GC2 B.A 2019/2020
Sommaire
Introduction
I- Les Plans .................................................................................................................... 4
1- Plancher ................................................................................................................. 6
3- Plancher ................................................................................................................. 7
2- Moment au travée................................................................................................. 12
4- Ferraillage ............................................................................................................. 16
2- Ferraillage ............................................................................................................. 24
2
GC2 B.A 2019/2020
Introduction
3
GC2 B.A 2019/2020
I- Les Plans
1- Les plans architecturaux
Soit un bâtiment R+2 :
→ Les étages sont à usage habitation
→ Les planchers sont en corps creux
→ La hauteur sous plafond est 3m
4
GC2 B.A 2019/2020
5
GC2 B.A 2019/2020
II- Le Prédimensionnement :
1- Plancher
2- Poutre
• PoutreA12 :
h=3.3/10 = 0.36 ➔ h = 35cm
• PoutreA13 :
h=2.8/10 = 0.28 ➔ h = 30cm
• PoutreA14 :
h=3.7 /10 = 0.37 ➔ h = 40cm
6
GC2 B.A 2019/2020
3- Plancher
La terrasse est Accessible.
Les charges permanentes appliquées sur la terrasse sont
comme suit :
→ Poids propre du plancher (en corps creux 15+5) = 280kg/m².
→ Forme de pente = 330 kg/m².
→ Etanchéité multicouche = 12 kg/m².
→ Enduit sous plafond en plâtre (1.5 cm) = 33 kg/m².
→ Mortier (5 cm) = 110 kg/m².
7
GC2 B.A 2019/2020
8
GC2 B.A 2019/2020
• Appuis de rive :
9
GC2 B.A 2019/2020
10
GC2 B.A 2019/2020
11
GC2 B.A 2019/2020
2- Moment au travée
Travée 1 :
Mw = 0
12
GC2 B.A 2019/2020
Mw = 0
Travée 2 :
13
GC2 B.A 2019/2020
Travée 3 :
14
GC2 B.A 2019/2020
Me = 0
Mw = 0
15
GC2 B.A 2019/2020
Recapitulative:
4- Ferraillage
16
GC2 B.A 2019/2020
ELU
• P1 = 1.35G1 + 1.5Q1
G1 = ƿ*b*h = 0.25*0.25*2.5 = 0.15 t/m
P2 = 2.26 t/m
• P3 = 1.35G3 + 1.5Q3
G3 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.3*2.5 = 0.18 t/m
P3 = 0.4 t/m
17
GC2 B.A 2019/2020
• P4 = 1.35G4 + 1.5Q4
G4 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.35*2.5 + 0.77*(3.2+4.5/2) = 3.18 t/m
P4 = 5.14 t/m
Nu = 13.10 t
ELS
• P1 = G1 + Q1
G1 = ƿ*b*h = 0.25*0.25*2.5 = 0.15 t/m
P2 = 1.65 t/m
• P3 = G3 + Q3
G3 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.3*2.5 = 0.18 t/m
P3 = 0.28 t/m
• P4 = G4 + Q4
G4 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.35*2.5 + 0.77*(3.2+4.5/2) = 3.18 t/m
P4 = 3.75 t/m
18
GC2 B.A 2019/2020
Ns = 9.52 t
Au niveau de l’étage :
ELU
• P1 = 1.35G1 + 1.5Q1
G1 = ƿ*b*h = 0.25*0.25*2.5 = 0.15 t/m
P2 = 1.95 t/m
• P3 = 1.35G3 + 1.5Q3
G3 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.3*2.5 = 0.18 t/m
P3 = 0.4 t/m
• P4 = 1.35G4 + 1.5Q4
G4 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.35*2.5 + 0.6*(3.2+4.5/2) = 2.52 t/m
Nu = 11.46 t
19
GC2 B.A 2019/2020
ELS
• P1 = G1 + Q1
G1 = ƿ*b*h = 0.25*0.25*2.5 = 0.15 t/m
P2 = 1.42 t/m
• P3 = G3 + Q3
G3 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.3*2.5 = 0.18 t/m
P3 = 0.28 t/m
• P4 = G4 + Q4
G4 = ƿ*b*h + Gt*(lx+ly/2) = 0.25*0.35*2.5 + 0.6*(3.2+4.5/2) = 2.52 t/m
P4 = 3.19 t/m
20
GC2 B.A 2019/2020
Nu(total) = 34.9 t
Ns(total) = Nst + Nse + 0.9*Nse = 9.52 + 8.28 + 0.9*8.28
Ns(total) = 25.25 t
2- Dimensionnement du poteau
a = 25 cm b=?
ʎ= 29.06 ≤ 50
Br = 0.02 m2
Br=(a-0,02)(b-0,02) = 0.02 ➔ b = 25 cm
Donc Br = 0.05 m2
21
GC2 B.A 2019/2020
• Espacement :
St < 18 cm
• Recouvrement :
R > 0.6*50*1.2
R > 36 cm
Str < 18 cm
• Enrobage :
C > 1.2 cm
3T8
a = 25 cm
22
GC2 B.A 2019/2020
23
GC2 B.A 2019/2020
2- Ferraillage
Nappe supérieure // A :
ElS
Elu
24