Vous êtes sur la page 1sur 9

646

NOTE / NOTE

Parameters affecting the thickness of bentonite


cake in cutoff wall construction: case study and
physical modeling
Abbas Soroush and Mohammad Soroush

Abstract: Concrete cutoff walls are usually constructed using a panel-by-panel technique in which primary panels are
constructed with space between them and then secondary panels are constructed and inserted in the spaces. A small
thickness of residual bentonite cake from the slurry used during excavation usually remains in the construction joints
between adjacent primary and secondary panels. The thickness of such bentonite-filled joints should be minimized in
terms of the performance of the cutoff wall in controlling seepage. This research experimentally evaluated the effects
of a number of design and construction parameters on the thickness of the bentonite cake using data from a case study
(the cutoff wall of Karkheh Dam). A physical model test was developed and a number of tests were conducted. The
test results showed that parameters such as age of the primary panels, cement content of the slurry, quantity of addi-
tives in the slurry, and circulation versus noncirculation of the slurry are responsible for the thickness of the bentonite
cake. The results are presented and analyzed.
Key words: cutoff wall, plastic concrete, bentonite slurry, bentonite cake, physical model.
Résumé : Les parafouilles de béton sont habituellement construites selon une technique panneau-par-panneau. D’après
cette technique, des panneaux primaires sont d’abord construits avec assez d’espace entre eux. Par la suite, les pan-
neaux secondaires sont exécutés dans ces espaces. Habituellement, une mince couche de bentonite résiduelle provenant
de la boue utilisée durant l’excavation forme une croûte qui reste coincée dans les joints de construction entre les pan-
neaux primaires et secondaires adjacents. Quant à la performance de la parafouille pour le contrôle de l’infiltration,
l’épaisseur de ces joints remplis de bentonite devrait être minimisée. Dans la présente recherche, en utilisant les don-
nées d’une étude de cas (la parafouille du projet de barrage de Karkheh), on a évalué expérimentalement les effets
d’un certain nombre de paramètres de conception et de construction sur l’épaisseur de cette croûte. Dans ce but, on a
développé un essai sur modèle physique et réalisé un certain nombre d’essais. Les résultats des essais montrent que les
paramètres tels que l’âge des panneaux primaires, la teneur en ciment de la boue, la quantité d’additifs dans la boue, la
circulation versus non circulation de la boue, etc. sont responsables de l’épaisseur de la croûte de bentonite. On pré-
sente et analyse ces résultats dans cet article.

Mots clés : parafouille, béton plastique, boue de bentonite, croûte de bentonite, modèle physique.

[Traduit par la Rédaction] Soroush and Soroush 654

Introduction develop a lateral support pressure against any potential in-


stability of the excavated walls, produce a thin concentrated
Bentonite slurry (i.e., a suspension of colloidal particles in cake on the walls of the excavation to minimize seepage of
water) has been used in a wide variety of geotechnical engi- groundwater into the excavated area, and facilitate extraction
neering projects for many years. There are three main func- and removal of excavated materials (Xanthakos 1979). In
tions of the bentonite slurry in an excavation assignment: terms of minimizing seepage, a thick cake might be desir-
able. In some cases in geotechnical engineering projects,
Received 6 December 2002. Accepted 30 August 2004. however, thick, stiff bentonite cakes may have adverse ef-
Published on the NRC Research Press Web site at fects, for example in the case of the construction of a cutoff
http://cgj.nrc.ca on 20 May 2005.
wall.
A. Soroush.1 Civil and Environmental Engineering Figure 1 shows how colloidal slurry penetrates into a po-
Department, Amirkabir University of Technology (Tehran rous granular medium. The slurry enters the pores due to a
Polytechnic), Tehran, Iran. pressure difference and during this process groups of solid
M. Soroush. Iran Water and Power Resources Development particles begin to occupy the void space between soil grains
Company (IWPC), Tehran, Iran.
(Fig. 1a). The slurry continues to infiltrate as more solid par-
1
Corresponding author (e-mail: soroush@aut.ac.ir). ticles accumulate in the pores, and the system then forms a

Can. Geotech. J. 42: 646–654 (2005) doi: 10.1139/T04-090 © 2005 NRC Canada
Soroush and Soroush 647

Fig. 1. Formation of filter cake: (a) deposition of colloid fraction in soil voids; (b) filtration of slurry; (c) formation of impermeable
film along face (after Xanthakos 1979).

tightly packed zone of gelled material, commonly called fil- Fig. 2. Plan view of secondary panel (S) between two primary
ter cake (Fig. 1b). The cake is soon covered by a thin layer panels (P) with overcut fraction. If depth < 40 m, overlap =
of bentonite particles, called a protective film or bentonite 25 cm; if 40 < depth < 50 m, overlap = 30 cm; if 50 < depth <
cake (Fig. 1c); at this stage the barrier is fairly impermeable 70 m, overlap = 35 cm; if depth > 70 m, overlap = 40 cm.
and resists further penetration (Xanthakos 1979).
This paper presents the findings of a study on the effects
of design and construction parameters on the thickness of
bentonite cake. A physical-testing model was used to simu-
late most conditions encountered with a prototype. The pro-
totype is the construction of the plastic concrete cutoff wall
in the foundation of Karkheh Dam in southwest Iran. The
paper introduces the parameters affecting the cake thickness,
describes the model test and testing procedure, and presents In the overcutting method, fractions of the two adjacent
results of the tests and the analyses. The results show the ef- primary panels are excavated and removed during excavation
fect of each of the parameters on cake thickness. The next of each secondary panel to (i) counteract a possible devia-
section presents the background information, including a tion in the direction of the wall axis at greater depths, where
summary of the general procedures of cutoff wall construc- there may be discontinuities between adjacent panels; and
tion and the characteristics of Karkheh Dam and its cutoff (ii) provide a tight construction joint between primary and
wall, which directed the authors to this research. secondary panels. The length of the overcut fraction depends
on the panel depth and may range from 25 to 40 cm; the
deeper the panel, the greater the overcut fraction. Figure 2
Research background shows a schematic plan view of a secondary panel with
overcut fractions between two primary panels.
Cutoff wall construction procedure Bentonite slurry is used during both the excavation and
Cutoff walls (COW) for controlling seepage can be made concreting of the trenches of the panels. Some additives may
of different materials and with different construction tech- be used to control viscosity and pH of the slurry. In general,
niques. These include slurry walls (i.e., mixture of water, a cutter machine excavates the trenches; however, the upper
bentonite, and in situ excavated materials), concrete walls, 3 m should be excavated by a backhoe. This preexcavation is
and plastic concrete walls. Plastic concrete is a special con- a prerequisite for the embedment of the cutter in the ground.
crete containing bentonite, which makes the concrete more Figure 3 illustrates schematically the insertion of a second-
deformable and weaker than ordinary concrete. While a ary panel between two primary panels.
slurry wall may be constructed in a continuous fashion with In general, the steps involved during the construction of a
no joints along the wall, concrete and plastic concrete COWs plastic concrete panel of a COW can be summarized as fol-
are usually constructed using a panel-by-panel technique lows:
(ICOLD 1985). An inherent feature of this technique is a (1) A trench is excavated by a cutter machine (or backhoe)
construction joint between every two successive panels. when bentonite slurry is used; this slurry is called a
With the panel-by-panel technique, a number of primary working slurry.
panels, each a few metres wide and with space between (2) For secondary panels, the trench walls are brushed using
them, are constructed. After a few days, secondary panels special brushes installed on the cutter frame to try to re-
are inserted between the primary panels. Since the COW move pasty bentonite cakes adhered to the sides of the
should be practically water-tight against excessive seepage, a adjacent primary panels. During the brushing, the trench
proper contact between the adjacent primary and secondary is washed with fresh slurry, which replaces the working
panels should be provided. There are a number of methods slurry.
for providing this contact (ICOLD 1985), one of which is (3) Plastic concrete is poured into the trench using a tremie
overcutting. pipe, which fills the trench by gradually moving up

© 2005 NRC Canada


648 Can. Geotech. J. Vol. 42, 2005

Fig. 3. Execution of a secondary panel (S) between two adjacent Table 1. Characteristics of Karkheh Dam.
primary panels (P).
Dam body
Maximum height (m) 127
Crest length (m) 3 030
Crest width (m) 12
Volume (m3 ×106) 32
Reservoir
Operational volume (m3 ×106) 5 600
Gross volume (m3 ×106) 7 800
Spillway (gated chute spillway) 18 395
discharge capacity (m3/s)
Diversion system (culvert with four 3 680
openings) capacity (m3/s)
Powerhouse (surface power house) 400
capacity (MW)
from the bottom of the trench. The period between the
termination of the trench excavation and the commence-
ment of the concreting should be minimized to prevent dam height, for different sections of the dam; however, this
formation of thick bentonite cakes on the walls of the thickness is constant with depth. The top of the COW is em-
trench. bedded in the dam core, with an embedment height ranging
Working and fresh slurries are usually quality controlled from 2 to 8 m for different sections depending on the height
in the laboratory for a number of specifications, including of the dam. Figure 6 shows a longitudinal section of the
pH, density, viscosity, filtration, and cake thickness. COW.
Tables 2 and 3 present the mix design and specifications,
Case study respectively, of the plastic concrete of the COW. The specifi-
cations of the fresh and working slurry used in the secondary
General characteristics
panels are summarized in Table 4; in general, the bentonite
The Karkheh Dam was constructed on the Karkheh River
content of the fresh slurry was about 50 kg/m3.
in the Province of Khoozestan, Iran. The Karkheh River,
which is the third largest river in Iran in terms of discharge, Joints between panels
is fed by a catchment area of about 50 000 km2. The river After the construction of a number of panels of the COW,
originates from the South Flank of the Zagross Mountain residual cakes of bentonite were observed in joints between
Range in the western and northwestern parts of Iran, flows some of the primary and secondary panels. The cakes had
about 900 km, and then terminates in Hoorolazim, a large adhered so strongly to the side walls of some of the primary
swamp at the border with Iraq. panels that they had not been removed even by (i) washing
The Karkheh Dam was constructed to (i) provide water the secondary trenches with fresh slurry prior to the concret-
for irrigation, (ii) produce electricity, and (iii) control floods. ing, (ii) brushing the side walls of the adjacent primary pan-
Construction was started in 1994 and finished in 2000. The els, and (iii) upward movement of the fresh plastic concrete
dam is an earth-fill dam with a central core. Table 1 summa- during concreting. The thickness of the cake was almost uni-
rizes some characteristics of the Karkheh Dam project, in- form across the wall, i.e., in plan view. Figure 7 shows
cluding the dam dimensions, the expected capacity, and the a simplistic, schematic three-dimensional view of these
size of the reservoir. bentonite-filled joints. The joints observed between the pan-
Figures 4 and 5 show the layout and a typical cross sec- els could be divided into two general categories, namely up-
tion of the dam, respectively. Materials for the dam core are per joints and lower joints. Some observations on the joints
mixtures of 60% clay (CL) and 40% gravelly clay (GC). The are given in the following sections.
shell material is a mixture of sand and gravel. The upstream
surface slope is 2.0 (H) to 1.0 (V), and the average down- Upper joints
stream surface slope is about 1.8 (H) to 1.0 (V), with a berm The upper joints were observed primarily from the surface
approximately at mid-height of the dam. The dam founda- after removal of the guide walls. To detect the extent of
tion comprises conglomerate masses intercalated by layers these joints with depth, the ground immediately upstream of
of mudstone (Fig. 5). Whereas the conglomerate is very non- the joints was excavated to produce observation wells. The
homogeneous and fairly permeable, the mudstones are ho- wells were later filled with plastic concrete. The upper joints
mogeneous and almost impervious. had a maximum depth of about 6 m (although in a few loca-
A plastic concrete COW was constructed to control seep- tions up to 12 m) and a maximum thickness of a few centi-
age in the foundation. The panel-by-panel technique with the metres. In the first 3 m, which were pre-excavated by a
overcutting method and the procedure described earlier in backhoe, the joints were thicker and contained pieces of
the paper were employed during the construction. The COW, plastic concrete in the matrix of bentonite cake. As shown in
with a maximum depth of around 80 m, is extended over al- Fig. 8, these joints were usually diagonal toward the adja-
most the whole length of the dam (2940 m). The thickness cent primary panels because the backhoe produces inclined
of the COW varies between 0.6 and 1.0 m, depending on the side walls (the sides of the adjacent primary panels) during

© 2005 NRC Canada


Soroush and Soroush 649

Fig. 4. Layout of the Karkheh Dam project. U/S, upstream; D/S, downstream.

Fig. 5. Cross section of Karkheh Dam. Vertical scale in metres.

Fig. 6. Longitudinal section of the cutoff wall of Karkheh Dam. Horizontal distances in metres.

© 2005 NRC Canada


650 Can. Geotech. J. Vol. 42, 2005

Table 2. Plastic concrete mix design for the no unexpected seepage has developed. In terms of the qual-
cutoff wall of Karkheh Dam. ity and filling material of the joints, we provide information
about two projects, namely the Al-Wahdedh Dam and the
Cement (kg/m3) 200
New Ensa Dam, both in Morocco (Soroush 1999a).
Bentonite (kg/m3) 37.5
A total of 37 joints were found in the Al-Wahdeh Dam, of
Aggregates (kg/m3) 1500
which six were continuous from the upstream to the down-
Ratio of water to cement 1.5–1.7
stream. The maximum depth at which such joints were
found was 6 m. The joints consisted of bentonite mixed with
Table 3. Specifications of the plastic concrete of the cutoff cement from overcutting of the primary panels (Soroush
wall of Karkheh Dam. 1999a). In the New Ensa Dam, bentonite-filled joints were
found between the panels of the COW, with the joint thick-
Plastic concrete (28 days) ness varying from 50 mm at the surface to 15 mm at a depth
(USC)min (kg/cm2) 30 of 3.90 m, and cements were found in the filling materials
E (kg/cm2, ×103) 20–50 (Soroush 1999a). The cutoff walls in both dams have not ex-
kmax (cm/s) 10–7 perienced any deficiencies, including erosion of the joint
materials (Soroush 1999a).
Fresh plastic concrete
Slump (cm) 18–22
Pouring temperature (°C) <30 Physical modeling
Cement Type V, low alkaline Observations and experience from the construction of the
Bentonite Sodium montmorillonite COW in the Karkheh Dam showed us that it is almost im-
Note: E, elastic modulus; k, permeability; UCS, unconfined possible to completely remove bentonite cakes from the side
compressive strength. walls of primary panels. The application of measures such as
washing the trenches with fresh slurry, brushing the side
walls of the panels, and concreting into the trenches could
the excavation. These upper joints were relatively thick be- have removed only a portion of the cakes at best. Therefore,
cause it is less likely that the bentonite cakes would have we concentrated on finding procedures and parameters that
been removed from these inclined walls during concreting could produce a thinner bentonite cake without jeopardizing
than from the vertical side walls produced by the cutter. the trench stability and without allowing the ambient water
Lower joints to enter the trench.
At the time of the excavation of the three power tunnels in
the left abutment of the dam, panels of the COW in this area Testing parameters
became fully exposed. This provided an excellent opportu- On the basis of the observations made during construction
nity to detect, and in fact observe, the quality and size of of the COW at the Karkheh Dam and conclusions made by
some joints to a depth of about 35 m below the top of the the international expert panel referred to earlier, the follow-
panels. The COW in this section of the dam was 73 m deep ing design and construction parameters and factors were
and continued down into mudstone layer 2. Six joints be- found to be responsible for the thickness of the bentonite
tween the adjacent primary and secondary panels, with two cakes: (1) age of the plastic concrete of the primary panels;
joints in each power tunnel, were evident in this area. Four (2) cement content of the slurry; (3) sodium bicarbonate, as
of the joints had thicknesses of less than 7 mm; however, an additive, added to the slurry; (4) bentonite concentration
two joints had a maximum thickness of about 15 mm. The of the slurry; (5) circulation versus noncirculation of the
joints were filled with flocculated and compacted bentonite slurry; (6) working slurry versus fresh slurry; (7) dry soil up-
slurry and extended from the upstream to the downstream of stream and downstream from the panel; (8) workability of
the panels. It should be noted that the upper joints observed the plastic concrete of the secondary panel; and (9) high fil-
in this area were a maximum of 5 m deep. tration of the slurry, high hydrostatic pressures, and suction
The significance of seepage control in the dam foundation forces.
led all sides of the project organization to arrange an interna- To experimentally evaluate the effects of these parameters
tional expert panel to review the bentonite-filled joint on the thickness of bentonite cakes adhering to the side
phenomenon and discuss its effects on seepage in the foun- walls of the primary panels, we tried to develop a physical
dation. More details of this case study and a summary of the model for simulating the general procedures of the insertion
opinions of the expert panel are given by Soroush (1999b). of a secondary panel between two successive primary panels
(see the section titled Cutoff wall construction procedure).
Joint phenomena in other projects During the development of the physical model, we realized
that it is very difficult to account for the effects of high fil-
Cutoff walls have been used to control seepage in a num- tration of the slurry, high hydrostatic pressures, and suction
ber of hydropower and waste-containment projects world- forces (parameter 9) and therefore did not consider them in
wide. Table 5 summarizes the characteristics of a number of the model development. Because of their significance, how-
cutoff walls in various countries. As indicated, the over- ever, a brief discussion is provided here. Parameters 1–8 are
cutting technique has been used for joint construction described during presentation of the tests results.
between the adjacent panels. Accordingly, the joint perfor- The process of high filtration of the slurry into the sur-
mance in all of these cutoff walls has been satisfactory and rounding dry ground and the unsaturated adjacent primary

© 2005 NRC Canada


Soroush and Soroush 651

Table 4. Typical specifications for fresh and working slurry in prototype practice.
Density Viscosity Sand content Filtration Cake thickness
pH (g/cm3) (s) (%) (cm3) (mm)
Fresh slurry 7–10 1.015 32–50 0 <30 <3
During excavation of secondary panels 7–12 1.200 32–60 <6 <50 <6
During concreting in secondary panels 7–12 1.100 32–50 <4 <30 <3

Fig. 7. Schematic three-dimensional view of joints between the Characteristics of the physical model
primary and secondary panels. The physical model consisted basically of a cubical steel
container with dimensions 130 cm × 100 cm × 30 cm (l ×
h × w), as shown schematically in Fig. 9. The front side of
the container was made of glass to provide a view into the
container during the tests. A hole was included in the floor
for evacuating slurry at the end of the tests. Two 15 cm wide
plastic concrete panels were constructed in the two sides of
the container to represent the prototype. To evacuate the
plastic concrete when required, two pull-out gates were in-
cluded in the side walls of the container. The corner joints of
the container were sealed to prevent loss of the slurry during
the tests.

Testing procedure
We developed a test program to examine the effects of
parameters 1–8 on the thickness of the bentonite cake. The
tests were carried out in the model container, which was lo-
cated at Karkheh Dam. The test site was located at the dam
to give the same temperature and humidity environment and
to ensure that sufficient test materials, including plastic con-
crete, fresh slurry, and working slurry, were readily avail-
able. The Karkheh site is located in a warm area with
Fig. 8. Schematic section of the upper joints between the pri- average monthly temperatures ranging from 11 °C (January)
mary (P) and secondary (S) panels. to 36 °C (August) and an average annual humidity of about
46%. The tests were conducted during the period May to
August, with an average temperature of 29 °C.
Generally, the same procedure used in the construction of
the prototype was followed at the test site. However, the ef-
fects of hydrostatic pressure of the slurry on the cakes, suc-
tion, and surface forces could not be simulated because of
the comparatively small dimensions of the model test con-
tainer and the simplistic boundary conditions. Therefore, the
physical tests modeled only the upper joints, and the conclu-
panels, with reference to the filter cake theory (Fig. 1), can sions, as far as an absolute value of the cake thickness is
be described as follows. In most sections of the foundation concerned, may not apply to the lower joints. In contrast
and abutments of the dam, the COW has been constructed with the prototype conditions, all of the tests were carried
above the groundwater table and in a dry condition. In these out in no-drainage conditions, and therefore, in general, cake
sections, a substantial amount of water from the plastic con- formation could have been limited by lack of drainage.
crete of the primary panels and from the slurry in the trench As mentioned previously, two 15 cm wide plastic concrete
of the secondary panel has been absorbed by the unsaturated panels, modeling the primary panels, were constructed in the
surrounding ground. This process results in high filtration of sides of the container. To comply with the prototype prac-
the slurry and therefore thickening of the bentonite cakes. tice, the plastic concrete was cured dry prior to filling the
Another consequence of this condition is high differential test tank with slurry. Depending on the test, fresh slurry or
hydrostatic pressure (especially at deeper elevations) from working slurry was poured into the space between the two
the slurry in the trench of the secondary panel against the primary panels and the thickness of the cakes was carefully
cake adhered to the overcut side walls of the primary panels. measured at different time intervals (usually every 2 h). To
This high differential pressure induces high gradients, result- facilitate these measurements, the level of the slurry in the
ing in higher rates of filtration. In addition, since the rock container was gradually lowered by evacuating it through the
formation consists of pervious but fine-grained unsaturated hole in the floor. To control the quality and characteristics of
materials, suction forces may have developed in the primary the slurry, density, Marsh viscosity, pH, and filtration testing
panels, which results in attracting the bentonite cakes ad- were carried out at the beginning, during, and at the end of
hered to the side walls of theses panels. each of the tests. Table 6 summarizes typical values of these

© 2005 NRC Canada


652 Can. Geotech. J. Vol. 42, 2005

performance
Fig. 9. Schematic perspective of the model test container.

Joint

OK
OK
OK

OK
OK
OK
OK
OK
OK
height (m)
Approx.
storage

15
14
35

45
30
20
30
45

45

into rock socket (granite)


Sand, clay, large boulders

Sand, gravel; key 1.5 m


Silty sand, boulders
Ground condition

Sand, gravel, silt


Existing dam
Gravel, marl
Sandstone
Sandstone

Alluvium
construction
Overcutting
Overcutting
Overcutting

Overcutting
Overcutting
Overcutting
Overcutting
Overcutting
Overcutting
Overcutting

Overcutting
Joint

parameters for the fresh and working slurry. The test results,
Cement–bentonite cutoff

analysis of the test results, and specifications of the tests are


Cutoff plastic concrete

given in the next section.


Table 5. Characteristics of a number of cutoff walls (H.-J. Bliss, personal communication, 1998).

Concrete cutoff

Results and analysis


Soil bentonite

The results of the tests performed to study the effects of


Wall type

parameters 1–8 on the thickness of the bentonite cake are


Cutoff
Cutoff
Cutoff

Cutoff
Cutoff
Cutoff

Cutoff

presented in this section. The results are shown in terms of


variations of thickness of the bentonite cake adhering to the
side walls of the primary panels versus time. The results are
8 500

7 500

3 200

9 000
1 760
12 500
19 000

19 050

11 500

15 650

22 760

analyzed and conclusions are made for each of the tests.


(mm)
Wall
area

(1) Age of the plastic concrete of the primary panels


Four tests were carried out with primary panels that were
depth
Max.

16 h, 24 h, 42 h, and 4 days old. Figure 10 presents the re-


(m)
30
40
10

40
21
24
51
50
46
41

42

sults of these tests; as indicated at any time after pouring the


slurry between the two primary panels, the cake thickness
Thickness

decreases as the age of the primary panel increases. A possi-


(mm)
600
600
600

600
600
600
900

900

800
1000
1000

ble explanation for this result is that the fresh (i.e., younger)
plastic concretes may need more water for their cement
hydration. Therefore, they may absorb more water from the
United Arab
Emirates

slurry, leading to a thicker cake. Another result of these tests


Germany
Germany
Country

and all of the other tests, as expected and as observed, was


Croatia
Austria
Japan

Spain

that the cake thickness increased when the slurry remained


US

US

US

US

for a longer period of time in the trench.


Shwaib Dam diaphragm

(2) Cement content of the slurry


Eastside Dam reservoir

Hodges Village Dam

During construction of the prototype secondary panels,


Meeks Cabin Dam

the slurry was contaminated by cement from the overcut


Brombachsperre

Shiokawa Dam

Ahrental dump

fraction of the adjacent primary panels. To examine the ef-


Peruca Dam
Kleine Roth

Wister Dam

fects of this cement on the bentonite cake thickness, a series


La Estance

project

of tests was performed with fresh slurry (i.e., without ce-


Project

wall

ment) and slurry with 1.7, 3.4, and 5.7 kg/m3 cement. Fig-
ure 11 shows the cake thickness versus time after pouring
the slurry for the fresh slurry and slurry with the various ce-
1985
1985
1988

1990
1990
1992
1993
1994
1997
1997

1998

ment contents. As shown, the cement content of the slurry


Year

has an increasing effect on cake thickness. Figure 11 also in-

© 2005 NRC Canada


Soroush and Soroush 653

Table 6. Typical specifications of fresh and working slurry used in the physical model
tests.
Density Viscosity Sand Filtration Cake thickness
pH (g/cm3) (s) content (%) (cm3) (mm)
Fresh slurry 8 1.025 33 0 28 1.5
Working slurry 12 1.165 37 2 45 5.3

Fig. 10. Variation in thickness of the bentonite cake versus time Fig. 12. Variation in thickness of the bentonite cake versus time
for different ages of the primary panel plastic concrete. for different sodium bicarbonate contents.

Fig. 13. Variation in thickness of the bentonite cake versus time


Fig. 11. Variation in thickness of the bentonite cake versus time for different bentonite concentrations of the slurry. B/W, kilo-
for different cement contents of the slurry. grams of bentonite per cubic metre of water.

teraction (i.e., less interaction than that of the fresh cement)


dicates that the higher the cement content of the slurry, the
with the slurry of the secondary panel.
higher the rate of increase of cake thickness with time.

(3) Sodium bicarbonate, as an additive, added to the (4) Bentonite concentration of the slurry
slurry We carried out a number of tests using a slurry with 12.5,
In the construction of the prototype cutoff wall, it was 20.0, 30.0, 40.0, 60.0, and 75.0 kg of bentonite per cubic
common to add additives to countermeasure the effect of metre of water. Figure 13 presents the results of these tests;
contamination of the slurry by cement. We examined this ef- as expected, the higher the bentonite content, the thicker the
fect by adding 4.1, 7.1, and 10.2 kg/m3 sodium bicarbonate cake adhering to the side walls of the model primary panels.
(SBC) to the slurry that had been contaminated by 6.8 kg/m3
cement. Figure 12 shows the variation of cake thickness with (5) Circulation versus noncirculation of the slurry
time for the fresh slurry, cement-contaminated slurry, and In field practice, slurry is circulated during the excavation,
cement-contaminated slurry with the various SBC contents. washing, and concreting of the trench. This is accomplished
As indicated by adding 4.1 kg/m3 SBC, the cake thickness by placing slurry from the top of the trench and evacuating it
generally decreases. For the higher SBC contents, however, from the bottom of the trench using a pump attached to the
this thickness slightly increases. This may indicate an opti- cutter. Circulation of the slurry may stop sometimes because
mal content of SBC, which was about 0.6 of the cement con- of a delay during the excavation or concreting to repair the
tent for these tests (i.e., 0.6 × 6.8 = 4.1 kg/m3). In the cutting and (or) concreting equipment. We performed a
prototype, however, this optimum ratio was lower (about number of model tests to compare the effects of circulation
0.35). The difference may be attributed to the fact that in the versus noncirculation of the slurry on the thickness of the
physical model we added fresh cement directly to the slurry. bentonite cake. Figure 14 shows that the slurry circulation
In the prototype, slurry was contaminated by cement from generally has a decreasing effect on the thickness of the
the primary panels; this cement had already activated during cake. This compares favorably with observations made dur-
concreting of the primary panels and therefore had less in- ing the prototype practice.

© 2005 NRC Canada


654 Can. Geotech. J. Vol. 42, 2005

Fig. 14. Variation in thickness of the bentonite cake versus time Fig. 15. Variation in thickness of the bentonite cake versus time
for circulation and noncirculation of the slurry. for working slurry and fresh slurry.

(6) Working slurry versus fresh slurry


In the prototype and during excavation of the trench, the concrete of the secondary panels has an important effect on
slurry mixed with the excavated materials is directed to a the removal of the bentonite cakes.
desander. The desander separates the slurry from these mate-
rials and directs it back into the trench for reuse. This is Summary and conclusions
called the working slurry. In contrast, the slurry used once
only during the trench washing and concreting is called the This paper studied a number of design and construction
fresh slurry. We repeated the model tests to evaluate the ef- parameters affecting the thickness of bentonite cake result-
fects of these two types of slurry. Figure 15 shows that the ing from slurry during the construction of cutoff walls. The
bentonite cake resulting from the working slurry is compara- background and data for this research were provided from
tively much thicker for all of the time intervals. the cutoff wall of the Karkheh Dam project as the prototype.
The study used a physical model that simulates the general
(7) Dry soil upstream and downstream from the panel procedures involved in the construction of the prototype cut-
If the surrounding ground immediately upstream and off wall. The results of the tests on the physical model
downstream from the cutoff wall trench is relatively pervi- showed that a number of design and construction parameters
ous and dry, which was the case for many sections of the influence the thickness of the bentonite cake, such as the
foundation of Karkheh Dam, it can adsorb some water from length of time the slurry remains in the excavated area, the
the slurry. This may produce a thicker cake adhering to the age of the plastic concrete of the primary panels, the cement
side walls of the trench. To study this effect, one side of the content of the slurry, and circulation versus noncirculation of
secondary trench in the model test was filled with the dry the slurry. The tests results and their analyses are presented.
materials of the foundation. We realized that at the begin-
ning the cake rapidly became thicker when some of the wa- Acknowledgements
ter from the slurry penetrated into the adjacent dry soil. The
rate of penetration decreased, however, as the cake became The authors would like to express their appreciation to the
thicker; hence, the rate of increase in the cake thickness Iran Water and Power Resources Development Company
started to decline. (IWPC) for permission to conduct this research and for the
support provided. The authors are also thankful to the
(8) Workability of the plastic concrete of the secondary IWPC, the Mahab Ghods Engineers Company (consultant),
panel and the Sepasad Engineering Company (contractor) for pro-
As mentioned with the prototype, concreting in both the viding data.
primary and secondary trenches is achieved using a tremie
pipe moving from the bottom to the top of the trench. As the References
plastic concrete substitutes for the slurry and fills up the sec-
ICOLD. 1985. Filling materials for watertight cutoff walls. Bulle-
ondary trench, it removes some gel-like parts of the cake ad-
tin 51, International Commission on Large Dams (ICOLD),
hering to the trench walls. To examine the effects of the Paris.
workability of the plastic concrete on the removal of the Soroush, M. 1999a. A physical model study on parameters affect-
cake, three model tests were carried out using models with ing bentonite slurry cake. M. Sc. thesis, Department of Civil En-
3, 4, and 6 in. diameter pipe (1 in. = 25.4 mm). The same gineering, Amirkabir University of Technology, Tehran, Iran.
plastic concrete of the prototype COW was used in these Soroush, A. 1999b. Plastic concrete cutoff wall in the Karkheh
tests. For the tests with 3 and 4 in. diameter pipes, the Dam: review of some construction aspects and a summary of
upward-moving plastic concrete in the trench was not able to opinions of expert panel. In Proceedings of the 52nd Canadian
remove the bentonite cake and gel-like parts of the cake Geotechnical Conference, Regina, Sask., 25–27 October 1999.
from the side walls of the adjacent panels because of the low Canadian Geotechnical Society, Alliston, Ont. pp. 573–583.
speed. In contrast, the plastic concrete poured with 6 in. di- Xanthakos, P.P. 1979. Slurry walls. McGraw-Hill Book Company,
ameter pipe removed a considerable thickness of the cake. New York.
This type of test confirms that the workability of the plastic

© 2005 NRC Canada

Vous aimerez peut-être aussi