shall carry out a trial
design) ated cabling jointing equipment, section that proves the asphalt mix
o Marshall stability (N) : > 5000 terminal boxes, panels, readout
(ASTM D6927-05, LC 26-060) equipment as shown on contrac-
The aggregate size distribution tual drawings.
should satisfy the Fuller grada- The Specialized Sub-Contractor
tion curve improved with approxi- is responsible for the placing of a
mately 13 % of filler (see Figure 7). mastic layer between the concrete
The components weight adds up to slab and the AC core, the mixing
100%, before bitumen. and batching of the AC mix and
The aggregates shall comply he must place and compact the
with the specifications outlined in AC core; he must transport, place
Table 5, page 17. and compact the supporting transi-
tion zones 2B on each side of the
AC core and carry on trial mixes
3.4 General construction and quality assurance testing for
of the dam the AC.
The construction of Nemiscau-1 Conventional practice estab-
Dam implies a General Contractor lished in Germany, Norway and
who is responsible for the construc- elsewhere was to place and com-
tion of the upstream and down- pact, on average, 2-3 layers of 200
stream cofferdams, the excavations, mm asphalt concrete per day. On
including overburden and rock Nemiscau-1 Dam, the layers have
excavation, the foundation clean- a thickness of 225 mm after com-
ing and treatment, the construction paction and 2 to 3 layers should
of the plinth, the grouting under- be placed each day. The asphalt
neath the dam, the removal of any core and the supporting transition
grouting spoils and the pumping/ zones must be built simultaneously
evacuating of any water from the in horizontal layers. This will be
surface before the beginning of the done in close coordination with the
of core construction. The General rest of the dam works, being under Figure 3: Rock excavation and plinth – details

Canadian Dam Association 9


Table 4: Testing the aggregates – tests, methods and requirements
Test Test method Requirements
Micro-Deval (MD), % LC 21-070* ≤ 25
Los Angeles (LA), % LC 21-400* (EN 1097-2) EN 1097-2 ≤ 35
Micro-Deval and Los Angeles MD+LA ≤ 70
Characteristics associated with the production of aggregates
Fragmentation, % LC 21-100** ≥ 20
Plate particles (grains), % LC 21-265** ≤ 25
Flakiness Index, % EN 933-3** ≤ 35
Elongated particles (grains), % LC 21-265** ≤ 45
N.B.: Plate and elongated particles must be tested on the grain size retained by the 10 mm sieve

*Standards of Quebec’s Ministry of Transportation; ** To be performed at mix design

Nemiscau-1 Dam site – Rock excavation and concrete plinth

Figure 4: Nemiscau-1 Dam – longitudinal section of the plinth

production and conformity, the con- compliance with the ASTM-D995- process is not within tolerance.
struction methods, machinery and 95b, 2002). The plant automatic- Mixes that are outside tolerance
personnel. Further, the trial shall ally loads and batches the correct will be rejected from the plant and
be used to establish the compaction weight for each constituent, with will not be used on the perma-
methods and compaction routine, a computer printout showing the nent works. Temperature gauges
and to prove that all machinery is weight of each constituent and are continuously monitoring the
fully operational and the personnel temperature of each batch. The temperatures in the hot storage
master their various duties. automatic control alerts the oper- aggregate bins, of the bitumen
The asphalt concrete mixing ator if the weight of any constitu- and of the final mix.
plant is a modern, automatic- ent is outside preset limits for the Mixing temperatures for the
ally controlled batch plant (in temperature or if any part of the asphalt with bitumen PG52-34

10 Winter 2010
must respect the mixing temper-
ature shown on the certificates Plan (QP) including Working
proving the compliance with the Procedures, where production,
technical specifications of the stan- transport and placement are
dard 4101 of Quebec’s Ministry of described, with special empha-
Transportation. sis on Quality Assurance. The
The asphalt concrete will be Specialized Sub-Contractor will
analysed continuously during pro- supply and operate a fully equipped
duction and aggregate compos- Site Testing Laboratory which
ition will not deviate beyond the includes equipment required for
tolerances specified in Table 5. routine testing of samples taken
Bitumen content must be within from the batch plant and the core,
± 0.3 % of that specified on the and equipment for drilling of “in
approved mix design which, as situ” cores/samples and testing for Figure 7: Aggregates for the asphalt concrete mix – grain size
mentioned on section 3.4, is 7.3%. voids content. distribution
Compaction of the core and The quality control program
the two transition zones 2B will and tests are summarized in be optimized, with an optimum bal-
be executed using three vibra- Table 5. (page 17) ance between the rock excavation,
tory rollers. The AC core will be the volume and shape of the con-
compacted by a vibratory roller 4. Conclusion crete plinth and finally, the place-
spanning the core width, but no Through the design and con- ment of the asphalt core with the
more than 100 mm wider than struction of Nemiscau-1 Dam, the manual method. Several combina-
the core, with weight in the range first rockfill dam with an asphalt tions of these 3 elements must be
of 500 - 1000 kg. After compac- core in North America, Hydro- analyzed at the design stage and the
tion, the layer thickness will be Québec wanted to gain experience most cost effective one should be
equal to 225 mm. The Specialized with asphalt concrete core construc- applied on site.
Sub-Contractor must provide tion, before proceeding with the Given its self compaction proper-
an adequate number of passes, final design and construction of the ties, imperviousness, flexibility and
until the void content <3%. The dams or dykes for the La Romaine ductile behaviour, the asphalt mix
AC must be compacted at a tem- Complex. The construction of the designed for the Nemiscau-1 Dam,
perature of approximately 130ºC Nemiscau-1 Dam started in May, with an average bitumen content of
– 150ºC, before the temperature 2008 and will be completed by 7.3 %, could be an interesting option
drops 14°C below the mixing tem- September, 2008. for the construction of the dikes of
perature shown on the certificate The first lesson learned from the La Romaine 2 facility and possibly,
of compliance of the bitumen. construction of this dam was that for other retaining structures of
The Specialized Sub-Contractor the longitudinal profile of the rock the Complex. ■
will present a formal Quality excavation and concrete plinth must

Construction of Nemiscau-1 Dam – The Asphalt Concrete (batch) plant

Canadian Dam Association 11


Table 5: Testing of Materials and Asphalt Core – Synthesis Table
Test Frequency
o Quality certificate at delivery

o Control tests of standard properties Delivery

o Density
o Grading curves Weekly

o Los Angeles and Micro Deval values for the aggregates


At mix design and when
o Water absorption in aggregates there is a change in the
source of material
o Adhesion to bitumen

On four Marshall specimens (ASTM D 1559-82):

o Bitumen content

o Aggregate size distribution


Daily, for each layer
o Bulk density

o Maximum specific gravity

o Voids content
Three core specimens of AC (one tested by the Specialized Sub-contractor in his laboratory,
another sent to a laboratory chosen by S.E.B.J. and the third one as a reserve):

o Density
One per week in the
o Voids content in the core first two weeks and if
satisfactory,
o Water absorption Monthly

o Marshall stability (N)

o Bitumen content
One measure for each layer Daily

Nucleodensimeter apparatus or other non – destructive method Daily, two per 1 layer

Measurement after compaction Per 1 layer


1 per week for the first
o Grading curves (LC-21-040) two weeks and then, if
o Density, min. and max. (vibrating table, CAN/BNQ 2501-058) satisfactory, monthly

12 Winter 2010

Vous aimerez peut-être aussi