RDJ MS 06 M 56
Type doc.: Dérivé de: Dérivé de: Echelle Format Feuille: Suit F. De
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCES
3.0 RESPONSIBILITIES
4.0 GENERAL
6.0 PREHEATING
7.0 ATTACHEMENTS
1.0 SCOPE
This procedure applies to minimum requirement for Post Weld Heat Treatment of carbon
steel and alloy steel (P-Nos. 1, 4, 5A and 15E) piping by means of electric resistance heating
system to release weld stress for RDPP Project
2.0 REFERENCE
3.0 RESPONSIBILITY
His responsibility will include all aspects of general piping arrangement, piping layout,
heat treatment and piping materials.
3.4 QA/QC Manager
The QA/QC Manager shall carry out inspection functions responsible according to
procedure.
He shall satisfy himself that all heat treating operations required have been correctly
performed.
3.5 PWHT Operator
Personnel will be involved in carrying out heat treatment job based on qualification and
job requirement. The PWHT Operator shall be responsible for identifying the necessity
of personnel involved in activities influencing quality.
4.0 GENERAL
4.1 Definition
PWHT Post-Weld Heat Treatment
MS Method Statement
WPS Welding Procedure Specification
ASME American Society of Mechanical Engineer
QA/QC Quality Assurance/Quality Control
DWR Daily Welding Report
NDE Non Destructive Examination
C/S Carbon Steel
A/S Alloy Steel
S/S Stainless Steel
FCR Field Change Request
4.2.1 Heat treatment and ancillary equipment to be used include the following:
Power control equipment – Transformer
Heating elements
Ancillary equipment – meters, testers
Thermal insulation
Projet RAS DJINET 1131,1 MW-Site N°. Client Rev Feuille De
4.2.2 Manpower
PWHT Technician
Helper
Tack welder
Safety Officer
Rigger
5.0 Preheating
Minimum gradient control band(GCB) width beyond heated band width =4 x √Rt]
3T ≤ W1 3T ≤ W1 Width of heated zone
W2 W2
Min.insulation width (shall be covered heating elements fully)
W1 = Heated Band Width in mm
W2 = Insulation Width in mm
T = Wall Thickness in mm
Fig. 1 MINIMUM HEATED BAND WIDTH AND MINIMUM INSULATION
WIDTH
Thermocouple must be attached within 25mm from weld joint of Mat-Type Heater
Attachment points on the weld reinforcement shall be dressed by light grinding of the
surface to allow good thermocouple contact.
5.3.2 Pipe Diameter above 6 inch to 12 inch (Top and Bottom side or Left and Right
Side)
Projet RAS DJINET 1131,1 MW-Site N°. Client Rev Feuille De
6.3.4 Pipe Diameter equal and less than 2 inch (Elbow & Tee)
6.4.4 For weld in which the PWHT temperature has dropped below the minimum
holding temperature without exceeding the specified cooling rate, actions shall be
initiated to restart the heat treatment as soon as possible.
6.4.5 The weldment shall be reheated at a rate not to exceed that specified by the
code or specification and the holding temperature re-established and kept for the
entire holding time.
6.4.6 Interrupted PWHT shall be noted and explained on the charts and records.
6.4.7 The weldment shall be held at the following temperature range for the period of
time specified in the attached table.
Refer to table PWHT & Pre-Heat Requirement (By ASME B31.1 Table 132)
(Attachment #1).
6.4.8 During the holding period, holding temperature shall be within the temperature
range required throughout the portion of the work piece being heated.
6.4.9 Cooling to 315°C shall be performed at a controlled rate which shall not exceed
the values indicated for heating.
6.4.10 From 315°C, the work piece may be cooled in still air (ATM).
6.6 Documentation
6.6.1 The PWHT temperature chart shall be identified by using the stamp
(Attachment #3), and all PWHT records shall be retained until the project is
complete and then shall become part of the quality assurance records.
6.6.2 PWHT records shall be identified by project name, unit number, line number,
weld number, location & number of thermocouples (demonstrated by a
sketch), time and date of starting, signature of operator and verification of QC
inspector.
6.6.3 After verifying that PWHT operations have been satisfactorily completed, the
Projet RAS DJINET 1131,1 MW-Site N°. Client Rev Feuille De
QC inspector shall, on a regular basis, submit original PWHT Chart and Heat
Treatment Plan/Record to contractor’s welding inspector for review.
6.6.4
Projet RAS DJINET 1131,1 MW-Site N°. Client Rev Feuille De
POWER
Heating Element
Temperature
Recorder
Thermocouple
“K” type (chromel / alume )
Temperature
Recorder Chart
7.0 ATTACHMENT
Attachment 6. Post Weld Heat Treatment Record (FORM NO. RDJ MS 06 M 56-06)
Projet RAS DJINET 1131,1 MW-Site N°. Client Rev Feuille De
ATTACHMENT.01
Holding
Holding Time Based on Nominal Thickness
S/N P-No. Items Temp. Thickness Method
Range(℃)
Up to 2"(51mm) Over 2"(50mm)
1Hr/Inch(25mm), 2Hr Plus 15min for each Electric resistance elements
PWHT 600~650℃ T>19.0mm
Minimum 15min additional Inch Over 2" with insulation applied
1 1 Min.80℃ Preheat to be applied by gas
Ambient
Pre-heat If, Carbon content>0.3% - - torch for Ø ≤ 4" and electrical
(≥10℃)
& Nominal THK>25.0mm pad for Ø > 4"
1Hr/Inch(25mm), 2Hr Plus 15min for each Electric resistance elements
PWHT 650~700℃ Nominal THK>13.0mm
Minimum 15min additional Inch Over 2" with insulation applied
2 4 Preheat to be applied by gas
Pre-heat Min.120℃ All Materials - - torch for Ø ≤ 4" and electrical
pad for Ø > 4"
1Hr/Inch(25mm), 2Hr Plus 15min for each Electric resistance elements
PWHT 700~760℃ Nominal THK>13.0mm
Minimum 15min additional Inch Over 2" with insulation applied
3 5A Preheat to be applied by gas
Pre-heat Min.200℃ All Materials - - torch for Ø ≤ 4" and electrical
pad for Ø > 4"
1Hr/Inch(25mm), 2Hr Plus 15min for each
PWHT 730~780 All Materials Electric resistance elements
4 15E Minimum 15min additional Inch Over 2"
with insulation applied
Pre-heat Min.200℃ All Materials - -
Note:
1. For A 106B,A335-P11, Preheating(80℃ and 120℃) by means of Heating Torch and keep monitored temperature with Temp-stick.
2. For A335-P91, RT shall carry out after all the activities (Preheat → Welding → PWHT → RT)
3. When any other items not stated following is found during the pre-heat or PWHT, It is to be carried out in accordance with Standard (ASME B31.1)
Holding
Holding Time Based on Nominal Thickness
S/N P-No. Items Temp. Thickness Method
Range(℃) Up to 2"(51mm) Over 2"(50mm)
1Hr/Inch(25mm), 2Hr Plus 15min for each Electric resistance elements
PWHT Min.595℃ T>19.0mm
Minimum 15min additional Inch Over 2" with insulation applied
1 1 Min.80℃ Preheat to be applied by gas
Ambient
Pre-heat If, Carbon content>0.3% - - torch for Ø ≤ 4" and electrical
(≥10℃)
& Nominal THK>25.0mm pad for Ø > 4"
1Hr/Inch(25mm), 2Hr Plus 15min for each Electric resistance elements
PWHT Min.650℃ Nominal THK>13.0mm
Minimum 15min additional Inch Over 2" with insulation applied
2 4 Preheat to be applied by gas
Pre-heat Min.120℃ All Materials - - torch for Ø ≤ 4" and electrical
pad for Ø > 4"
1Hr/Inch(25mm), 2Hr Plus 15min for each Electric resistance elements
PWHT Min.675℃ Nominal THK>13.0mm
Minimum 15min additional Inch Over 2" with insulation applied
3 5A Preheat to be applied by gas
Pre-heat Min.200℃ All Materials - - torch for Ø ≤ 4" and electrical
pad for Ø > 4"
1Hr/Inch(25mm), 2Hr Plus 15min for each
PWHT 730~780 All Materials Electric resistance elements
4 15E Minimum 15min additional Inch Over 2"
with insulation applied
Pre-heat Min.200℃ All Materials - -
Note:
1. For A 106B,A335-P11, Preheating(80℃ and 120℃) by means of Heating Torch and keep monitored temperature with Temp-stick.
2. For A335-P91, RT Shall carry out after all the activities(Preheat→Welding→PWHT→RT)
3. When any other items not stated following is found during the pre-heat or PWHT, It is to be carried out in accordance with Standard (ASME Sec.I)
ATTACHMENT.02
HEATING RATE
Max. 315℃ / hr COOLING RATE
730~780 Max. 315℃ / hr
HOLDING TEMP
300~350℃
2Hr
ATTACHMENT.03
ATTACHMENT.04
ATTACHMENT 05
PRE-HEATING RECORD
PROJECT: RAS DJINET POWER PLANT PROJECT
(RDPP)
ATTACHMENT 06
PWHT RECORD
PROJECT: RAS DJINET POWER PLANT PROJECT
(RDPP)