1. During testing, multiple defects were identified in a product, The project manager overseeing this product's development cao best use which tool to help
prioritize the problems?
A. Pareto diagram.
B. Control chart,
C. Variance analysis.
D. Order of magnitude estimate.
1. Lors d'un test, plusieurs dfauts ont t identifis sur un produit. De quels outils dispose le chef du projet qui supervise le dveloppement du produit afin de
prioriser les problmes?
A. Le diagramme de Pareto.
B.Le diagramme de contrle.
C. L'analyse des carts.
D. Une estimation de type ordre de grandeur.
2. Vou are the manager of an aircraft design projecr, A significant portion of this aircraft will be designed by a subcontracting firm, How will this affect your
communications management plan?
A. More formal verbal communication will be required.
B. Performance reports will be more detailed.
C. More forrnal written communication will be required.
D. Official communication channels will significantly increase.
2. Vous tes le chef d'un projet de conception d'un avion. Une partie significative de cet avion sera conue par une socit de sous-traitance, ./ Comment cela peut
affecter votre plan de management des communications?
A. Plus de communication verbale formelle sera exige.
B. Les rapports d'excution seront plus dtaills.
C. Plus de communication crite formelle sera exige.
D. Les canaux de communication officiels augmenteront significativement.
3. What officially creates the project?
A. The project initiation document.
B.The kickoff meeting.
C. The project charter.
D. The statement of work.
3. Qu'est-ce qui cre officiellement le projet?
A. Le document de dmarrage du projet.
B.La runion de dmarrage.
C. La charte de projet.
D. L'nonc des travaux.
4. Refer to the table. What is the critical path?
A. Start-A-B-C-I-Finish.
B.Start-A-B-H-I-Finish.
C. Start-D-E-H-I-Finish.
D. Start-F-G-I-Finish.
Task
Dependency
Duration
Start
None
Stad
Start
Stad
B,E
C,G,H
Finich
Page 1
Activit
Dpendance
Dure
Dbut
None
Dbut
Dbut
Dbut
B,E
C,G,H
Fin
Page 2
Page 3
20. You overhear a casual conversation between two team members in which one confides to the other sorne problems he is having in completing his part of the
project work. You realize that the work being discussed is on the project's critical path and that the information you overheard could mean a significant delay
for your project. What should you do?
A. Let the team member know that you heard his conversation and discuss the work problerns with him immediately.
B. Begin analyzing ways to compress the project schedule in anticipation of the potential delay.
C. Ask a third team member to get involved immediately and encourage the two other team rnembers to come to you with the delay.
D. Ask human resources for help in resolving the problem.
20. Vous surprenez une conversation informelle entre deux membres de l'quipe, l'un d'eux confie l'autre qu'il a du mal terminer sa partie du travail. Vous
ralisez que le travail en question est important pour le projet et pourrait signifier un retard significatif pour votre projet. Que
Page 4
'
~.
devriez-vous faire?
A. Faire savoir aux membres de l'quipe que vous les avez entendu et parler de ce problme avec la personne concerne immdiatement.
B. Commencer analyser des faons de compresser l'chancier en prvision du retard potentiel.
C. Demander un troisime membre de les aider immdiatement et encourager les deux autres venir vous voir pour parler du retard. D.
Demander aux ressources humaines de l'aide afin de rsoudre le problme.
21. In which group of processes should the project manager be assigned his or her role in the project?
A. lnitiating.
B. Planning.
C. Executing.
D. Controlling.
21. Dans quel groupe de processus le chef de projet devrait-il tre assign?
A. Dmarrage.
B.Planification.
C. Excution.
D. Surveillance et matrise.
22. A project charter should always include:
A. Historica! information.
B.The business need underlying the project. C.
A detailed budget.
D. The scope management plan.
22. Une charte de projet doit toujours contenir:
A. Des informations historiques.
B.Le besoin d'affaire la base du projet. C.
Un budget dtaill.
D. Un plan de gestion du contenu.
23. Your project team has just received the sponsor's approval for the scope statement. What is the NEXT step that needs to be taken?
A. Develop the product description.
B.Create a work breakdown structure. C.
Hold the kickoff meeting.
D. Create the network diagram.
23. Votre quipe vient juste de recevoir l'approbation du sponsor pour l'nonc du contenu du projet. QueUe est l'tape SUIVANTE prendre en compte?
A. Dvelopper la description de produit.
B.Crer une structure de dcoupage du projet. C.
Tenir la runion de dmarrage du projet.
D. Crer un diagramme de rseau.
Page 5
B. La charte de projet.
C. Le plan de gestion de points. D.
Le rapport de points de projet.
27. The process in which project deliverables are reviewed and accepted is called:
A. Scope planning.
B.Scope verification.
C. Initiation.
D. Scope change control.
27. Le processus dans lequel les lments fournir sont passs en revue et accept, est appel:
A. Planification du contenu.
B.Vrification du contenu.
C. Initiation.
D. Commande de changement de contenu.
28. A statement of work is:
A. A type of contract,
B.A description of the project's product.
C. Necessary for every project,
D. A description of the part of a product to be obtained from an outside vend or.
28. Un nonc des travaux est:
A. Un type de contrat.
B.Une description du produit de projet.
C. Ncessaire pour chaque projet.
D. Une description d'une partie d'un produit obtenir d'un fournisseur extrieur.
29. A commercial real-estate developer is planning to build a new office complex. He contacts with a construction firm to build one of the buildings for the actual cost of
providing the materials and services plus a fixed fee for profit. What type of contract does this scenario represent?
A. Independent vend or.
B. Fixed priee.
C. Cost-reirnbursable,
D. Time and rnaterials.
29. Un promoteur immobilier planifie de construire un nouveau complexe de bureaux. Il contacte une socit de construction pour construire un des btiments pour le
cot rel des matriaux et des services plus les honoraires fixes pour le bnfice. Quel type de contrat ce scnario reprsente-t-il?
A. Vendeur indpendant.
B. Prix fixe.
C. Cot remboursable.
D. Pices et main d'oeuvre.
30. You and your spouse both work for large companies in different industries. However, one day you learn that your company will be soliciting bids for a project and
your spouse's company intends to bid. Your spouse will not be involved in the bidding process or any of the work it might produce if won. What should you do?
A. Request to be transferred off the project.
B. Inform management of the situation.
C. Say nothing and go on with the bidding proeess.
D. Say nothing but set up a system of checks and balances to ensure that your team selects the contractor impartial1y.
30. Vous et votre conjoint(e) travaillez tous deux pour de grandes compagnies dans diffrents domaines. Cependant, un jour vous apprenez que votre compagnie
sollicitera des offres pour un projet la socit de votre conjoint(e). Votre conjoint(e) ne sera pas impliqu(e) dans le processus ou dans tout autres travaux si cette
socit gagne. Que devriez-vous faire?
A. Demander ne pas faire partie du projet.
B.Informer la direction de la situation.
C. Ne rien dire et continuer le projet.
D. Ne rien dire et tablir un systme de contrle afin de vous assurer que votre quipe choisisse l'entrepreneur avec impartialit.
31. Which of the following is NOT a purpose that Create WBS serves?
A. To increase the accuracy of estirnates.
B. To help facilitate roles and responsibilities,
C. To document the relationship between the product business need.
D. To define a baseline for project performance.
31. Laquelle des rponses suivantes n'est PAS un objectif de crer la SDP?
A. Augmenter l'exactitude des valuations.
B. Aider faciliter les rles et les responsabilits.
C. Documenter la relation entre le besoin d'affaire de produit.
D. Dfinir une rfrence de base pour l'excution de projet.
32. You are assigned to replace a project manager on a large software project for a telecommunications company in the middle of executing the work, Portions of the
software are being supplied by subcontractors working at your company's offices. You would Iike to know what
Page 6
.'
performance metrics are going to be tracked for these contract workers, Where could you find such information?
A. The project charter,
B.The procurement management plan,
C. The work breakdown structure.
D. The organizationa! chart,
32. Vous tes dsign pour remplacer un chef de projet en plein milieu de la ralisation du travail, sur un grand projet logiciel pour une compagnie de
tlcommunications. Une partie du logiciel est fournie par des sous-traitants travaillant dans les bureaux de votre compagnie. Vous voudriez savoir quelle
mtrique de performance sera utilise pour ces sous-traitants. O pourriez-vous trouver une telle information?
A. La charte de projet.
B.Le plan de management des approvisionnements.
C. La structure de dcoupage du projet.
D. L'organigramme.
33. Which of me following is NOT a type of contract?
A. Cost-revisable.
B. Fixed-price.
C. Cost-reirnbursable.
D. Time and materials.
33. Laquelle des propositions n'est PAS un type de contrat?
A. Cot rvisable.
B. Prix fixe.
C. Cot remboursable.
D. Pices et main d'oeuvre
34. Your team has identified a component that they need for a project, There is sorne concern that they have never constructed a component like this one, but
there are similar components available from sellers, Which of the following procurement activities would be MOST appropriate to perform?
A. Solicitation.
B.Make-or-buy analysis.
C.
Benefit/
cost
analysis.
D.
Source
selection.
34. Votre quipe a identifi un composant dont ils ont besoin pour un projet. Le souci est qu'ils n'ont jamais conu un tel composant, mais des composants
similaires sont disponible sur le march. Quelle serait l'activit lie l'approvisionnement qui serait la mieux adapte?
A. Sollicitation.
B.Analyse produire ou acheter
C. Analyse avantages/cot.
D. Choix de la source.
35. The activity list serves as an input to:
A. Create WBS.
B. Activity Definition.
C. Activity Duration Estimating.
D. Resource Planning.
35. La liste des activits est une entre :
A. Crer la SDP.
B. L'identification des activits.
C. Estimation de la dure des activits.
D. La planification des ressources.
36. The pers on or group that formally accepts the project's product is:
A. The quality team.
B. The eus tomer.
C. The project tcarn.
D. Senior management.
36. La personne ou le groupe pouvant formellement accepter le produit du projet est:
A. L'quipe qualit.
B. Le client.
C. L'quipe de
projet. D. La
direction.
37. The schedule activity list:
A. Serves as an extension of the work breakdown structure.
B.Is synonymous with the work breakdown structure.
C. Is used to create the project scope statement.
D. Is inc1uded in the project charter.
37. La liste des activits de l'chancier:
A. Sert d'extension de la structure de dcoupage du projet.
B. Est synonyme de structure de dcoupage du projet.
C. Est utilis pour servir d'nonc du contenu du projet.
Page 7
39. Si le contenu du projet exige des marchandises ou services devant tre obtenus en dehors de l'organisation de projet. Quels processus de gestion seront utiliss
pour les obtenir?
A. Management des contrats.
B. Management des sollicitations du projet.
C. Management des approvisionnements du projet.
D. Management de l'externalisation du projet.
41. What is the most important function the project manager serves?
A. Staffing.
B. Motivating.
C. Team building.
D. Communicating.
41. Quelle est la plus importante fonction que doit faire un chef de projet?
A. Obtenir les ressources humaines.
B. Motiver.
C. Construire et assurer la cohsion de l'quipe.
D. Communiquer.
42. If a task has been estimated at 0 = 4 days, P = 9 days, and M = 7, what is the standard deviation?
A. 5/6 of a day.
B. 6.83 days.
C. 1/3 of a day.
D. 1/2 of a day.
42. Si une tche a t estime 0 = 4 jours, P = 9 jours et M = 7, quel est l'cart type?
A. 5/6 d'un jour.
B. 6.83 jours.
C. 1/3 d'un jour.
D. 1/2 d'un jour.
Page 8
.i
43. Refer to the table. If task H were increased from 3 to 7, what impact would this have on the project?
A. The project would finish later.
B.The project would finish earlier.
C. The schedule risk would decrease.
D Th
. . al
h
Id h
b
h fi . h date would not change.
e erme . pat wou
cange, ut t e 1ms
Task Dependency
Duration
Start
None
Start
Start
Start
B,E
C,G,H
Finich
43. Rfrez-vous sur le tableau de droite. Si la tche H tait augmente de 3 7, quel impact ceci aurait sur le projet?
A. Le projet serait en retard.
B. Le projet serait en avance.
C. Le risque de l'chancier diminuerait.
D Le chemin critique changerait mais la fin ne changerait pas
Tche
Dpendance
Dure
Dbut
None
Dbut
Dbut
Dbut
B,E
C,G,H
0
Fin
1
44. Ali of the foUowing are needed for creating the project budget except:
A. Activity cost estimates.
B.Work breakdown structure.
C. Project schedule.
D. Risk Register.
44. Tous les points suivants sont ncessaires pour crer un budget except:
A. Estimations des cots des activits.
B.Structure de dcoupage du projet.
C. Echancier du projet.
D. Registre des risques.
45. Your company's CIO has requested a meeting with you and two other project managers for a status update on four various projects. What is the BEST document you
can bring with you to this meeting:
A. The milestonc chart for this project.
B. The network diagram for this project.
C. Copies of the most reeent status reports from the team members.
D. The project charter.
45. Le CIO de votre compagnie a demand une runion avec vous et deux autres chefs de projet pour une mise jour de statut de quatre projets diffrents. Quel
est le MEILLEUR document que vous pourriez prendre avec vous pour cette runion?
A. Le diagramme des jalons pour ce projet.
B. Le diagramme de rseau pour ce projet.
C. Une copie des rapports d'avancement les plus rcents des membres des quipes.
D. La charte de projet.
Page 9
Page la
i.
52. Scatter diagrams, flowcharts, mn diagrams, control charts, and inspection are aU techniques of what quality process?
A. Quality Planning.
B. Perforrn Quality Control.
C. Perforrn Quality Execution.
D. Perforrn Quality Definition.
52. Les diagrammes de corrlations, les diagrammes de flux, les relevs d'observation, les diagrammes de contrle et l'inspection sont toutes des
techniques de quel processus de qualit?
A. Planification de qualit.
B. Mettre en oeuvre le contrle de qualit.
C. Mettre en oeuvre l'excution de qualit.
D. Dfinition de qualit.
53. Which of the following is NOT an input to quality planning?
A. Entreprise environnemental factors.
B. Organizational process assets,
C. Quality baseline.
D. Scope bascline.
53. Laquelle des propositions suivantes n'est PAS une entre de la planification de qualit?
A. Facteurs environnementaux de l'entreprise.
B. Actif organisationnel.
C. Rfrence de base de la qualit.
D. Rfrence de base du contenu
54. The procurement management plan provides:
A. Templates for con tracts to be used,
B. A formal description of how risks will be balanced within contracts.
C. A description of procurement options.
D. The types of contracts to be used for items being procured.
54. Le plan de management des approvisionnements fournit:
A. Des modles pour les contrats utiliser
B. Une description formelle de comment les risques seront quilibrs dans le contrat.
C. Une description des possibilits d'approvisionnement.
D. Les types de contrats utiliser.
55. Ultimately, responsibility for quality management lies with the:
A. Project team.
B. Quality team,
C. Project manager.
D. Functional manager.
55. La responsabilit ultime pour le management de la qualit revient :
A. l'quipe de projet.
B. l'quipe de qualit.
C. Au chef de projet.
D. Au directeur fonctionnel.
56. AU of the following are tools used in Perform Quality Control EXCEPT:
A. Benchmarking.
B. Pareto charts.
C. Histograms.
D. Statistical sarnpling.
56. Tout les outils suivants sont utiliss dans mettre en uvre le contrle qualit l'EXCEPTION de:
A. L'Etalonage.
B. Le diagramme de Pareto.
C. Les histogrammes.
D. L'chantillonnage statique.
57. Control ch arts are:
A. Used in product rcview.
B. Used to chart a project's expected value.
C. Used to determine if a process is in control.
D. Used to define a statistical sample.
57. Les diagrammes de contrle sont:
A. Utilis dans l'examen de produit.
B. Utilis pour reprsenter graphiquement la valeur attendue d'un projet.
C. Utilis pour dterminer si un processus est sous contrle.
D. Utilis pour dfinir un chantillon statique.
Page 11
58. Laquelle des affirmations suivantes concernant les parties prenantes est VRAIE?
A. ils ont un certain intrt financier dans le projet.
B. Leurs besoins devraient tre qualifis ou valus quantativement.
C. Les parties prenantes cl participent la cration de plan de gestion des parties prenantes.
D. Elles peuvent tre positivement ou ngativement affectes par le rsultat du projet.
63: Vou are managing a team developing a software product. Vou have contracted out a portion of the development, Midway through the project
you learn that the contracting company is entering Chapter 11. A manager from the subcontracting company assures you that the state of the
company will Dot affect your project, What should you do FIRST?
A. Perform additional risk response planning to control the risk this situation poses.
B.Stop ail pending and future payments to the subcontractor until the threat is fully assessed.
C. Contact yourlegal department to research your options.
D. Meet with senior management to apprise them of the situation.
Page 12
...
63. Vous grer une quipe dveloppant un logiciel. Vous avez sous-trait une partie du dveloppement. A mi-chemin du projet vous apprenez que la socit
contract se met sous le chapitre 11 qui concerne les socits en cessation de paiement. Un directeur de la socit de soustraitance vous assure que l'tat de la
compagnie n'affectera pas votre projet. Que devriez-vous faire en PREMIER?
A. Reprendre la planification de rponse aux risques afin de matriser le risque li cette situation.
B.Arrter tous les paiements en suspens et future au sous-traitant jusqu'a ce que la menace soit entirement value.
C. Entrer en contact avec votre service juridique pour faire des recherches sur vos options.
D. Rencontrer la direction pour les informer de la situation.
64. In a functional organization:
A. Power primarily lies with the project manager.
B. Power primarily lies with the functional manager.
C. Power is blended between functional and project managers.
D. Power prirnarily lies with the project office.
64. Dans une organisation fonctionnelle:
A. Le pouvoir se trouve principalement entre les mains du chef de projet.
B.Le pouvoir se trouve principalement entre les mains du responsable fonctionnel.
C. Le pouvoir est rparti entre le responsable fonctionnel et le chef de projet.
D. Le pouvoir se trouve principalement au bureau du projet.
65. The process of identifying, documenting, and assigning roles, responsibilities, and reporting relationships for a project is caUed:
A. Project lnterfacing.
B.Organizational Breakdown,
C. Staff Management Planning.
D. Human Resourcc Planning.
65. Le processus d'identification, de documentation et d'assignation des rles et responsabilits et les relations de reporting pour un projet est appel:
A. Interface de projet.
B. Rpartition organisationnelle.
C. Planification de la gestion de personnel.
D. Planification des ressources humaines.
Page 13
69. Si une quipe de projet bute sur un conflit ou sur une dcision technique et l'excution de projet est affecte ngativement. QueIle est la MEILLEURE
source de pouvoir que peut utiliser un chef de projet pour amener la coopration?
A. Lgitime.
B.Coercisif
C.
Rfrent.
D. Expert.
70. You have asked a team member to estimate the duration for a specifie activity, and she bas reported back to you with three estimates. The best case scenario
is that the activity could be completed in 18 days; however, her most likely estimate for the task is 30 days; She also indicated that there is the possibility the
task could take as long as 60 days. What is the three point estimate for this task?
A. 4 days.
B.7 days.
C. 33 days,
D. 49 days.
70. Vous avez demand un membre d'quipe d'valuer la dure d'une activit spcifique, eIle vous prsente un rapport avec trois estimations. Le meilleur
scnario est que l'activit pourrait tre complte en 18 jours. Cependant, l'valuation la plus probable est de 30 jours; eIle indique la possibilit que la tche se
fasse en 60 jours. QueIle serait une estimation 3 points pour cette activit?
A. 4 jours.
B.7 jours.
C. 33 ours.
D. 49 jours.
71. You are the project manager of a project that is executing. Several defects have been discovered in the project product. The project team does not have
time to repair aIl the defects, Which tool wiIl you use to prioritize the defects?
A. Control chart
B. Pareto diagram
C. Decision tree analysis
D. Variance analysis
71. Vous tes le chef d'un projet en cours. Plusieurs dfauts ont t dcouverts dans le produit du projet. L'quipe du projet n'a pas le temps de corriger tous les
dfauts. Quel outil peut tre utilis pour prioriser les dfauts?
A. Les diagrammes de contrle
B.Les diagrammes de pareto
C. Les arbres de dcision
D. L'analyse des carts.
72. The communications management plan:
A. Should include the performance reports.
B. Should always be higWy detailed.
C. Should include the project's major milestones,
D. Should detail what methods should be used to gather and store
72. Le plan de management des communications:
A. Devrait comprendre les rapports de performance
B. Devrait toujours tre trs dtaill.
C. Devrait inclure les jalons majeurs du projet.
D. Devrait dtailler quelles mthodes devraient tre utilises pour le recueil et le stockage des informations.
73. When communication links are undefined or broken:
A. The communications management plan should be rewritten.
B. Conflict will increase.
C. The project manager's power will decrease.
D. Project work will stop.
73. Quand les liens de communication ne sont pas dfinis ou sont casss:
A. Le plan de management des communications devrait tre recrit.
B. Les conflits augmenteront.
C. Le pouvoir du chef de projet diminuera.
D. Le travail de projet s'arrtera.
74. For two days you have been asking a member of your team for a status report on one of the key deliverables of your project. You finaIly get the report
thirty minutes before you are to meet with your manager for a project update. A quick review of the status report reveals some information that you know is
incorrect. What action should you take?
A. Fix what you can in the report before the meeting starts and try to steer discussion away from the areas you don't have time to fix.
B.Bring your team member with you to the meeting and confront her with the inaccuracies in her report.
C. Reschedule the meeting for a later date and have the tearn member rewrite the report.
D. Cancel the meeting, fix the report yourself, and circulate the new report to senior management in lieu of the original meeting.
Page 14
74. Vous avez demand depuis 2 jours un membre de votre quipe un rapport d'avancement par rapport un livrable cl de votre projet. Vous recevez
finalement le rapport trente minutes avant de rencontrer votre manager pour une mise jour du projet. Une lecture rapide des rapports d'avancement rvle
que quelques informations dont vous aviez connaissance sont incorrectes. Quelle mesure devriez-vous prendre?
A. Corriger ce que vous pouvez dans le rapport avant le dbut de la runion et essayer d'viter de discuter des points que vous n'avez pas eu le temps de
discuter.
B. Inviter le membre de votre quipe la runion et le confronter aux inexactitudes de son rapport.
C. Reporter la runion pour une date ultrieure et demander ce membre de l'quipe de reprendre le rapport.
D. Annuler la runion, rcrire le rapport vous-mme et envoyer le nouveau rapport la direction la place de la runion.
75. There were 10 people on your project, and 5 more people were added last week, How many additional paths of communication were created?
A. 10.
B.4S.
C. 60.
D.10S.
75. Il Y avait 10 personnes sur votre projets, et 5 autres ont t ajoutes la semaine dernire. Combien de cannaux de communications supplmentaire
ont t cres?
A.10.
B.4S.
C.
60.
D.10S.
76. A project manager is having difficulty getting resources from a functional manager. Which of the following would be the MOST appropriate to help resolve
this problem?
A. Senior management.
B. The cu st omer.
C.Key stakeholders.
D. The sponsor.
76. Un chef de projet des difficults pour obtenir des ressources de la part d'un directeur fonctionnel. Qui serait mme de rsoudre ce problme?
A. La direction gnrale
B. Le client.
C. Les parties prenantes
cl. D. Le sponsor.
77. The project manager of the Mother Nature project has le ft during the project execution, and you have been appointed the new project manager for this
project. The project sponsor has asked you to give her a copy of the document that contains the work package descriptions. Which of the following documents
will you look for?
A. The project scope statement
B.The WBS dictionary,
C. The project schedule
D. The project charter
77. Le chef du projet Mother Nature a quitt durant l'excution du projet et vous avez t nomm nouveau chef de projet. Le sponsor du projet vous a demand
de lui donner une copie du document qui contient la description des lots de travail. Quel document devrez-vous chercher?
A. L'nonc du contenu du projet
B.Le dictionnaire de la SDP
C. L'chancier du projet
D. La charte du projet
78. Smoothing, forcing, and withdrawing are ail forms of:
A. Organizational power.
B. Communication.
C. Conflict resolution.
D. Schedule compression.
78. L'apaisement, le passage en force et le retrait sont toutes des formes de:
A. Pouvoir organisationnel.
B. Communication.
C. Rsolution de cont1it.
D. Compression d'chancier.
79. Vou have a team member who is habitually late to meetings with the customer. The customer has expressed dissatisfaction with the ) situation and has
asked you to resolve it, Your BEST course of action is :
A Issue a formaI writtcn reprimand to the team member
B. Meet with the team member to discuss the problem and ask for solutions.
C. Meet with the team rnernber and the custorner to promo te further understanding,
D. Email the team rncmber to bring the situation to his attention.
\.-'< ,
:'}
79. Vous avez un membre de l'quipe qui est gnralement en retard aux runions avec le client. Le client vous exprime son mcontentement
et vous demande de rsoudre la situation. Votre MEILLEURE ligne de conduite est:
A. Le sanctionner formellement par crit.
B. Rencontrer le membre de l'quipe et discuter du problme et demander des solutions.
C. Rencontrer le membre de l'quipe et le client afin de trouver un arrangement commun.
D. Envoyer un email au membre de l'quipe pour le prvenir de la situation sa connaissance.
80. Vou are midway through managing a project wit a sponsor-approved budget of $850,000. Using earned value management, you have determined that the
project will run $125,000 under budget. Vou have also determined that if the project is delivered that far under budget you will not make your bonus since you
are compensated for the hours you bill. What is your BEST course of action?
A. Add extra features to the project that take advantage of the available budget, and increase customer satisfaction.
B. Meet with the project sponsor to inform him of you findings.
C. Maintain current project activities, and bill for the original amount.
D. Ask the sponsor to approve additional features, given the available budget.
80. Vous tes au milieu d'un projet dont le budget approuv par le sponsor est de 850.000$. En utilisant l'outilla gestion de la valeur acquise, vous avez
dtermin que le projet cotera 125.000 $ de moins que le budget prvu. Vous avez galement dtermin que si vous livrez le projet en dessous du budget initial,
vous ne toucherez pas votre prime du fait que vous tes jug sur les heures factures. Quelle serait la MEILLEURE chose faire?
A. Ajouter des fonctions supplmentaires au projet en profitant du budget restant, et augmenter la satisfaction client.
B. Rencontrer le sponsor du projet afin de l'informer de ce que vous avez trouv
C. Maintenir les activit es actuelle du projet et facturer pour le montant initial.
D. Demander au sponsor d'approuver des fonctions supplmentaires, vu le budget disponible.
83. Votre quipe a rencontr des problmes imprvus rcemment. Aprs l'analyse de valeur acquise vous dterminez que le projet a un indice de performance
de l'chancier de .54 et un indice de performance des cots de 1.3. De plus votre client vient de demander un changement significatif. Que devriez-vous faire?
A. Alerter la direction au sujet du retard
B. Alerter la direction du surcot.
C. Alerter la direction du changement de porte.
D. Rejeter la demande de modification.
Page 16
84. Y ou are in the middle of bidding on a large and complex project that will produce a great deal of revenue for your company should you win the bid. The
buyer has specified several conditions that accelerate sorne of the key dates and milestones. Vou have done extensive planning with your team and have
determined that there is no way that your organization can perform the required scope of work under these new deadlines. Your boss, however, is not
convinced that you are right and is also concerned that if you don't agree to the new dates you williose the contract. What should you do?
A Appeal to the buyer for additional time to estimate,
B. Ask your boss to make the commitment on behalf of the team.
C. Adhere to the estirnates your tearn has made.
D. Agree to the dates the customer has requested,
84. Vous tes en plein milieu d'une soumission pour un grand projet complexe qui produira beaucoup de revenus pour votre socit si vous remportez cette
affaire. L'acheteur a spcifi plusieurs conditions qui acclrent certaines dates et jalons du projet. Vous avez ralis avec votre quipe une planification
dtaille et avez dtermin qu'il n'y avait aucune faon que votre compagnie puisse raliser le contenu demand dans ces nouveaux dlais. Cependant, votre
patron n'est pas sr que vous ayez raison d'autant plus que si vous n'tes pas d'accord avec ces nouvelles dates, vous perdrez le contrat. Que devriez-vous faire?
A Demander l'acheteur du temps supplmentaire pour valuer.
B. Demander votre patron de s'engager la place de l'quipe.
C. Adhrer aux valuations que votre quipe a faite.
D. Etre en accord avec les dates que le client demande.
85. Your company is soliciting bids from advertising firms for the marketing of the product your project will produce. A sales representative from one of the
bidding firms calls to invite you to attend a sporting event with him at his expense so that he can ask you sorne questions about the product to help him put
together his bid. How should you respond?
A Attend the event and discuss the project with the representative.
B. Accept his offer but tell him in advance that you cannot answer questions about the project.
C.Attend the event and answer aIl questions, but then write a report on the questions and answers and subrnit the FAQ to the other bidders.
D. Reject the offer and invite the sales representative to pose his questions at the bidders' conference.
85. Votre socit sollicite des offres de socits publicitaires pour le marketing du produit que votre projet produira. Un reprsentant d'une des socits
sollicites vous appel pour vous inviter assister un vnement sportif avec lui, ses frais, afin qu'il puisse vous poser des questions sur le produit en vue de
vous proposer une offre. Comment devriez-vous rpondre?
A. Suivre l'vnement et discuter avec le reprsentant.
B. Accepter son offre mais lui dire d'avance que vous ne pouvez pas rpondre aux questions concernant le projet.
C. Suivre l'vnement et rpondre toutes ses questions, puis crire un rapport sur les questions et les rponses et soumettre les Questions/Rponses aux
autres soumissionnaires.
D. Rejeter l'offre et inviter le reprsentant poser ses questions la confrence des soumissionnaires.
86. Analogous estimating is also called:
A Vendor bid analysis.
B. Bottom-up estimating.
C. Scalable mode! estimating.
D. Top-down estimating.
86. L'estimation par analogie est aussi appele:
A Analyse d'offre de fournisseur.
B. Estimation ascendante.
C. Estimation de modle volutif.
D. Estimation de haut en bas.
87. Vou are beginning construction of a bridge in another country when you discover that this country requires thar one of its licensed engineers sign off on the
plans before you break ground. Your senior engineer on the project is licensed in your own country and is probably more qualified than anyone to sign off on
this, and their engineer is not available to review the plans for another three weeks, The customer has stressed that this project must not be delayed. What do
you do?
A Have your engineer sign off on the plans, forward them to the other engineer and begin construction.
B. Have your engineer sign off on the plans since he is licensed in your country and begin construction.
C. Wait to begin construction until the country's engineer signs off on the plans.
D. Forward the plans ta the country's engineer for his signature and start construction.
87. Vous commencez la construction d'un pont dans un autre pays quand vous dcouvrez que ce pays exige qu'un de ses ingnieurs agr doit valider le plan
avant de commencer les travaux. Votre ingnieur est confirm dans votre propre pays et il est probablement le plus qualifi que quelqu'un d'autre pour valider
le projet, d'autant plus que leur ingnieur n'est pas disponible pendant les trois prochaines semaines. Le client a soulign que ce projet ne doit pas prendre du
retard. Que faites-vous?
A. Laisser votre ingnieur valider les plans et envoyer ceux-ci l'autre ingnieur puis commencer les travaux.
B.Laisser votre ingnieur valider les plans puisqu'il est autoris dans votre pays et commencer les travaux.
C. Attendre que l'ingnieur du pays en question valide les plans pour commencer la construction.
D. Envoyer les plans l'ingnieur pour signature et commencer les travaux.
Page 17
D.23
Task
Duration
Start -A
A-B
B-C
A-E
3
4
3
E-F
C-D
E-C
B-F
F-G
G-Finich
7
5
D-Finich
D 23
Tche
Dure
Start -A
A-B
B-C
3
4
A-E
E-F
C-D
E-C
B-F
F-G
G-Finich
D-Finich
89. Vou are managing the installation of a new oil weil pump in a very productive well. Due to very efficient management and significant personal effort, the project
is completed several days ahead of schedule. The customer is ecstatic and offers you a $2,500 "appreciation fee." What should you do?
A. Accept the fee, but notify management.
B. Do not accept the fee and notify management.
C. Put the gift into the project's reserve fund.
D. Donate the gift to charity.
89. Vous grez l'installation d'une nouvelle pompe de puits de ptrole sur un gisement trs productif. En raison d'une gestion efficace et d'un effort personnel
significatif, le projet est complt plusieurs jours avant la date prvue. Le client admiratif, vous offre 2500 $ pour "prime d'apprciation". Que devez-vous faire?
A. Accepter la prime mais en informer la direction.
B. Ne pas accepter et informer la direction.
C. Mettre le cadeau dans le fond de rserve du projet.
D. Faire un don de charit avec le cadeau.
Page 18
.,a
..
Page 19
98. Votre directeur a demand passer en revue le plan de management de la qualit pour s'assurer qu'il est suivi convenablement. Dans quel processus votre patron estil impliqu?
A. Mettre en uvre le contrle qualit
B.Mettre en uvre le management de la qualit.
C. Planifier la qualit.
D. Mettre en oeuvre d'assurance de qualit.
99. Variance analysis is a tool used to:
A. Measure variance between actual work and the baseline,
B.Measure variance between planned value and schedule variance.
C. Measure variance between earned value and actual cost.
D. Measure variance between earned value and cost variance.
99. L'analyse des carts est un outil utilis pour:
A. Mesurez l'cart entre le travail rel et la rfrence de base.
B.Mesurez l'cart entre la valeur planifie et l'cart de dlais
C. Mesurez l'cart entre la valeur acquise et le cot rel.
D. Mesurez l'cart entre la valeur acquise et l'cart de cot.
100. ln a strong matrix organisation:
A. More power is given to the functional manager.
B. More power is given to the project manager.
C. More power is l,,>iven to the project expeditor.
D. More power is given to the project coordinator.
100. Dans une organisation matricielle forte:
A. Plus de pouvoir est donn au directeur fonctionnel.
B. Plus de pouvoir est donn au chef de projet.
C. Plus de pouvoir est donn l'expditeur de projet.
D. Plus de pouvoir est donn au coordinateur de projet.
101. Team performance assessments are made during which process?
A. Develop Human Resourcc Plan
B.Acquire Project Tearn.
C. Develop Project Team.
D. Manage Project'Team.
101. Les valuations de performance de l'quipe sont faites pendant quel processus?
A. Planifier les ressources humaines.
B.Constituer l'quipe de projet.
C. Dvelopper l'quipe de projet.
D. Diriger l'quipe de projet.
102. The Project Scope Statement is typically:
A. A definitive list of ail the work and only the work to be done on the project.
B.Issued by senior management.
C. Progressively elaborated.
D. Defined before the functional specifications.
102. L'nonc du contenu du projet est typiquement:
A. Une liste dfinitive de tout le travail et seulement le travail faire sur le projet.
B.Ralis par la direction gnrale.
C. Progressivement labor.
D. Dfini avant le cahier des charges fonctionnel.
Page 20
..
'.
103. In general, the procurement documents contain the following elements EXCEPT:
A. The procure ment management plan
B.The desired form of response
C. The contractual provisions
D. The statemcnt of work
103. En gnral, les documents d'approvisionnements contiennent les lments suivants l'EXCEPTION de:
A. Le plan de management des approvisionnements
B.La forme desire de rponse
C. Les dispositions contractuelles
D. L'nonc des travaux
104. During Direct and Manage Project Team, your project team should he:
A. Focused on making sure earned value is equal to planned value.
B. Communicating work results to the stakeholders.
C. Ensuring that ail project changes are reflected in the project plan.
D. Executing the work packages.
105. Le systme supportant tous les aspects des processus de management de projet du dbut la fin est:
A. Technologie de l'information.
B. Le systme de distribution de l'information.
C. Le systme de gestion de l'information de projet.
D. Le systme d'autorisation de travail.
106. In a typical project, most of the resources are utilized and expended during:
A. Initiati. JO proccsses,
B.Planning processes,
C.Executing process
D.Monit, )ring and controlling processes.
106. Dans un projet typique, la plupart des ressources sont utilises et dpenses pendant:
A. Les proces,;us de dmarrage.
B.Les processus de planification.
C. Les processus d'excution.
D. Les proces,;us de surveillance et de matrise.
107- A pro je jet manager is taking the product of his project to his customer for verification that it meets the scope. The customer and the project
manager are working together to carefully compare the product to the project's scope to ensure that the work was done to specification. The tool that the
customer and the project manager are using is:
A Inspection.
B Perform Quality Assurance.
C Perform Quality Control.
D User acceptance testing.
107. Un chef de projet a pris un produit de son projet pour le montrer son client pour une vrification du contenu. Le client et le chef de projet ont travaill
ensemble afin de comparer soigneusement le produit au contenu du projet pour s'assurer que le travail a t fait selon les spcification. L'outil que le client et le
chef de projet utilisent est:
A. Inspection.
B.Mettre en uvre l'assurance de qualit.
C. Mettre en uvre le contrle de qualit.
D. Tests d'acceptation des utilisateurs.
108. Wich of the following is NOT a project quality management process?
A. Perform Quality Assurance.
B. Quality Planning.
C. Quality Improvcment,
D. P erform Quality Control.
Page 21
108. Laquel des propositions suivantes n'est PAS un processus de management de la qualit de projet.
A. Mettre en uvre l'assurance de qualit.
B.Planifier la qualit.
C. Amliorer la qualit.
D. Mettre en uvre le contrle de qualit.
-'
109- Schedule constraints would likely include all of the foUowing EXCEPT:
A. Imposed dates.
B. Key events.
C. Major milestones.
D. Leads and lags,
109. Les contraintes de l'chancier incluraient probablement tout ce qui suit EXCEPTE:
A. Les dates imposes.
B.Les vnements cls.
C. Les jalons majeurs.
D. Les dcalages avec avance et avec retard.
110- Wich of the foUowing choices fits the definition for benchmarking?
A-Comparing planned results to actual results.
B-Comparing actual or planned results to those of other projects.
C- Statistical sampling of results and comparing them to the plan.
D- Cornparing planned value with earned value.
110. Lequel des choix suivants corespond la dfinition de l'talonnage?
A. La comparaison entre le rsultat prvu et le rsultat rel.
B. Comparaison de rsultats rels ou projets ceux d'autres projets.
C. Echantillonnage statique des rsultats et comparaison de ceux-ci avec le plan.
D. comparaison de la valeur acquise et de la valeur planifie.
111- The activity list should include:
A. The schedule activities on the project that are on the critical path.
B. A subset of ail schedule activities.
C. All of the schedule activities defined on the project.
D. A superset of the schedule activities for this and rclated projects.
111. La liste d'activit devrait inclure:
A. Les activits de l'chancier du projet qui sont sur le chemin critique.
B.Un sous-ensscmblc de toutes les activites de l'chancier.
C. Toutes les activits de l'chancier dfinies pour le projet.
D. Un sur-ensemble des activits de l'chancier pour les projets lis.
112. Close Project should be performed:
A. At the end of each phase or the end of the project.
B.Bcfore formal acceptance of the project's product.
C. As a safeguard against risk.
D. By someone other than the project manager.
112. clore le projet devrait tre excute:
A. A la fin de chaque phase ou la fin du projet.
B.A vant l'acceptation formelle de produit du projet.
C. Comme sauvegarde contre le risque.
D. Par quelqu'un d'autre que le chef de projet.
113. Release criteria for team members is defined as part of:
A. The organizational management plan.
B. The human resources plan.
C. The staffing management plan.
D. The work authorization system.
113. Les critres de dsengagement des membres de l'quipe sont dfinis comme faisant partie du :
A. Le plan de management organisationnel.
B. Le plan des ressources humaines.
C. Le plan de management des Ressources Humaines.
D. Le systme d'autorisation de travail.
114. Which of the following is NOT an input into Activity Definition?
A. The work breakdown structure.
B.Organizational process assets.
C. Project scope statement,
D. The activity list.
Page 22
"
114. Lequel des lments suivants n'est PAS une entre d'Identifier les activits.
A La structure de dcoupage du projet.
B. L'actif organisationnel.
C. L'nonc du contenu du projet.
D. La liste des activits.
115. A project to lay 10 miles of a petroleum pipeline was scheduled to be completed today, exacdy 20 weeks from the start of the project. You receive a
report that the project has an overall schedule performance index of 0.8. Based on this information, when would you expect the project to be completed?
A. 2 weeks early.
B.ln 2 more wceks.
C. ln 5 more wceks.
D. ln 10 more wecks.
115. Un projet de pose une canalisation de ptrole de 10 miles a t programm pour tre accompli aujourd'hui, exactement 20 semaines aprs le dbut du
projet. Vous avez reu un rapport vous indiquant que l'indice de performance des dlais est de 0.8. Sur la base de cette information, quand vous attendriez-vous
ce que le projet soit achev?
A 2 semaines plus tt.
B. Dans 2 autres semaines.
C. Dans 5 autres semaines.
D. Dans 10 autres semaines.
116- the term "slack" is also known as:
ALag.
B.Lead.
C.Float.
D.Free float.
116. On connat aussi le terme ~k comme:
A dcalage avec retard.
.
B. dcalage avec avance
C. marge
D. marge libre
117- Wich of the following BEST describes the project plan?
A A formal, approved document used to guide project execution, control, and closure.
B. The aggregatc of all work performed during planning.
C. The work brcakdown structure, schedule management plan, budget, cost management plan, and quality management plan.
D. The document that outlines ail of the work and only the work that must be performed on a project.
117. Laquelle des faons suivantes est la MEILLEURE pour dcrire le plan de projet? A Un
document formel guidant l'excution, le contrle et la fermeture de projet.
B. L'ensemble du travail excuter pendant la planification.
C. La structure de rpartition de travail, planification de gestion de plan, de budget et de planification de gestion de cot et de qualit.
D. Un document qui dcrit tout le travail et uniquement le travail devant tre excuter sur un projet.
118. Which of the following is NOT a primary goal of integrated change control? A Influencing factors that cause change.
B -Determining that a change has occurred.
C- Managing change as it occurs,
D -Denying change.
118. Laquelle des rponses suivantes n'est PAS un but principal de la matrise intgre des modifications?
A. Influencer les facteurs causant les modifications.
B.Dterminer si une modification s'est produite.
C. Grer les modifications comme elles arrivent.
D. Refuser systmatiquement les modifications.
119- Vou are providing project management services in a foreign country. In an attempt to improve employment, this country has enacted a law limiting the
number of hours foreigners may work per week. Vou are behind schedule on the project and need to work overtime. What is the BEST way to handle this
situation?
A- Work the overtime only if your own country's laws do not prohibit this.
B- Work the overtime if it is not constituted overtime by your country's definition.
C-Do not work the overtime since it is prohibited by law.
D- Speak with legal representation to find out if the law is enforceable.
119. Vous fournissez des services de management de projet dans un autre pays. Dans une tentative d'amlioration des emplois, ce pays a promulg une loi
limitant le nombre d'heures de travail par semaine pour les trangers. Vous tes en retard sur l'chancier du projet et devez faire des heures supplmentaires.
Quelle est la meilleure faon de traiter cette situation?
A Faire des heures supplmentaires seulement si les lois de votre propre pays ne l'interdisent pas.
B. Faire des heures supplmentaires seulement si ce n'est pas considr comme heures supplmentaires par dfinition dans votre pays.
C. Ne pas faire d'heures supplmentaires puisque c'est interdit par la loi.
D. Parler avec un reprsentant lgal pour savoir si la loi est excutoire.
Page 23
-,
120- " The features attributes that characterize a product" de scribes which of the following?
A. The product scope.
B. The project scope.
C. The work breakdown structure.
D. The critical success factors.
120. "Les attributs de fonctionnalits qui caractrisent un produit" dcrivent lequel des lments suivants?
A. Le contenu du produit.
B. Le contenu du projet.
C. La structure de dcoupage du projet
D. Les facteurs de succs critiques.
121. You have assumed responsibility for a project that bas completed planning and is executing the work packages of the project. ln one of your first status
meetings, a member of the project te am begins to question the validity of the duration estimates for a series of related tasks assigned to her, What action should you
take FIRST?
A. Remind the team member that planning bas been completed an ask her to do her best to adhere to the estirnates.
B. Temporarily suspend execution and ask the team member for updated estimates.
C. Revicw the supporting detail for the estima tes contained in the project plan to understand how the estimates were originally derived.
D. Ask another team member with expertise in this area to perform a peer review on the estimates to validate or invalidate the concern.
121. Vous avez assum la responsabilit d'un projet dont la planification et l'excution ue travail est acheve. Dans l'une de vos premires runions d'tat
d'avancement, un membre de l'quipe de projet commence mettre en doute la validit des valuations de dure pour une srie de tches qui lui ont t assignes.
Quelle action devriez-vous prendre d'abord?
A. Rappeler au membre de l'quipe que la planification est acheve et lui demander de faire de son mieux pour adhrer aux valuations.
B. Suspendre temporairement l'excution et demander aux membres de l'quipe d'valuation une mise jour de celles-ci.
C. Revoir les dtails des valuations contenues dans le plan de projet pour comprendre comment les valuations ont t faites l'origine.
D. Demander un autre membre de l'quipe avec de l'exprience dans ce domaine d'examiner ces valuations afin de les confirmer ou de les rfuter.
122. Approved budget increases should be:
A. Added to the schedule management plan.
B. Added to the projecr's cost baseline.
C. Added to the project's reserve fund and used only if needed.
D. Added to the lessons lcamed.
122. Des augmentations budgtaires approuves devraient tre:
A. Ajoutes au plan de management de l'chancier.
B. Ajoutes la rfrence de base de cot de projet.
C. Ajoutes la rserve de financement de projet et utilis seulement si c'est ncessaire.
D. Ajoutes aux leons apprises
123. An organization where the project manager is in charge of the projects and has primary responsibility for the resources is:
A. Functional.
B.Projectized.
C. Matrix.
D. Hierarchical.
123. Une organisation o le chef de projet est en charge de projets et a la principale responsabilit sur les ressources est:
A. Fonctionnelle.
B.de type projet
C. Matricielle
D. Hirarchique.
124 - Based on the table Which path listed below represents the LEAST schedule risk? A. Start - A-BC-I Finich
B - Start - A-B-H-I Finich
C - Start - D-E-H-I Finich
D - Start - F-G-I Finich
Task
Dependency
Duration
Start
None
Start
Start
Start
B,E
C,G,H
Finich
Page 24
..
C
D
E.
124. Sur la base du tableau, quel est le chemin reprsentant le moins de risque sur l'chancier? A. Dbut
-A-B-C-! Fin
13. Dbut -A-B-I!-! Fin
C. Dbut -D-E-H-! Fin
D. Dbut -F-G-! Fin
Tche
Dpendance
Dure
Dbut
None
Dbut
Dbut
Dbut
B,E
C,G,H
Fin
125- As part of your project, four customer needs a software module to handle credit card payments. Senior management informs you that they already own
the rights to such a module and would like for you to use this piece of software on the project; however, upon investigation, you determine that your
company's software is not a good match for this customer's needs. After informing your senior management, they maintain their request that you use their
software. How should you resolve this conflict?
ALook to buiId or procure another solution for the custorner.
13Act in favor of the performing organization.
CUse your company's software module as rcquested as long as it does not jeopardize the project,
DInvolve an objective outside party to help resolve the dispute.
125. Pour une partie de votre projet, votre client a besoin d'un module logiciel pour traiter des paiements par carte de crdit. La direction vous informe qu'ils
ont dj les droits pour un tel module et voudrait que vous l'utilisiez dans le projet. Cependant, aprs enqute, vous dterminez que ce logiciel de votre
compagnie ne correspond pas aux besoins du client. Aprs avoir inform votre direction, ils maintiennent leur demande qui est d'utiliser leur logiciel. Comment
devez-vous rsoudre ce conflit?
A. Songer procurer une autre solution au client.
B. Opter en faveur de l'organisation qui ralise
C. Utiliser le logiciel comme demand tant que celui-ci ne met pas en danger le projet.
D. Impliquer un partie tierce objective afin d'aider rsoudre la situation.
nd lags are evaluated and adjusted in which process?
formance.
hedule,
Schcdulc.
Page 25
131. Quel processus se concentre sur la production d'une liste des activits ncessaire pour produire les lments et les sous-lments fournir dcrit dans la Structure
de dcoupage du projet?
A. Identifier les activits.
B.Organiser les activits en squence.
C. Lister les activits.
D. Estimer la dure d'activit.
132. Whose job it to resolve competing objectives and goals between parties on the project? A- The
stakeholders.
B- The project manager.
C- Senior management.
D- The sponsor.
132. A qui revient la tche consistant rsoudre les objectifs et les buts contradictoires entre chaque parties du projet?
A. Les parties prenantes
B. Le chef de projet.
C. La direction gnrale
D. Le sponsor.
133. As project manager, you have made the decision to outsource a part of your project to an outside organization with whom you have never previously worked. You
are ready to begin negotiating the contract. what should be YOUf goal in the contract negotiations?
A. Having a lawyer or the legal departmcnt revicw each clause in the proposed contract prior to sharing it with any outside entity.
B. N egotiating the bcst possible priee for Y0uf custorner or organization.
C.Arriving at mutually agreeable terms for the contract between your organization and the subcontracting organization.
D. Shifting as much of the project risk to the subcontracting organization as possible.
133. En tant que chef de projet, vous avez pris la dcision d'extemaliser une partie de votre projet une organisation avec laquelle vous n'avez jamais travaill
auparavant. Vous tes prt ngocier le contrat. Quel devrait tre votre but dans cette ngociation?
A. Avoir recourt un avocat ou un service juridique pour passer en revue les clauses du contrat avant de le partager avec n'importe quelle entit extrieure.
B. Ngocier le meilleur priX pour votre client ou organisation.
C. Parvenir une entente mutuelle sur les termes du contrat pour les deux parties.
D. Transfrer le plus de risque possible l'organisation de sous-traitance.
Page 26
134. you have heen working under contract on a very large automotive project that has spanned several years. As part of this project, you have
been privileged to praetically ail of the project information. As you are transitioning off of the project, you would like to use the extensive work breakdown
structure as an input into future projects (in other companies). Vou were never asked to sign a non-disclosure agreement with the current organjzation. What is
the appropriate thing to do in this case?
A. Use the woel; brcak.lown structure as you are not bound by any agreement not to.
B. Use the work brcakdown structure, but do not share it with others.
C. Do not use the work breakdown structure without the organization's permission.
D. Do not use the work breakdown structure because it would still be illegal.
134. Vous avez travaill sous contrat pour un grand projet automobile pendant plusieurs annes. En tant que membre de ce projet, vous avez eu un accs
privilgi pratiquement toutes les informations du projet. Comme vous tes en train de quitter le projet, vous aimeriez utiliser les structures de dcoupage du
projet dans de futurs projets (chez d'autres compagnies). On ne vous a jamais demand de signer un contrat de non-divulgation avec l'organisation actuelle. Quelle
est la chose faire la plus approprie?
A. Utiliser les Structures de dcoupage du projet tant donn que vous n'tes lis aucun accord.
B.Utiliser les Structures de dcoupage du projet, mais ne jamais la partager avec d'autres.
C. Ne pas utiliser les Structures de dcoupage du projet sans l'accord de l'organisation.
D. Ne pas utiliser !cs Structures de dcoupage du projet parce que ce serait illgal.
135. Which of the following is NOT an output of Cost Control?
A- Work performance measurcrnent.
B. Budget forccrsts.
C. Change rcqucsts
D. Project budget.
135. Lequel des lments suivants n'est pas un rsultat de matriser les cots?
A. Mesure de performance du travail.
B. Prvisions budgtaires.
C. Demandes de modifications
D. Budget de projet.
136. If the sche dulc variance $0.00, what must also he true?
A. Earned value must he cqual to planned value.
B. The cost performance index must be equal to 1.
C. The schcduk performance index must be greater than 1.
D. The estimatt- at complete must be equai to budgeted at complete.
136. Si l'cart des dlais est 0,00 $, qu'est-ce qui doit galement tre vrai?
A. La valeur acquise dort tre gale la valeur planifie.
B. L'indice de performance des cots doit tre gal 1.
C. L'indice de performance des dlais doit tre suprieur 1.
D. L'estimation j'achvement doit tre gale aux budget l'achvement
137. Schedule activitic s arc a further decomposition ofwhich of the following:
A. The statcmcnt of scope.
B. The work packages.
C. The project ncrwork diagram.
D. The functional specification.
137. Les activits de l'chancier sont une nouvelle dcomposition de quel lment suivant?
A. L'nonc du content!
B. Les lots de travail
C. Le diagramme de rseau du projet.
D. la spcification fonctionnelle,
138- Which statcmcnt is TRUE regarding the staffing management plan?
A. It is used as an input into Human Resource Planning.
B. It is a component of the project plan.
C. It should narne every human and material resource who will be working on the project.
D. It should contain an organization chart for the performing organization.
138. Laquelle des affirmations suivantes est vraie concernant le plan de management des ressources humaines?
A. Il est utilis comme une entre dans la planification de ressource humaine.
B. C'est un composant du plan du projet.
C. Il devrait nommer chaque ressource matrielle et humaine travaillant sur le projet.
D. Il devrait contenir \l11 organigramme de l'organisation dans laquelle se droule le projet
139 - Which of the following statements is TRUE regarding risk management?
A. Negative risks shoukl be quantified, while positive risks should be qualified.
B. Identified ris ks shou Id be added to the risk register.
C. AIl known risks should be listed in the risk management plan.
D. The risks thar cannot be mitigated must be avoided.
Page 27
1
139. Laquelle des dclarations suivantes est vraie quant la gestion ds risques?
A. Les risques ngatifs devraient tre quantifis, tandis que les risques positifs devraient tre qualifis.
B.Les risques identifis devraient tre ajout au registre de risque.
C. Tous les risques connus devraient tre inscrits dans le plan de management des risques.
D. Les risques qui ne peuvent pas tre attnus doivent tre vits.
140- You have a friend in another organization who has shared with you that he is having difficulty understanding the value of doing a scope statement, Your
friend's boss is not familiar with formai project management processes and does not want to waste time on the project performing unnecessary activities. What is your
MOST appropriate response?
A. Do not get involved since this is not within your organization.
B. Fay a visit to your friend's project office and educate them on the value of a scope statement.
C.Mentor your friend on the value of project management processes.
D -Encourage your friend to change organizations.
140. Vous avez un ami dans une autre socit qui vous a confi qu'il a de la difficult comprendre les apports de l'laboration d'un nonc du contenu. Le patron de
votre ami n'est pas familier avec les processus de management de projet et ne veut pas perdre de temps excuter des activits de projet inutiles. Quel est votre rponse
la plus approprie?
A. Ne pas vous impliquer tant que ce n'est pas dans votre socit.
B.Faire une visite au bureau de votre ami et leur enseigner la valeur d'un nonc du contenu
C. Aider votre ami comprendre les apports des processus de management de projet
D. Encourager votre ami changer de socit.
141- you are managing a project to construct 25 miles estimated co st of $1.2 million per mile. You have projected that you should be able to complete the project
in 5 weeks. What is your planned value for the end of the 3rd week of the project?
A. $12,000,000
B.$18,000,000
C. $24,000,000
D. $30,000,000
141. Vous grez un projet de construction de 25 miles valu 1.2 million $ par miles. Vous avez projet que vous seriez capable d'accomplir le projet en 5 semaines.
Quelle est la valeur planifie pour la fin de la 3me semaine de projet?
A. 12000 000 $
B.18 000000 $
C. 24 000 000 $
D. 30 000 000 $
142. Which term below de scribes the amount of time a schedule activity may be delayed before it affects the early start date of any subsequent schedule activity?
A. Float.
B. Slack.
C. Free float.
D. Lead.
142. Quel terme ci-dessous dsigne le temps dont peut tre retarde une activit avant qu'elle n'affecte la date de dbut de la suivante dans l'chancier?
A. Marge
B. Slack.
C. Marge libre.
D. Dcalage avec avance
Page 28
'-
144. Vous avez un tat du projet dfavorable annoncer votre client lors d'une runion hebdomadaire. Cependant, Vous tes convaincu que
vous pouvez rtablir la situation d'ici la runion de la semaine prochaine. Le client ne sera pas ravi d'entendre le statut actuel et bas sur le pass, il ragira de
manire excessive. Comment devriez-vous traiter cette situation?
A. Annoncer l'-tat actuel au client.
B. Reporter la remise de l'-tat du projet la runion prvue la semaine suivante votre client.
C. Omettre de donner les informations et couvrir le sujet la semaine suivante quand la situation s'amliorera.
D. Demander des conseils la direction.
145. What type ofprocess is conduct procurements?
A. Planning.
B. Executing.
C. Monitoring and comrolling.
D. Closing.
145. De quel type de processus est procder aux approvisionnements?
A. Planification.
B.Excution.
C. Contrle.
D. Clture
146. Who is responsiblc for providing funding for the project?
A .The qualified financial institution.
B. Senior management.
C. The sponsor.
D. The project manager.
146. Qui est responsable de fournir les finances au projet?
A. L'institution financire qualifie,
B.La direction.
C. Le sponsor.
D. Le chef de projet.
147- The project has bcen successfully completed when:
A. AIl of the work has beert completed to specification within time and budget.
B. The customer is happy.
C. The sponsor signs off on the project. D.
Earned value equals planned value.
147. Le projet est achev avec succs quand:
A. Tout le travail a -t- achev temps et en respectant le budget.
B. Le client est heureux.
C. Le sponsor termine le projet.
D. La valeur acquise est -gale la valeur planifie.
148- What is the PRIMARY objective of the project manager?
A. To follow l'MI's processes.
B. To delivcr maximum value for the organization.
C. To deliver the agreed upon scope of the project within the timc and budget.
D. To delight the cusromcr.
148. Quel est l'objectif principal du chef de projet?
A. Suivre les pruccssus du PMI.
B. Livrer la valeur maximale pour l'organisation.
C. Livrer le contenu convenu du projet dans les dlais et le budget.
D. Enchanter le client.
149. wich of the following would NOT be an organizational process as set?
A. Projcct plan tcmplutes.
B. Methodology guides.
C. Previous activity lists from projects, D.
Strong communication skills.
149. Lequel des lments suivants ne serait pas considr comme un actif organisationnel?
A. Modles de plan de projet.
B. Guides de rncthodol. 'gie.
C. Listes d'activit de projets antrieurs.
D. Comptences en communications fortes.
150 - Defective dclivcrables are repaired as part of which proeess?
A.Direct and Manage Project Execution.
B.Perform Quality Assurance.
C.Monitor and Control Projcct Work.
D. Integrated Change Control.
Page 29
Page 30
Page 31
166. Vou have been directed by your customer, your sponsor, and senior management to manage a project that you believe will have a very negative impact on the
economy and society. Vou have shared your concems, but ail parties continue to insist that you proceed. What should you do?
A. Manage the project because ail parties agree.
B. Refuse to manage the project.
C. Manage the project, but document your objections.
D. Contact PMI.
166. Vous avez t choisi par votre client, votre sponsor et votre direction pour grer un projet qui votre avis aura un mauvais impact sur l'conomie et la
socit. Vous avez partag vos soucis, mais toutes les parties insistent pour que vous le ralisiez. Que devriez-vous faire?
A. Grer le projet parce que toutes les parties sont d'accord.
B. Refuser de grer le projet.
C. Grer le projet, mais documenter votre objection.
D. Contacter le PMI.
Page 32
~
i
"
v169. Un chef de projet a un problme avec le taux de prsence d'un membre de l'quipe, le chef de projet prvoit chaque fois une runion pour parler du
problme, mais le membre trouve toujours une raison la dernire minute pour ne pas se prsenter. Quelle technique de gestion de conflit le membre expose-til?
A. Passive - agressive.
B.Couverture.
C. Diversion.
D. Retrait
170. In wich of the following organizations is the project manager MOST like to be part-time?
A. Weak rnatrix
B.Strong matrix
C. Functional
D. Projectized
170. Dans laquelle des organisations suivantes le chef de projet serait probablement temps partiel?
A. Matricielle faible.
B.Matricielle forte.
C. Fonctionnel.
D. Projet.
171. Which output would be used to show project roles and responsibilities?
A. A resource histogram.
B.An organization chart.
C. A RAC! chart.
D. A staffmg management plan.
171. Quelle sortie serait utilis pour montrer les rles dans le projet et les responsabilits?
A. Un histogramme de ressource.
B. Un organigramme.
C. Un diagramme de RACI.
D. Un plan de gestion de personnel.
Page 33
.,
'\.
...
176. Un projet est prvu sur une dure de 6 mois et coutera 300'000 $. A la fin du premier mois, le projet est achev 20%. Quel est la valeur acquise?
A. 50.010 $
B.60.000 $
C. 100.020 $
D. 120.000 $
177. Which of the following roles typically has the LEAST power?
A. Project coordinator,
B.Project expeditor.
C. Project manager.
D. Project director.
177. Lequel des rles suivants a typiquement le moins de pouvoir?
A. Coordinateur de projet.
B.Expditeur de projet.
C. Chef de projet.
D. Directeur de projet.
178. Configuration management is:
A. Technique used in Develop Project Management Plan.
B.Used to ensure that the product scope is complete and correct.
C. Formally defined in initiation.
D. A procedure to identify and document the functional and physical characteristics of an item or system.
178. La gestion de la configuration est:
A. Une technique utilise dans le dveloppement du plan de management de projet.
B.Utilise pour s'assurer que le contenu du produit est correct et complet.
C. Formellement dfinie dans le dmarrage
D. Une procdure pour identifier et documenter les caractristiques fonctionnelles et physiques d'un article ou d'un systme.
179. Which two processes are tighdy Iinked when performing a project (and often are performed at the same time or in the same sequence)?
A. Define Scope and Estimate Cost.
B.Direct and Manage Project Execution and Acquire Project Team.
C. Perforrn Quality Assurance and Manage Project Team.
D. Perform Quality Control and Verify Scope.
179. Quels processus sont lis dans un projet (et sont parfois excut en mme temps ou dans une mme squence)? A. Dfinir le
contenu et Estimer les cots.
B. Diriger et piloter l'excution du projet et constituer l'quipe projet.
C. Mettre en uvre l'assurance qualit et diriger l'quipe projet.
D. Mettre en uvre le contrle qualit et vrifier le contenu.
180. A company in the middle of a new product development merges with another company in the middle of the project, The project is terminated
because the new company already offers a similar product. What is the FIRST thing the project manager should do?
A. Make sure your lessons leamed are communicated to the manager of the existing product,
B. Obtain a written project termination,
C. Perform a comparative product analysis.
D. Perforrn the Close Project process.
180. Une socit en plein milieu du dveloppement d'un nouveau produit fusionne avec une autre socit. Le projet prend fin du fait que la seconde socit
dispose dj d'un produit similaire. Quelle est la premire chose que le chef de projet devrait faire?
A. S'assurer que les leons apprises sont communiques au directeur du produit existant.
B. Obtenir un rapport crit de fin de projet.
C. Excuter une analyse comparative de produit.
D. Excuter le processus de clture du projet.
181. A benefit-cost ratio of 1.5 tells you that:
A. The payback period will be one and one half years.
B. The project cannot pay for itself.
C. The project will field revenue that is 1.5 times its cost.
D. The project will cost 1.5 times the revenue it produces,
Page 35
Page 36
186. Le projet a une Valeur Acquise (VA) de 200, la Valeur Planifie (VP) est 150 et le Cot Rel (CR) est 175. Quelles sont les valeurs correctes
pour ce projet?
A. IPC est de 1.14 & IPD est de 1.14
B.IPC est de 1.33 & IPD est de 1.33
187. Alex est un chef de projet qui veut motiver son quipe en leur offrant une semaine de congs pays si le projet est livr temps. En prsentant cela l'quipe, il
passe beaucoup de temps convaincre l'quipe que cet objectif est ralisable. Quelle thorie explique le mieux le comportement d'Alex?
A. La thorie des attentes
B. La thorie des alas.
C. La thorie de l'accomplissement.
D. La thorie de stimulation/rponse
188. Ail of the following are needed for creating budget except.
A. Cost estirnates.
B. Schedule.
C. Resource calendar.
D. Organizational policies,
188. Tout ce qui suit est utilis pour crer un budget sauf:
A. Estimations de cots.
B. Echancier
C. Calendrier de ressource.
D. Politiques organisationnelle.
189. The fact that a software program must be written before it can be tested is an example of a:
A. Mandatory dependency.
B. Discretionary dependency.
C. External dependency.
D. Milestone dependency.
189. Le fait qu'un logiciel doit tre cre avant d'tre test est un exemple d'une:
A. Dpendance obligatoire.
B.Dpendance sur optionnelle.
C. Dpendance externe.
D. Dpendance de jalons.
190. What is the difference between a Gantt chart and a milestone chart?
A. A Gantt chart is a project plan and a milestone chart is not.
B. A milestone chart is a project plan and a Gantt chart is not.
C. A milestone chart shows interdependencies between activities.
D. A milestone chart shows only major events, while a Gantt chart shows more information.
190. Quelle est la diffrence entre un diagramme de Gantt et un diagramme de jalons?
A. Le diagramme de Gantt est un plan de projet tandis que le jalon ne l'est pas.
B.Un diagramme de jalon est un plan de projet et celui de Gantt ne l'est pas.
C. Un diagramme de jalon montre des interdpendances entre les activits.
D. Un diagramme de jalon montre uniquement des vnements majeurs tandis qu'un diagramme de Gantt donne plus d'informations.
191. Your team has created a project scope statement and a work breakdown structure. What is the NEXT step that needs to be taken?
A. Create a network diagram.
B. Develop the schedule.
C. Determine the critical path.
D. Create the activity list.
Page 37
4
191. Votre quipe a cre un nonc du contenu du projet et une structure de dcoupage du projet. Quel est l'tape suivante qui doit tre
ralise?
A. Crer un diagramme de rseau.
B. Elaborer l'chancier
C. Dterminer le chemin critique.
D. Dfinir les activits
192. You have assumed the position of project manager for a project that is nearly 50% complete. Because this project has reportedly had many quality
problems, you want to review what trends and variances have occurred overtime, Which tool would be most helpful to you?
A. Cause and effect diagrams.
B.Run charts.
C. Inspection.
D. Statistical sampling.
192. Vous avez assur le poste de chef de projet pour un projet achev 50%. Parce que ce projet a eu plusieurs problmes de qualit, vous dsirez
examiner quelles les tendances et les carts qui se sont produits dans le temps. Quel outil vous serait le plus utile?
A. Diagramme de causes et effets.
B.Relev d'observation
C. Inspection.
D. Echantillonnage statique.
193. A cable company is installing new fiber optic cables in a community you are the project manager and you will be using subcontractors to provide sorne
of the installations. You have completed the procurement management plan and the statement ofwork, and you have gathered and prepared the documents
that will be distributed to the sellers. What process should happen next?
A. Defme Scope,
B. Select Sellers.
C. Plan Procurements.
D. Conduct procurements.
193. Une socit de cblage installe de nouveaux cbles en fibre optique dans une communaut. Vous tes le chef de projet et vous devez utilis la soustraitance pour fournir certaines installations. Vous avez achev le plan de management des approvisionnement et l'nonc des travaux et avez runis et
prpar les documents qui seront distribus aux vendeurs. Quel processus devrait arriver ensuite?
A. Dfinir le contenu
B. Slection des fournisseurs
C. Planifier les approvisionnements
D. Procder aux approvisionnements.
194. Evaluating overall project performance on a regular basis to ensure that it meets expectations takes place in which process group of project
management?
A. Planning.
B. Executing.
C. Monitoring and controlling
D. Closing.
194. Evaluer la performance du projet sur une base rgulire pour assuer qu'il respectera les exigences se droule dans quel groupe de processus?
A. Planification.
B. Excution.
C. Surveillance et matrise
D. Clture
Page 38
199. Un projet est prvu pour durer 4 mois et coter 300.000 $. A la fin du premier mois, le projet est achev 20%. Quel est l'indice de performance des
dlais.
A. 0.80
B.1.02
C. 1.18
D.2.15
200. Bringing the entire project team and the customer on site to work together is an example of:
A. Communication control.
B. Collocation.
C. Active participation.
D. Collective team distribution.
200. Rassembler toute l'quipe de projet et le client au mme endroit afin de travailler ensemble est un exemple de:
A. Contrle de communication.
B. Regroupement
C. Participation active.
D. Distribution d'quipe collective.
Page 39