Académique Documents
Professionnel Documents
Culture Documents
Inspection and Test Plan for GRP Pipe Installation & Hydro Test
RDJ ITP 06 M 51
Type doc.: Dérivé de: Dérivé de: Echelle Format Feuille: Suit F. De
3 Lamination Joint
As per MS for GRP Pipe Fit-up Inspection
Fit-up Inspection (Grinding, Installtaion & Hydro Test Report
3.1 H W R
Chamfering, Gap, Alignment check) (RDJ MS 06 M 51) RDJ MS 06 M 51-04
As per MS for GRP Pipe Visual Inspection
Visual Inspection (External, internal Installtaion & Hydro Test Report
3.2 H W Wx
Width, Thickness check) (RDJ MS 06 M 51) RDJ MS 06 M 51-06
As per MS for GRP Pipe Barcol Hardness Test
3.3 Barcol Hardness Check Installtaion & Hydro Test Report(Record) H W W
(RDJ MS 06 M 51) RDJ MS 06 M 51-03
5 Pressure Test
As per MS for GRP Pipe Piping Test Pack
5.1 Line Walkdown Installtaion & Hydro Test Punch List H W W
(RDJ MS 06 M 51) RDJ MS 06 M 51-02
As per MS for GRP Pipe Pressure Test
5.2
Pressure Test Installtaion & Hydro Test Report H W W
(RDJ MS 06 M 51) RDJ MS 06 M 51-01
Inspection Point W : Witness Point, H : Hold Point, R : Review Point, Wx : Spot Witness Point, I : Information Point
Reviewed and Accepted by Owner or his designee
Prepared by Construction Engineer :
(Name) (Date)
Form No. : RDJ CQ 032 007-01