Académique Documents
Professionnel Documents
Culture Documents
Summary Sommaire
The use of friction piles in compensated foundations appears to L’emploi des pieux à frottement dans les fondations compensées
open a new horizon for design in places like Mexico City where very ouvre un nouvel horizon dans le dessin des fondations pour des
highly compressible clay deposits are encountered. régions comme la Cité de Mexico, où l’on trouve une argile très
The author describes the design and performance o f such a founda- compressible. L’auteur rend compte des résultats obtenus avec une
tion at a site where the clay deposits assume a very high compressi- fondation compensée, avec des pieux à frottement, en un point de la
bility compared with other places in the city. Cité de Mexico, où les dépôts d’argile assurent au sol une plus grande
Settlement observations and subsoil investigations revealed the compressibilité qu’en d’autres emplacements dans la Cité. L’obser
behaviour of the friction piles used in the building. The settlement vation des tassements et les recherches sur le sous-sol ont permis de
was much smaller compared with settlement estimâtes for the same connaître le comportement des pieux à frottement sous l’édifice et ont
building but without piles. A great economy was achieved because montré que les tassements obtenus étaient considérablement réduits
the friction piles carried only a fraction o f the total load of the comparés aux estimations pour l’édifice sans pieux à frottement.
building. Furthermore, since the piles were designed without Une grande économie fût obtenue grâce à ces pieux qui ont sup
support from deep strata, the undesirable feature of the sidewalk porté seulement une fraction de la charge de l’édifice.
settling away from the building, on account of the well known ground D e plus, les pieux n’étant pas appuyés sur les couches les plus
surface subsidence of Mexico City, was eliminated. profondes, on élimine le problème difficile du tassement relatif entre
l’édifice el la surface du sous-sol dû à l’affaissement superficiel bien
connu dans la Cité de Mexico.
The building ‘La A zteca ’ with a total weight o f 1-2 kg/cm 2 sation load available at 6 m depth is 5790 ton, and therefore the
was constructed in a part o f M exico City where the clay deposits piles were assumed to take a load o f 2160 ton or the équivalent
are very highly compressible. o f 26-0 ton per pile. The foundation area and the pile layout
Subsoil investigations show ed that at this particular site the are show n in Fig. 7.
first hard stratum at a depth o f 32 m, used in the heart o f the Computed and observed settlements are compared in Fig. 9.
city to support point-bearing piles, was absent. It was found The observed settlement resulted in about one-half o f the
that the only possible level to support piles was on a firm sand estimated settlement that w ould have taken place if the same
stratum encountered at 42 m depth. H owever, this idea was foundation had been designed w ithout friction piles. The
abandoned because o f the high cost o f the piles, which had to be computed settlement for the com pensated friction pile founda
designed n ot only to carry the total weight o f the building but tion is o f the same order o f magnitude and trend as the observed
also the large negative friction induced by the ground surface settlement.
subsidence. This paper discusses also the probable behaviour o f the fric
The piles to reach 42 m depth had to penetrate ail the highly tion piles under the foundation structure in order to justify the
compressible clay deposits w hich are strongly affected by the working hypothesis that has been used in the design.
réduction in the piezom etric levels. The ground surface sub
sidence caused by the com pression o f these deposits is very Subsoil Characteristics
large; therefore difficult problem s could be created in the public The site is located in the lacustrine area occupied by the
utilities entering the building (Z eevaert, 1952a). western central part o f M exico City. This location is known
A totally com pensated foundation, on the other hand, was particularly by the very high compressibility o f its subsoil, since
also undesirable because costly spécial précautions would need many buildings up to six storeys high o n fully-com pensated
to be taken to m ake a deep excavation in the soft clay. A large foundations have suffered large settlements. The subsoil pro
heave would be obtained (Z eevaert, 1955) and the re-com- file is show n in Fig. 1. The typical lacustrine sériés o f deposits
pression would be very large because o f the very high com- o f volcanic clay with a high water content start at 6 m and extend
pressibility o f the clay. to 40-5 m depth, and are underlain by a sériés o f alluvial deposits
Finally, the author decided to recomm end a compensated o f fine andesitic gravel, sand and clayey silt that follow to greater
friction pile foundation which, according to soil mechanics depth, Tarango Sand II (Z eevaert, 1953 a, b, c).
computations, gave an acceptable settlem ent. The weight o f The lacustrine volcanic clay deposits are interbedded with
the building was balanced partly by an excavation 6 m deep, thin fine sand and silt stratifications. Specially significant for
and partly by 83 concrete friction piles 40 cm diameter driven settlement analysis (Z eevaert, 1951) are those marked clearly
a depth o f 24 m. in the soil profile (Fig. 1). The first thick soft clay deposit,
The total weight o f the building is 7950 ton. The compen- Tacubaya I to V, exhibits a very high water content that in
81
W ATE R C O N T E N T UNCONFINEDl som e places is well above 400 per cent. The second semi-rigid
IN % O F D R Y COMPRES5IVE! clay deposit, Tarango Clay I, show s an average water content
CLA55FICATI0N
W E IG H T O F 50LID 5 STRENGTH Kg/ o f about 175 per cent and is correspondingly less compressible.
100 ZOO 500 400 LO Ü JS d O W I
It should be noticed that at the contact horizon at 31-5 m
depth, between first and second clay deposits, the typical
Tarango Sand I alluvial deposit know n as the first hard for
m ation is absent. M ost o f the point-bearing piles for buildings
SUT &F1NE S^KiD / in the heart o f the city rest on this form ation.
WITU LlTTLt CLW, ; T o find out the source o f ground surface subsidence in this
caub: ;
c m c iu m
area piezom eters were installed in the pervious strata at depths
AMD RCOT-WOLES •
42, 37, 28, 22, 14 and 8 m respectively. It was found (F ig. 1)
olive - geêen ;
BROWN AND
REDDI5H BROWN
that there is practically no drop in piezom etric level from the
SAN D f ground surface to a depth o f 28 m, where a water-bearing
BROWN stratum o f silt and fine sand o f m icroscopic shells is encountered.
reddm brcwj
The vertical effective pressure in the subsoil has remained
BROW N practically unchanged up to this depth. H ow ever, from 28 to
REDOlJrt BROWN L
YELLOfcfl B R O W ff
GREY Pressure 'p' kg /cm 2
ÇREY 5 IL T
OLIVE BROW
O LIVE G R E E N [
BROW N
17
— ' g 2-56
G R EY
<->RfIEDMH BROWN
O L IV E
GREEN u g I-
G R EEN
5 tND 1
DARK BROWN
WITU
82
the friction piles to be used in the foundation design. U n- sponding tendency for expansion o f the clay mass in the vertical
disturbed clay sam ples close to the shafts o f piles driven in other direction. U p on dissipation o f the excess pore water pressure,
parts o f the city were recovered in open-pit excavations, the the vertical effective pressure assumes its initial value. There-
piles investigated having been driven for several months. From fore, no appréciable consolidation o f the clay takes place under
the results o f tests (Fig. 3) made o n the clay samples and field these circumstances, except very close to the pile shaft where a
observations o f the clay close to the pile shaft, the following thin layer o f remoulded clay consolidâtes because o f com plété
conclusions were drawn: structural breakdown.
(a) A thin skin o f perfectly remoulded and Consolidated clay (c) The natural shearing strength o f the clay, approximately
was observed close to the pile shaft that did not exceed 5 per 0-5qu, is affected by pile driving to about a distance o f one dia
cent o f the diameter o f the pile, thus giving rise to shearing meter away from the pile shaft. Close to the pile shaft the
strengths (Fig. 4) according to the équation: shearing strength o f the clay is reduced to about 60 per cent
S $ = 0 -5 3 .K 0p u ...•(!) (Fig. 3b). H ence shearing will develop in the semi-disturbed
clay at a distance o f about 1-1 r from the centre o f the pile with
"1 a shear strength o f approximately :
•-T<J / q S c = 0-3qu . . . . (2)
V /
«.— +— +- ' \
V > ~ - + --- --------
T o investigate the total shearing résistance at which a friction
pile starts to yield it is necessary to investigate the minimum
values o f the shearing strength by m eans o f both form ulae 1
<a) and 2.
An analysis o f the shearing strength per unit length o f a
concrete pile 40 cm in diameter, using both concepts 1 and 2,
-
was made and is show n in Fig. 5. The average values o f qu
. * * 4- for each clay layer to a depth o f 27 m are also show n in Fig. 5.
J- ® •
X
+ X xt In this particular case the minimum shearing strength is
V '" • X • obtained with a com bination o f the concepts expressed in
* +
• formulae 1 and 2. After intégration between 2 and 24 m
p * • depth (/i) a total force (F ) o f 55 ton was obtained for the
ultimate load necessary to mobilize the total shearing strength
o f the soil along the shaft o f the pile. Because o f the highly
compressible clay the point résistance does not play an im
(b) portant part until a rather large seulem ent o f the pile has taken
place and the shearing strength along the shaft has been alm ost
0 0-5 10 1-5 20 25
Dislance from p ile / diameter o f pile entirely mobilized.
T wo pile tests were made with 40 cm diameter concrete
Fig. 3 Shearing strength of disturbed clay close to pile shaft
Résistance au cisaillement de l’argile remaniée près du fût section-piles pushed slowly with jacks from 2 to 24 m depth.
du pieu The results o f the tests are reported in Fig. 6. L oading test
N o . 1 was made 28 days after the pile was pushed. T he
where K 0 = 0-75 is the ratio o f horizontal to vertical effective duration o f the test was 6 days, and this permitted maximum
pressure (Zeevaert, 1953d). seulem ent o f the pile to occur for each incrément o f load.
(b) The water content (Fig. 3) close to the shaft o f the The maximum load reached was 100 ton. The next load in
pile remains unchanged showing that there is practically no crément was not sustained by the pile; the load dropped im -
consolidation o f the clay during pile driving or afterwards. mediately to 79 ton and a continuous seulem ent occurred under
This fact may be explained if it is considered that the excess this load. L oading test N o . 2 was m ade 20 days after the pile
pore water pressure induced during pile driving produces was pushed and the test occupied 3 days. A total load o f
momentarily a réduction in the effective pressures and a corre- 70 ton was sustained (Fig. 6a).
E 7-5
o
i
V Sign depth
en
• 20-60 p-133
-C + 6S7 p-134
x 1020 p-133
a 7-70 p-135
7/1r o
J0
y '
A
A
c/ Conc/-ele re remoulde i
Î0-5
"o + / X
.C
O
■te
'a
o
6o.
Q: Nbrmal stress kg/crr^
qu to n /m 2 ton/m
10 20 0 1 2 3 4 5 6 7
• • •• ■
\
\ À 0-5 1(Pc -Ap ÎXC +
• • 3 £
• ,• \
• •
• *• i \
\ Af
• • \ Le ■412 qu
••• •
\ A i
Cla • I \
10
11 l
11
1
• | * 33-7 \\
* 1
V 5 •• 11
• .r Clay l l
• i \
\
'. \
\
20
T t- Clay IL \
• i • \\
1
e
\\ ^ \
. ' !•* j
Cla f i s \ ■^Sr- (b)
25
• \ < cl ;
st No 1 < Test No 2
\
...i—
\è ±
Apexc - Relief due to excavation to drive piles «
Ap - Produced by loaded pile. Assum ed equal zéro for y
p ile test No.2 r ■—y
8-
Fig. 5 Variation o f friction résistance along pile shaft Q J j r
aJ £
Résistance du frottement le long du fût du pieu
J -& .
this locality. T est N o . 2, which may be considered as a quick
loading test for point résistance, m ay be interpreted using the
results so far explained in this paper. The total load o n the Pushiitg load ton
pile is equal to the sum o f the ultim ate frictional strength o f Fig. 6 Tests on friction piles
55 ton, plus the point résistance that at least under these Essais sur pieux de frottement
conditions was no smaller than 20 ton, thus giving a total load
o f 75 ton. This com puted load is surprisingly close to the
measured ultimate load o f Test N o . 2 (Fig. 6a). Table 1
Settlements Depth AH Ap As
m eo cm kg/cm2 cm
The proposed building after total com pensation produced a
net incrém ent o f pressure at 6 m depth o f 0-326 kg/cm 2. The 6-33 6-5
9-30 0-0714 710 0-665 33-75
total pressure, including this incrément o f stress, is given by the 8-34
16-70 10-1 0-0973 465 0-475 21-52
curve labelled A (Fig. 8). 19-10 6-6 0-113 160 0-40 7-22
T o reduce heave (Z eevaert, 1955) during excavation and 24 1 2 8-5 0-1275 470 0-32 19-20
subséquent settlem ent the author recomm ended a preliminary 29-30 7-3 0-1505 360 0-225 12-20
excavation to a depth o f 3 -5 m, corresponding to the depth o f 32-90 4-2 0-0481 460 0-18 3-98
37-20 4-91 0-0423 180 0-15 1-14
the basement. It was recomm ended that the subséquent 2-5 m 39-08 4-65 0-0408 220 0-13 1-17
o f excavation, in which the foundation structure was to be
placed, should be m ade in trenches backfilled with concrete, Total 100-18
and that subsequently the spaces excavated between the con
84
seulement obtained was o f the order o f 100 cm. This value is The very large seulem ent m entioned above favoured the
considered conservative since in sonne places the critical décision to use friction piles to take care o f the excess pressure
pressure was reached. A more précisé seulem ent analysis was o f 0-326 kg/cm 2. The 83 piles used were driven to a depth o f
made as a function o f tim e taking into account the construction 24 m into the clay deposit unaffected by the réduction o f
period and the secondary tim e effect using the seulem ent piezom etric pressures, thus assuring that in the future the
building would follow the ground surface subsidence instead o f
emerging above the ground surface.
The friction piles served only to reinforce the clay deposits
between 6 and 24 m depth, and also to reduce expansion during
excavation and re-com pression o f the highly com pressible clay
surrounding the piles. The excess load o f 0-326 kg/cm 2 pro-
duces a load o f 26-0 ton per pile. Under these circumstances
the block formed by the soil and the piles was assumed to act
as a unit, transmitting the excess pressure in a favourable way
to its base and on to the less compressible clay deposits.
The total stresses in the subsoil under this condition were
com puted by current m ethods and are given as curve labelled C
in Fig. 8. The net incrément o f pressure was used for seu le
ment com putations as given in Table 2. The total seulem ent
Depth AH Ap As
eo mv cm kg/cm2 cm
m
86